Pilot validation plan: five BIM coordinators

Status: proposed. No pilot has been run. This page contains no results, no participant quotes and no measurements. Every number below is a threshold chosen in advance, not an observation. The results template at the end is empty on purpose.

This is the plan for roadmap item 18 in the adoption priorities. It assumes the first demo from that roadmap (the find, review, approve, verify loop on the canonical fixture) works on a live Revit session. If it does not, fix that first; a pilot on a broken demo measures the bugs, not the product.

Do not schedule a session until model writes have worked once in a real Revit. An architecture review found that BridgeCommandFactory.CreateTransaction in the add-in calls itself, so every model write would crash Revit. The fix is hotfix PR #95, open and not merged when this was written. Writes are untested in a real Revit until #95 is merged, the add-in is rebuilt from it, and one real write on a throwaway copy has been tried. Tasks 2 and 3 depend on this. The proof bundle and plan_revert work (#62) and the draft-plan gate fix (#63) are merged into main; neither has been seen working against live Revit either.

What we are trying to find out

Three bets are unproven. Each could be wrong independently, so each gets its own question, its own evidence and its own kill criterion. A pilot that returns one blended "people liked it" score would hide which bet failed.

Bet Question Why it could be wrong
1. Safety Do coordinators who do not script trust approve-before-change enough to let it edit a model? They may approve without reading, refuse to approve anything, or want a stricter gate than we provide.
2. Interop Does the workflow fit the tools they already use (Navisworks, pyRevit, BIM 360 / Autodesk Construction Cloud)? They may see it as a parallel tool to carry alongside their own, or it may collide with worksharing and cloud models.
3. Client reach Would their firms and clients allow and pay for it? Individuals may like it while IT, security or the client's BIM execution plan blocks it.

The product currently covers Revit through an add-in and a local server. It does not integrate with Navisworks, pyRevit or BIM 360. Bet 2 therefore asks whether it fits alongside those tools, not whether it connects to them. What we learn there decides whether any integration work is justified, as the roadmap already says.

Who to recruit

Target: five people. Five is enough to see repeated failures, not enough to estimate rates. Report counts ("3 of 5"), never percentages.

Inclusion:

  • Works as a BIM coordinator or model manager on live projects, at least part of the week.
  • Runs model checks today, by hand or with existing tools.
  • Does not write scripts (Dynamo, Python, C#) as part of the job. Using pre-built pyRevit buttons or Dynamo players someone else made is fine and is relevant to bet 2.
  • Has Revit on a machine where a pilot add-in may be installed, or agrees to a session on a loaner machine.

Spread the five on purpose, so one kind of workplace does not decide the result:

  • at least two firms, and at most two people from any single firm;
  • at least one consultant-side and one contractor-side coordinator;
  • at least one who works on BIM 360 / ACC cloud-workshared models, and one who does not;
  • at least one who uses Navisworks for coordination routinely.

Exclusions: friends who will be kind, anyone who has seen a demo and been told what to expect, and anyone who writes scripts for their team. Record how each person was found and any prior relationship with the maintainer.

Recruiting steps:

  1. Write a short invitation that says what the session is (about two hours, on a test model, nothing from their project) and that the tool is unfinished. Do not promise features.
  2. Ask for consent to record screen and audio, to take notes, and to publish anonymised, aggregated findings. Participants may withdraw at any point and have their data deleted.
  3. Use a synthetic model only. No client data enters the session. Participants use their own Revit (version recorded) or a provided machine.
  4. Compensate participants for their time if budget allows, and say so up front. State in the report whether they were paid.
  5. Keep a screening sheet (name code, firm type, Revit version, tools used, scripting experience, cloud or local models) before any session starts.

Session format

One person at a time, about two hours (the timings below are guesses until the dry run in the checklist), moderator present. The moderator observes and does not help unless the participant is stuck for more than three minutes; every help event is logged. Order:

  1. Ten minutes: background interview and consent (interview prompts, part A).
  2. Five minutes: moderator explains only that this is an assistant that can find and fix missing parameters and asks before changing the model. Nothing about how the approval works.
  3. Task blocks, in the order set by the participant's number (below).
  4. Twenty minutes: debrief interviews (parts B to D).

Each participant does two blocks in the same session:

  • Manual block: task M, the manual baseline.
  • Tool block: task 0 (setup), then tasks 1 to 5.

