Prerelease-to-GA Promotion Readiness Blocked Record
- Date:
2026-03-13 - Gate:
rc-to-ga-promotion-readiness - Result:
blocked
Blocking Facts
- No Pulse v6 prerelease has shipped yet.
- The repository contains accidental prerelease git tag history (
v6.0.0-rc.1), but those tags were never published and do not count as shipped prerelease lineage. - GitHub still validates
Release Dry Runworkflow dispatch inputs against the default branchmain, whose current workflow contract does not accept the governed stable rehearsal metadata envelope (promoted_from_tag,rollback_version,ga_date, andv5_eos_date). - The governed release profile in
docs/release-control/control_plane.jsoncurrently declares bothprerelease_branchandstable_branchaspulse/v6-release. - The active control-plane target is still
v6-rc-stabilization, notv6-ga-promotion. - The active local
pulse/v6-releasebranch currently reportsVERSION=6.0.0-rc.1, so the working line is still prerelease and there is not yet a governed local stable6.0.0candidate. - There is still no governed
Prerelease-to-GA Rehearsal Recordproving a successful non-publishRelease Dry Runfor the eventual stable6.0.0candidate. docs/releases/RELEASE_NOTES_v6.mdanddocs/release-control/v6/internal/V5_MAINTENANCE_SUPPORT_POLICY.mdstill leave the GA announcement dates as placeholders because no real prerelease lineage or GA-ready rehearsal has locked them yet:v6GA date placeholder:[v6-ga-date]v5end-of-support placeholder:[v5-eos-date]
- There is still no governed
Release Dry Runartifact or rehearsal record exercising stable inputs for:version=6.0.0- no governed
promoted_from_tagexists yet because no prerelease has shipped - the artifact-owned candidate stable tag for that rehearsal
- the artifact-owned promotion channel for that rehearsal
- the artifact-owned promoted prerelease tag for that rehearsal
- the artifact-owned rollback target for that stable candidate
- no exact
ga_dateis locked yet because the GA notice is still pending - no exact
v5_eos_dateis locked yet because the GA notice is still pending - an explicit
rollback_version - the exact derived rollback command that artifact will publish
Why The Gate Cannot Be Cleared Yet
The blocker is no longer missing governance text. The remaining problem is that
the control plane still treats v6 as the prerelease-stabilization line, the working
version is still prerelease (6.0.0-rc.1), and there is still no exercised
Release Dry Run record proving the eventual stable 6.0.0
candidate is ready for GA-style promotion. Until that rehearsal exists, stable
users would still be the first real cohort for the final promotion path.
Required Unblock Steps
- Promote the active target from
v6-rc-stabilizationtov6-ga-promotiononly when that change is actually intended. - Push the governed
pulse/v6-releasebranch state that is intended to become the stable6.0.0candidate, including the eventualVERSION=6.0.0change and release-control records, toorigin/pulse/v6-release. - Land the canonical
.github/workflows/release-dry-run.ymlworkflow-dispatch input contract on the default branchmainso GitHub accepts the governed stable rehearsal metadata envelope when dispatching frompulse/v6-release. - Ship the first real prerelease through the governed prerelease release path and record its exact published prerelease tag plus rollback target and exact derived rollback command.
- Run
Release Dry Runfrompulse/v6-releaseusing that published prerelease aspromoted_from_tagwith:version=6.0.0- an artifact-owned candidate stable tag matching that rehearsal
- an artifact-owned promotion channel matching that rehearsal
- an artifact-owned promoted prerelease tag matching that rehearsal
- an artifact-owned rollback target for the stable candidate
- the exact planned GA and v5 end-of-support dates for the publish notice
- an explicit
ga_datechosen for that rehearsal - an explicit stable
rollback_version - the exact derived rollback command that artifact will publish
- an explicit
v5_eos_datechosen for that rehearsal
- Capture the
rc-to-ga-rehearsal-summaryartifact and run URL. - Materialize the final rehearsal record from that artifact without hand-repairing any missing candidate tag, promoted prerelease tag, rollback target, rollback command, or GA/EOS metadata.
- Change the gate from
blockedonly if the rehearsal passes and the rollout inputs remain explicit.