Open-source manufacturing ERP, MES and QMS. Quoting, MRP, inventory, shop floor, quality and lot/serial traceability on one Postgres schema, with a REST API and MCP server. Self-host or use Carbon Cloud.
Planning chart live supply, legend what-if, max order split, surplus Cancel
Last tested: 2026-10-13 Routes: /x/production/planning, /x/purchasing/planning, /x/part/$itemId/planning
Prerequisites
- Dev stack up and migrations applied (
crbn migrate). A migration edited after its version was recorded is NOT re-applied; run the file withpsql -f. - A Buy item with an open Order suggestion, a supplier part (conversion factor 1 keeps the drawer in inventory units), and policy Demand-Based Reorder.
- A make-to-stock job (Planned/Ready) on an item with no demand, for the Cancel.
- MRP has run at least once after the data exists (Recalculate button, or wait for the 3-hourly cron on the hour UTC).
Steps
1. Surplus item on Production planning (issue 10)
Open /x/production/planning?location=<plant>. The item with the demand-less
job is listed with a "Cancel" chip in the Actions column. Expand the row: the
line reads "Cancel job <J…>" with Review/Apply.
2. Purchasing planning loads (RPC)
Open /x/purchasing/planning?location=<plant>. Grid renders rows; the row's
button reads "Order ".
3. Max order quantity splits (issue 6)
Open /x/part/<itemId>/planning?location=<plant>. In the Planning card set
"Maximum Order Quantity" (react-aria number: fill, then click another field
to blur; verify input[name=maximumOrderQuantity]). Submit with
requestSubmit on the FIRST button whose text starts with "Save" (the card has
its own form; a later Save belongs to Supersession). The save re-runs MRP.
Back on Purchasing planning, click the row's "Order " button: Suggested
Orders lists several rows each <= the maximum (2280 with max 1000 → 1,000,
1,000, 280), due dates spread across the week.
4. Order, then the chart (issues 2 and 9)
Click the drawer's "Order" button. PO lines are created with requiredDate
only. Open the part planning tab: the "Incoming" card grows by the ordered
quantity before any MRP run, and every new PO row in Supply & Demand shows a
date (no "No due date").
5. Legend what-if (issue 7)
Read path.recharts-line-curve's d. Click the "Supply" legend button: d
changes. Click again: d is identical to the first read.
Selector Notes
- Legend buttons are plain buttons named "Projected on hand", "Safety stock", "Supply", "Planned", "Demand", "Demand Forecast" under the "Projected inventory" heading.
- The planning card's number fields have no accessible name; locate by the "What is Maximum Order Quantity?" help button, the textbox follows it.
- Summary cards: generic "Quantity on Hand", "Incoming", "Outgoing".
Common Failures
psql -c "a; b"prints only the last statement's result — one statement per call when reading probes.- A sizing function without the accumulation-period clamp spins forever on a
stored period of 0; set
statement_timeouton probes.