Surface unschedulable operations on the Forecast

Date: 2026-08-18 Branch: naveen/capacity-planning Problem: an operation that can't be placed (no qualified operator for its ability, no feasible slot, horizon-exhausted) leaves NO capacityReservation row. The Forecast Gantt is built entirely from reservations, so the job "hangs" after the last placeable op — no bar, not counted in the conflict badge, and job.projectedCompletionAt wrongly reports an early finish. On the ops Kanban the same conflict IS visible (that path reads jobOperation.hasConflict directly).

Root cause (verified)

  • work-center-selector.ts:536-538 short-circuits the no-qualified-operator case; the op falls into the best === null branch (:778-801) which stamps hasConflict/conflictReason + a fallback work center but emits no plannedReservation.
  • persistChanges (scheduling-engine.ts:1018) only inserts capacityReservation rows from plannedReservations, so nothing represents the op.
  • projectedCompletionAt (scheduling-engine.ts:731-742) is the max over placed ends + planned reservations → excludes the unplaced op.
  • Forecast (forecast.tsx → getCapacityReservationsForResources → buildResourceTimeline) and its conflictCount (forecast.tsx:394-396) are 100% reservation-driven → the op is invisible.
  • Bonus bug: an unplaced op sets no placedEndByOperation, so its successors schedule from now as if it finished instantly.

Approach: Option A — engine emits a flagged placeholder reservation

When an op can't be placed, emit a placeholder capacityReservation at the earliest feasible start (earliestStart, after predecessors) for the op's work-content duration in calendar time, on the fallback work center, flagged isPlaceholder = true. It:

  • renders on the Forecast (distinct "blocked" bar) and folds into the conflict count,
  • pushes job.projectedCompletionAt to (at least) this op — honest,
  • chains successors after it (placedEndByOperation),
  • but must NOT hold capacity against other jobs → getLiveReservations excludes isPlaceholder = true, and it is NOT pushed into the in-run capacity.reservations blocking set.

Why a column (not derive from hasConflict)

A late-but-placed op is ALSO hasConflict yet is a REAL capacity hold. Only a dedicated marker can distinguish "shown but non-binding." Cheapest correct marker: one boolean on capacityReservation.

Tasks

  1. Migration …_capacity-reservation-placeholder.sql: ALTER TABLE "capacityReservation" ADD COLUMN "isPlaceholder" BOOLEAN NOT NULL DEFAULT false; + COMMENT. Apply + pnpm run generate:types.
  2. Engine types (functions/lib/scheduling/types.ts): add PlannedReservation.isPlaceholder?: boolean.
  3. work-center-selector.ts best === null branch: when durationHours > 0 and a fallback work center exists, compute end = earliestStart + durationHours (calendar ms, like outside-processing at :380), push a placeholder PlannedReservation (isPlaceholder: true, resourceKind: "WorkCenter", resourceId: fallbackWc, scheduleNote = the conflict), and placedEndByOperation.set(op.id, end). Do NOT touch capacity.reservations. Keep the existing selection (conflict + fallback WC, no placed dates).
  4. scheduling-engine.ts persistChanges: map isPlaceholder on the insert. (The endAt > startAt filter already lets it through.)
  5. master-data-provider.ts getLiveReservations: add .where("cr.isPlaceholder", "is not", true) so placeholders never occupy capacity for other jobs / next regen.
  6. Deno tests (work-center-selector.test.ts / determinism.test.ts): no-qualified-operator op → a placeholder reservation is emitted, is NOT in the capacity blocking set, and successors chain after it. Placement of OTHER jobs is byte-identical with/without the placeholder present.
  7. Service (production.service.ts getCapacityReservationsForResources): select isPlaceholder.
  8. resourceTimeline.ts: thread isPlaceholder onto ResourceTimelineReservation → the bar keeps isError red but gets a distinct style.icon (blocked/ban) so "can't be scheduled" reads differently from "scheduled but late"; pass isPlaceholder into the reservation detail.
  9. timeline.ts / TimelineDetail.tsx: add unschedulable to the detail type; a placeholder reservation shows an "Unschedulable" status chip (red), renders date-only (no fictional booked clock time / relative time), and an explanatory line: "This operation can't be scheduled — {reason}. The bar shows where it would run once resolved."
  10. forecast.tsx: map isPlaceholder through; conflict badge already counts it (the reservation now exists). Add a one-line header summary "{n} can't be scheduled" next to the conflicts badge (distinct wording).
  11. i18n: pnpm lingui:extract for the new strings (then /translate at commit).

UI mechanism (the "figure out a mechanism" ask)

Three layers, cheapest-first, all riding the existing pipeline:

  • Bar: distinct icon (blocked) + red — visually separates unschedulable from late.
  • Detail panel: dedicated "Unschedulable" chip + the reason + "where it would run" explanation, date-only (the span is a placeholder, not a booking).
  • Header: a small "{n} can't be scheduled" count beside the existing conflict badge.

Verification

  • deno test lib/scheduling/ from the functions dir (new + determinism cases green).
  • pnpm exec turbo run typecheck --filter=@carbon/erp --filter=@carbon/database.
  • Browser (/auth + /test): a job whose last op needs an ability nobody holds now shows a distinct blocked bar right after its previous op, the conflict/"can't be scheduled" counts fire, and the detail panel explains it.

Out of scope (noted for later)

  • Whether projectedCompletionAt should become a "never" sentinel when a job has an unschedulable op (vs. the placeholder end). Current change makes it honest-er (extends to the placeholder), which is strictly better than today.