Order is counterbalanced. Odd-numbered participants (P1, P3, P5) do the manual block first; even-numbered (P2, P4) do the tool block first. With five people that is three and two, so the groups are too small to compare statistically.

The manual baseline has to be measured before the participant has seen any finding from the tool, so for the manual-first group task 0 comes after task M, never before it. Task 0 ends with a correct finding on screen. If it ran first it would show the participant what is wrong with the canonical fixture, and rebuilding the model does not remove what they now know. Their manual time and error count would then be measuring recall, not method.

For the tool-first group the effect runs the other way: by the time they reach task M they have seen the answer (12 doors, 3 rooms). Rebuilding the fixture before each block does not undo that. Do not hide it. Record the order next to every manual-versus-tool comparison, report the two groups separately, and say in the write-up that the tool-first manual times are likely too fast. If budget allows, give the manual block a second fixture build with a different set of seeded defects, and record that change in the results.

Rebuild the fixture before each block so one block cannot change the model for the other.

Task script

The fixture is the canonical model seeded with 12 doors that have no Mark and 3 rooms that have no Number (see seeded-defects.json). These are the expected counts. Before each session the moderator confirms the actual counts on the rebuilt model and writes them down. If they differ from 12 and 3, the session uses the actual counts and the difference is noted.

Participants get a one-line goal for each task, not instructions.

Task 0: setup to first result. Starting from a machine with Revit and without the add-in, install the supported package and get the tool to report a finding on the open fixture. The clock starts when the participant opens the install instructions and stops at the first correct finding on screen. It is the first task of the tool block, so for odd-numbered participants it happens after task M has finished and been verified (see the session format for why).

Task 1: find. "Find out which doors and rooms are missing data." Expected: 12 doors without Mark, 3 rooms without Number.

Task 2: review and approve the door fix. "Fix the missing door Marks." The participant reviews the proposed changes and approves or rejects. The moderator does not say how many changes to expect. Two probes are set up before the session and not announced:

  • one door already has a populated Mark that must stay untouched;
  • the numbering rule is not stated to the participant, so a careful one should have to confirm or correct it.

Task 3: rejection. "Ask it to fix the missing room Numbers. When it shows you the proposal, reject it." Every participant is told to reject, so a rejection always happens and can be checked. This task tests whether rejecting is easy and whether a rejection holds. It does not test whether the participant would have approved; ask that afterwards ("would you have approved that proposal as shown? why?") and record the answer as review behaviour, separate from the integrity check.

The moderator checks afterwards, from the recording and from the tool:

  • the plan's state is rejected (Plans tab after a refresh, or the pending-plans list no longer shows it);
  • the panel Run Log has a Plan reject entry and no Error: plan.reject entry. A Plan reject entry alone only records the click;
  • asking the assistant to run the plan is refused because the plan is not approved;
  • a new snapshot compared with the one taken before the task shows no parameter differences, and the 3 rooms still have no Number.

What counts as a failure of rejection integrity, for that participant: the plan is not in state rejected; the reject call produced an error entry; the plan runs after rejection; or any parameter differs between the two snapshots. Any changed parameter is also a tool-caused unapproved change (bet 1 kill trigger). If the participant approves instead of rejecting, that is a deviation from the script, not a pass. Log it, restore the fixture, and repeat the task with a fresh proposal and a clear instruction to reject. Rejection integrity is not scored for that participant until a rejection has been observed.

Task 4: verify. "Show me that the door problem is fixed." Expected after a correct task 2: 0 missing door Marks, 3 room Number findings unchanged. The check must use a freshly captured snapshot, not the earlier one.

Task 5: handover. "Your BIM manager asks what changed and why. Give them something they can read." Observe what the participant produces (a report, a screenshot, the audit log, nothing). Do not assume the compact report from roadmap priority 4 exists; record what is actually available (for example the proof bundle from get_proof_bundle, the audit log, the panel).

Task M: manual baseline. Same fixture (rebuilt), same goals as tasks 1, 2 and 4, using the participant's own normal method (schedules, filters, Navisworks searches, a pyRevit tool, whatever they usually use). The clock starts at the goal statement and stops when the participant says the model is fixed and verified. The moderator then runs the same verification to find residual errors.

