Prerelease-to-GA Promotion Readiness Blocked Record

  • Date: 2026-04-04
  • Gate: rc-to-ga-promotion-readiness
  • Result: blocked

Blocking Facts

  1. The latest shipped Pulse v6 prerelease tag is v6.0.0-rc.7.
  2. That shipped prerelease tag resolves to commit 2900e41b2db95561471d17bb9f4fdf097b56b8ac.
  3. The selected remote ref origin/pulse/v6-release is still behind the current local governed branch state, so Release Dry Run would exercise stale remote control-plane metadata instead of the intended candidate.
  4. The governed release profile in docs/release-control/control_plane.json currently declares both prerelease_branch and stable_branch as pulse/v6-release.
  5. The active control-plane target is v6-ga-promotion, so stable or GA promotion is now the governed objective for Pulse v6.
  6. The active local pulse/v6-release branch currently reports VERSION=6.0.0, so a local GA candidate exists on the governed stable line.
  7. There is still no governed Prerelease-to-GA Rehearsal Record proving a successful non-publish Release Dry Run for the current 6.0.0 candidate.
  8. docs/releases/RELEASE_NOTES_v6.md and docs/release-control/v6/internal/V5_MAINTENANCE_SUPPORT_POLICY.md now carry the currently proposed exact dates for the eventual GA notice:
    • v6 GA date: 2026-07-04
    • v5 end-of-support date: 2026-10-02
  9. There is still no governed Release Dry Run artifact or rehearsal record exercising stable inputs for:
    • version=6.0.0
    • promoted_from_tag=v6.0.0-rc.7
    • the artifact-owned candidate stable tag for that rehearsal
    • the artifact-owned promotion channel for that rehearsal
    • the artifact-owned promoted prerelease tag for that rehearsal
    • the artifact-owned rollback target for that stable candidate
    • ga_date=2026-07-04
    • an explicit rollback_version
    • the exact derived rollback command that artifact will publish
    • v5_eos_date=2026-10-02

Why The Gate Cannot Be Cleared Yet

The blocker is no longer missing governance text. The remaining problem is that there is still no exercised Release Dry Run record proving the exact 6.0.0 candidate is ready for GA-style promotion. Until that rehearsal exists, stable users would still be the first real cohort for the final promotion path.

Required Unblock Steps

  1. Push the governed pulse/v6-release branch state, including the current VERSION=6.0.0 candidate and release-control records, to origin/pulse/v6-release.
  2. Run Release Dry Run from pulse/v6-release with:
    • version=6.0.0
    • promoted_from_tag=v6.0.0-rc.7
    • an artifact-owned candidate stable tag matching that rehearsal
    • an artifact-owned promotion channel matching that rehearsal
    • an artifact-owned promoted prerelease tag matching that rehearsal
    • an artifact-owned rollback target for the stable candidate
    • the exact planned GA and v5 end-of-support dates for the publish notice
    • ga_date=2026-07-04
    • an explicit stable rollback_version
    • the exact derived rollback command that artifact will publish
    • v5_eos_date=2026-10-02
  3. Capture the rc-to-ga-rehearsal-summary artifact and run URL.
  4. Materialize the final rehearsal record from that artifact without hand-repairing any missing candidate tag, promoted prerelease tag, rollback target, rollback command, or GA/EOS metadata.
  5. Change the gate from blocked only if the rehearsal passes and the rollout inputs remain explicit.