Forecast-First Finite Scheduling

Last tested: 2026-08-18 Routes: /x/resources/work-centers/:id, /x/job/:id, /x/priority/people?view=capacity, /x/priority/dates, /x/priority/operations, MES /x/operations + /x/operation/:opId

Prerequisites

  • At least one work center, one job, and location shifts seeded (dev seed has these).
  • Slack badge on the job header only shows once job.projectedCompletionAt is set (requires a regen wave to have run for that job's location). Expedite works regardless.

Scenarios

(a) Work center operating hours + alwaysOn

  1. Navigate — /x/resources/work-centers, click a work-center row → edit form.
  2. Verify — the form has an "Operating shifts" multiselect (placeholder "Select" when empty) and a "Runs 24×7 (lights-out)" switch below the Processes field.
  3. Toggle the 24×7 switch, requestSubmit the form whose button reads "Save".
  4. Reopen the same work center URL → the switch is aria-checked=true (persists).

(b) Job header — slack badge + Best case what-if

  1. Navigate — /x/production/jobs (NOT /x/jobs — 404), click a job (e.g. J000001).
  2. The header renders at /x/job/:id/details. A slack badge ("Nd early/late" with a "Projected completion" tooltip) shows only when the job has a projectedCompletionAt.
  3. Open the "More options" menu → click "Best case…".
  4. Verify — a "Best case {jobId}" dialog opens showing "Current projection" and "Best case projection" (calls the schedule edge function with expediteJobId, persists nothing). A non-released job shows "Not scheduled" gracefully.

(c) Capacity view — Scheduled vs Available on one basis

  1. Navigate — /x/priority/people?view=capacity.
  2. Verify — SCHEDULED and AVAILABLE series; a station with no assignments shows its calendar hours (e.g. "9h free"), NOT 0 (the fallback-cliff fix). Sub-tabs "Load" and "Due (by due date)". An assumption banner ("Hours assumed from location shifts" for rung 2, or "No shifts configured — assuming Mon–Fri, 8h days" for rung 3).

(d) Dual dates — op due (need-by) vs projected completion

Prerequisite: a released multi-op job. Seed item BUS-STR-001 (3-op routing) via /x/job/new (item combobox → "BUS-STR-001", deadline "Medium Priority Soft Deadline" reveals a month/day/year date field; fill + blur commits hidden dueDate), then Release → "Release Job" confirm. Release itself triggers a schedule run.

  1. BOP rows — /x/job/:id/details "Bill of Process" card. Each op row: the due-date picker is button[aria-label="Calendar"] whose text is the date; the forecast is a plain span "Projected {date}" — text-muted-foreground when on target, text-amber-500 + tooltip "Behind target by N day(s)" when projected > due. The span is absent when projectedCompletionAt is null (e.g. an op with a placement conflict like "No qualified operator" never gets a forecast).
  2. Regen wiring — any schedule input change fires carbon/schedule.inputs.changed → mark-schedule-stale → schedule-replan-wave (~30 s debounce). Poll the DB (jobOperation.dueDate/projectedCompletionAt) rather than sleeping a fixed 90 s.
  3. Job due-date change — /x/priority/dates card's own Calendar button posts the same update as the drag (dnd-kit drag via agent-browser mouse does NOT take). Moving the job due earlier tightens op dueDates on the next wave; projections stay byte-identical when placement is unchanged.
  4. Pin — picking a date in a BOP op's Calendar writes dueDate + manuallyScheduled immediately. The pin SURVIVES later waves and upstream ops re-derive from the pinned op's target start. NOTE: the pin route (/x/job/methods/operation/due-date → updateJobOperationDueDate) does NOT fire notifyScheduleInputsChanged — upstream re-derivation only appears after the next wave from some other input. The popover "Clear" button unpins (null due + manuallyScheduled=false).
  5. Behind-target amber — a maintenance dispatch with "Takes work center offline" (planned window covering the placement) slips projections past the targets: BOP + /x/priority/operations ItemCards + MES op detail all flip to text-amber-500 "Proj. {date}" with the "Behind target by N day(s)" tooltip, while op dueDates stay byte-identical. Completing the dispatch reverts projections on the next wave.
  6. Best case dialog — "First behind target: {op} (due X, projected Y)" is appended to the bottleneck sentence ONLY when the JOB itself is late (projected day > job due). The expedite call can take ~20 s under the local edge-runtime CPU cap — re-read the dialog until "Calculating best case…" resolves.
  7. MES — /x/operations board cards sort by due date/priority (never projection); card link → /x/operation/:opId, whose Due Date card shows the "Proj. {date}" line.