Interop probes (bet 2)

Asked during or right after the tasks, not as a separate test:

  • "Where in your normal day would this happen? What would you do right before and right after it?"
  • Ask them to show how they would get the result into the tool they use next (an issue in BIM 360 / ACC, a Navisworks viewpoint or search set, a pyRevit button, an Excel list). Record whether they can, what they do instead, and what they would copy by hand.
  • Ask about the model they would really run it on: cloud-workshared, linked, owned by others. Record every blocker they name.

Client-reach probes (bet 3)

Asked in the debrief, as questions about their organisation, not about the product's quality:

  • Who at your firm would have to approve installing this on a work machine? What would they ask?
  • Does your client's BIM execution plan or IT policy restrict add-ins or cloud AI services? Would model data leaving the machine be a problem?
  • If it saved time, who would pay and from which budget?
  • Would you show the output to your client? What would it need to contain?

Ask about past facts ("what happened last time a new tool was introduced?") rather than hypotheticals. Answers are stated intent, which is weak evidence; only an actual follow-up action counts as strong evidence.

Interview prompts

A. Before the tasks. How do you check for missing parameters today? How long does it take? With what tools? Have you ever let an automated tool change a model? What happened? What would make you refuse?

B. Safety. Describe what you saw before you approved. What did you check? What did you not check? What was missing that you would want? Would you run this on your real model without watching? Who else would need to see the approval?

C. Interop and D. Client reach. The probes above.

What to measure

All measurements are per participant per task, recorded by the moderator and checked against the recording.

Measure How Bet
Setup time to first result Minutes from opening the install instructions to the first correct finding on screen (task 0). Also count help events and failed attempts. 2, 3
Task time, tool vs manual Minutes for tasks 1, 2 and 4 combined, against task M. Report both per participant, with which block came first; do not average away a slower participant. all
Errors, tool path Count of wrong or missed changes after verification: populated Marks overwritten, doors left unfixed, wrong values, elements changed outside the proposal. 1
Errors, manual path The same count for task M. 1
Review behaviour Seconds between the proposal appearing and the approval click; whether the participant opened the per-element list; whether they changed or rejected anything. Observed, not inferred. 1
Probe catches Whether the participant caught the pre-populated Mark and questioned the numbering rule before approving. 1
Rejection integrity After the instructed rejection in task 3: plan state rejected, no Error: entry in the Run Log, execution refused, and no parameter difference between the snapshots before and after. Any miss is a failure for that participant. 1
Stated trust One question after task 4, 1 to 5: "I would let this change my real model after approving a proposal like that." Supporting colour only; behaviour outranks it. 1
Workflow fit Manual hand-off steps needed to move the result into their next tool; blockers named for their real models. 2
Adoption blockers Count and category of organisational blockers named (IT, client, data policy, cost). 3
Follow-up action Within 14 days, whether the participant took an unprompted concrete step: installed it on their own machine, asked their IT, or asked to try it on a real project. 3

Also log every crash, error message, confusing screen and moderator help event with a timestamp. These feed the product backlog regardless of the bets.

Success and kill criteria

Set before any session is run. Do not change them after seeing data. If a criterion turns out to be unmeasurable, record that and change it only for future pilots, in a commit that predates the next pilot.

The thresholds are judgement calls made without data. They are meant to be strict enough that a pass means something and a fail is clear.

Bet 1: safety

Pass (all of these):

  • No tool-caused overwrite of a populated Mark, and no element changed outside the approved proposal.
  • Rejection integrity holds for every participant, measured under the instructed rejection in task 3 (a participant who approved instead does not count as a pass until a rejection has been observed).
  • At least 4 of 5 inspect the per-element proposal before approving, and at least 3 of 5 catch the pre-populated Mark or question the numbering rule.
  • At least 4 of 5 say they would use it on a real model, and at least 3 of 5 can describe, unprompted, what the approval step protects them from.

Kill or redesign trigger (any one):

  • Any tool-caused unapproved change in the model.
  • Two or more participants approve without reviewing and then cannot say what changed. The gate is a rubber stamp; the safety claim fails even if no error occurred this time, and the review design changes before any further pilot.
  • Two or more participants refuse to approve any change even after a correct proposal, for reasons we cannot address.

Bet 2: interop

Pass (all of these):

  • At least 4 of 5 complete task 0 within 30 minutes with no more than two help events.
  • At least 3 of 5 name a specific point in their existing workflow where it would sit, and none says it would replace a tool they are unwilling to drop.
  • Blockers named for real models (worksharing, linked or cloud models) are ones the roadmap already covers or are small enough to address; none rules out most of their projects.

