Canvix grant accounting — budget evidence and expenditure ledger
Why this exists: the review of the pending FOSS United application flagged that commit trailers alone cannot prove hours worked or money spent, and that the thesis expects periodic check-ins and milestone/outcome-based disbursement for grants above ₹3 lakh. If the grant is approved, this ledger is how the money is accounted for. Preparing the evidence before a decision keeps the request auditable and honest. This template is unfunded application work — no grant trailer.
1. Ledger (maintained from approval, published monthly)
| Field | Where it comes from | Example row |
|---|---|---|
| Date | — | 2027-01-08 |
| Milestone | M1–M4 plan guid | m1-baseline-and-harness |
| Hours | Dated timesheet (see §2) | 21.5 h |
| Work items | Commit SHAs + issue/PR links | a1b2c3d, #92 |
| Expenses | Receipt/invoice number + vendor | INV-2027-004 · test bench RAM |
| Amount claimed | Milestone budget line | ₹0 (M1 = stipend) |
| Funding source | FOSSUnited / NLnet / unfunded | FOSSUnited M1 |
| Scope check | Confirm no overlap with the other application | distinct — evaluation harness |
Stored as research/grant-ledger.csv + monthly rendered summary in the progress report.
Rule: a row exists for every claimed hour and rupee, or it is not claimed.
2. Timesheets (the "hours" column's evidence)
- Daily log: date, milestone, hours, one-line description. Plain dated text files under
research/timesheets/YYYY-MM.md(private identifiers redacted). - Cross-check: hours claimed per month ≤ realistic capacity (~25 h/week declared in the proposal — over-claiming weeks are the first thing an auditor would test).
- Cross-reference: each work block maps to commit SHAs landing in the same window
(the repo's
Grant: FOSSUnited M#trailers tie commits to milestones).
3. Expense evidence to gather now (before approval)
| Budget line | Evidence to obtain | Status |
|---|---|---|
| Test-hardware (₹70,000) | 2–3 dated written quotations (vendor + model + price + validity), the chosen one, and a purchase decision note | To gather — quotations age out; refresh within 30 days of any disbursement |
| Evaluation/community (₹70,000) | Itemized expected costs: corpus hosting, domain/tooling, printed material for workshops | To itemize |
| Maintainer support (₹3,60,000) | The published milestone acceptance criteria in the proposal §milestones — the "unit of work" definition | Already published |
4. Double-funding boundary (the standing rule)
- Every commit carries at most one funding trailer (
Grant: FOSSUnited M#orGrant: NLnet WP#, never both). - The scope split: FOSS United = design-output correctness + evaluation + education; NLnet (pending, separate) = deployment trust, collaboration scale, mobile editing, sharing, v1.0 stabilization. Overlap candidates (e.g. test infrastructure that serves both) get an explicit scope note in the ledger when they arise.
- The ledger's "Funding source" column is the audit surface: any reviewer can diff trailers vs ledger rows.
5. Reporting cadence (matches the thesis's expectations)
- Monthly: public progress report (the M1 plan already commits to this) — milestone status, hours, spend, artifacts, deviations.
- Quarterly: one community engagement (thesis expectation: talk, blog post, or forum update — M4 commits to this).
- On deviation: a ledger note + report section — an honest miss beats a silent rebaseline.