Selector Notes

  • The 24×7 field is switch "Runs 24×7 (lights-out)"; check state via button[role=switch][aria-checked=true].
  • Login: the "Sign in with Email" button stays disabled until the email input registers in React state — real keystrokes (agent-browser type) enable it; a raw fill may not.
  • Jobs list is /x/production/jobs; job detail is /x/job/:id.

Common Failures

  • /x/jobs → 404. Use /x/production/jobs.
  • Best case shows "Not scheduled" for Draft/Planned jobs — correct (the edge function only schedules Ready/In Progress/Paused jobs; expedite returns null for others).
  • Popovers (BOP date picker, dispatch work-center combobox) close between agent-browser CLI invocations (live revalidation re-renders). Do open + option-click in ONE agent-browser eval (dispatch pointerdown/mousedown/pointerup/mouseup/click on the option). The "Takes work center offline" Radix switch also needs that full pointer sequence — a bare .click() does not toggle it.
  • agent-browser type silently drops "." characters (e.g. in emails) — use fill.
  • The shared default agent-browser session may be owned by another worktree's agent — set AGENT_BROWSER_SESSION=<name> for an isolated browser (and close only YOUR session).
  • Dev-only hydration failure marks the tab title "Error" on /x/priority/dates while the board still renders client-side — read document.body.innerText, not the title.
  • Seed work centers have zero workCenterShift rows: an op whose need-by falls at/before today runs away ~1 year per subtracted working day (MAX_CONSECUTIVE_CLOSED_DAYS cap in need-by-calculator.ts) — e.g. a first op showing "Aug 10, 2024". Known bug surfaced 2026-08-18, not a test regression.

Require-staffing policy (per-location) — verified 2026-08-21

Setting: Settings → Production → Scheduling card (/x/settings/production) lists the CURRENT company's locations, each with a "Require staffing" switch (company-scoped — a same-named location in another company is NOT shown). Backed by location.requiresStaffing, written service-role (settings admins lack resources_update).

Toggle it (Radix switch needs the full pointer sequence, not .click())

sw = [...document.querySelectorAll('button[role=switch]')]  // Scheduling switches are the LAST N (one per location)
// dispatch pointerdown/mousedown/pointerup/mouseup/click at the switch center

Verify: toast "Staffing requirement enabled/disabled" + DB location.requiresStaffing.

Verify on the forecast (force regen with the Regenerate button, don't wait 30s)

  • Regenerate = IconButton aria-label "Regenerate" inside a fetcher form → form.requestSubmit(btn).
  • ON: an ungated op on a non-lights-out work center with NO manning on the placement date becomes an unschedulable PLACEHOLDER (capacityReservation.isPlaceholder=t, scheduleNote "No operator assigned"). Forecast header shows "N CAN'T BE SCHEDULED"; clicking the op row → detail sidebar "Unschedulable / No operator assigned / where it would run".
  • Lights-out exempt: set a work center alwaysOn=true → its ops still place (ph=f) while non-alwaysOn WCs' ops stay placeholders. (My Deno gate: capacity.workCenter.alwaysOn.)
  • OFF: regen → all ops place again (ph=f), header "no conflicts". Byte-identical to pre-setting.
  • WC popover ("How are these hours calculated?" info button) gained a line: gated → "runs ability-gated work…", ungated → "runs work with no ability requirement…"; plus a "Staffing required" section only when the location's policy is ON.

KEY UX GOTCHA (not a logic bug, but reads as "empty/broken")

The forecast opens on today's Day view. Forward-ASAP places Ready jobs at the next available shift — if today is Friday afternoon/weekend, work lands on next Monday, so the default view shows "0 resources · 0 reservations · 0 jobs" even though work IS scheduled. Navigate to the week that actually contains the placements (?range=week&date=<placement date>) to see it. Placeholders (unschedulable ops) pin at now, so they appear in the CURRENT week even when the real placements are a future week.

Test-data note (dev seed, company "Carbon Development" / Manufacturing Plant)

  • Jobs J000002 (Ready, 3 ops) + J000004 (Ready, 3 ops) at Manufacturing Plant; all ops UNGATED (processes: Machining/Weld/Final assembly — requiresAbility=false). Only "Brake Press" is gated, on "Press Brake - 700T" (no job op → the floater/double-booking edge cases 1–2 aren't reproducible from seed; they're covered by the Deno suite).
  • Manning (peopleAssignment) is all PAST (Aug 10–14) at CNC Mill / Press Brake — does not cover the Aug-24 placements, which is why require-staffing ON makes everything unschedulable.