Kill or re-scope trigger (any one):

  • Three or more participants cannot get a first result in 45 minutes. Setup is the product problem to fix before anything else.
  • Three or more say they need Navisworks, pyRevit or BIM 360 / ACC integration before they would use it at all. This does not kill the product; it moves that integration ahead of other work, and the pilot is repeated afterwards.
  • The tool cannot work on the cloud-workshared models most participants use, with no workaround.

Bet 3: client reach

Pass (all of these):

  • At least 3 of 5 identify a plausible route to organisational approval (a named role or process), and no more than 1 of 5 reports a flat prohibition on AI or cloud services for model data.
  • At least 3 of 5 take a concrete follow-up action within 14 days.
  • At least 2 of 5 can name a budget or a client who would value the output.

Kill or park trigger (any one):

  • Four or more report that their firm or client policy would block it with no realistic route to an exception. The product may still serve individuals (see security), but the client-facing plan is dropped.
  • Nobody takes any follow-up action and nobody can name who would pay. Treat this as weak demand and stop adoption work until a different audience is identified.

Speed and accuracy (cross-cutting)

Not a separate bet, but required for any "go":

  • For tasks 1, 2 and 4 combined, the tool path is faster than manual for at least 3 of 5 participants, including review time.
  • Tool-path errors are no higher than manual-path errors for any participant.

If the tool path is slower for most participants, say so plainly. Saving time is not the only possible value (an audit trail may matter more), but it must not be claimed.

Overall decision

  • Go: all three bets and the cross-cutting checks pass.
  • Go with changes: one bet fails on a fixable cause and the other two pass. Fix and rerun that part only, with new participants.
  • Stop or pivot: any kill trigger in bet 1, or kill triggers in two or more bets.

One participant can be an outlier. When a single participant causes a trigger, record it, repeat that task with one more participant, and decide on both outcomes. Never discard a result because it is inconvenient.

Analysis and reporting

  • Score each criterion pass or fail against the numbers above before writing any narrative.
  • Report counts out of five. Do not compute averages of ratings or percentages from five people.
  • Quote participants only from the recordings, labelled with their code and with their consent. Do not paraphrase into quotes.
  • Report failures, Revit versions, commit and the fixture counts used.
  • Publish the filled results template together with this page at the commit used.
  • State what the pilot cannot show: five people, one fixture, one task, a moderated setting.

Preparation checklist

  • Hotfix PR #95 (the CreateTransaction self-call) merged, the add-in rebuilt from it, and one real parameter write tried on a throwaway copy in live Revit. Until then writes are untested.
  • Roadmap priorities 0 to 2 verified on a live Revit session (explicit snapshots, dependable fix review, repeatable fixture counts).
  • Install package for the Revit versions used, and written install instructions a participant can follow cold.
  • Fixture rebuild rehearsed twice with matching counts.
  • Probes (populated Mark, unstated numbering rule) prepared.
  • Block order sheet (odd participants manual first, task 0 after task M) and the task 3 rejection checks printed for the moderator.
  • Consent form, screening sheet, recording setup.
  • A dry run with someone outside the target group, results discarded.
  • This page committed unchanged before the first session; its commit hash entered in the results.

Results template

Fill after the pilot. Leave fields blank rather than estimating. Until real sessions are done, this section stays empty.

Pilot run: not run.

Field Value
Dates
Commit of this plan and of the product
Revit version(s)
Fixture counts confirmed before each session
Participants (count, firm types, paid or not)
Deviations from the plan

Per participant

Code Setup min Help events Tool min (tasks 1, 2, 4) Manual min Tool errors Manual errors Reviewed list Caught probes Rejection intact Trust 1 to 5 Follow-up in 14 days
P1
P2
P3
P4
P5

Criteria outcome

Bet Criterion Threshold Result (count of 5) Pass / fail
1 Safety
2 Interop
3 Client reach
Speed and accuracy

Decision (go / go with changes / stop or pivot), and the criteria behind it:

Kill triggers hit:

Interop and workflow findings (tools named, hand-off steps, blockers):

Organisational blockers named:

Defects and confusing screens found (link to issues):

What the pilot cannot show:

Next step: