Batch Release & Batch Scheduling — Confirmatory Research
Date: 2026-09-04 Purpose: Ground the Carbon job-operation-batching design against how leading ERP/MES/APS systems model (1) releasing a batched set of operations independently of the parent order, and (2) simultaneous vs sequential batch processing in scheduling.
Bottom line: every one of the four decided design choices has clear industry precedent. Nothing contradicts them. Terminology to adopt is noted inline.
Topic 1 — Independent release of a batched/grouped set of operations
SAP process orders (PP-PI): release is multi-level, phase is the unit
An operation in a master recipe is subdivided into phases — "an independent subdivision of an operation" and the main planning object of the recipe. SAP determines dates, capacity requirements, and process costs at the phase level, not the order header.
Crucially, release is granular: you can release a process order at header, operation, OR phase level.
- Release at header → all operations and phases release.
- Release at operation → all its phases release.
- Release a phase individually → only that phase becomes executable, and its control recipe/process instructions go to the floor (PI sheet).
So SAP already treats "make this sub-unit of work executable" as a gate separate from the order being released as a whole. A phase that has not been released does not produce a live control recipe on the floor. This is direct precedent for choice (a): batch release as a floor-visibility gate separate from order release, and for choice (b): the executable sub-unit is governed by its own release state, not solely the order's.
MES / APS: campaigns pool operations across orders and dispatch as a unit
APS tools (Siemens Opcenter APS, formerly Preactor) model campaigning — an optimization/sequencing rule that pools like operations (same setup family, same resource) drawn from multiple orders into one run to minimize changeovers. The campaign is scheduled and dispatched to the resource as a single block; the member operations are "spoken for" by it. The order each member belongs to still carries its own order-level release/status — the campaign is a second, cross-order dispatch object layered on top. This is the "batch spans multiple orders and is dispatched as a unit" pattern the design assumes.
The "spoken for, not loose" pattern — how double-dispatch is avoided
The general mechanism across these systems: once an operation is assigned into a campaign/batch (or a phase into a control recipe), it stops appearing as a loose, independently dispatchable operation — the batch object owns it. The floor sees the batch as the dispatchable unit, and the member is reachable only through it until the batch is released. That is exactly Carbon's intended model: an op in a batch does not surface on the floor as a free operation; the batch's release state governs its visibility (choice b). Double-dispatch is prevented structurally by there being one owner of the op (the batch), not by a lock or a race check.
Note where systems differ: SAP's phase release is hierarchical (a sub-division of ONE order's operation), whereas an APS campaign is lateral (pools ops from MANY orders). Carbon's batch is the lateral kind, but borrows SAP's "release is its own gate" semantics. No system releases a pooled campaign automatically when a member order releases — the campaign/batch has its own release, which confirms (a) and (b).
Topic 2 — Simultaneous vs sequential batch processing
The standard terminology: p-batch vs s-batch (parallel vs serial batch)
This is the textbook term of art in the scheduling literature and the cleanest name for choice (c) — the distinction is a property of the process/resource:
| Regime | Term | Members processed | Batch duration |
|---|---|---|---|
| Simultaneous (furnace, oven, heat-treat, plating) | parallel batch / p-batch — a "batch processing machine" (BPM) | all at once, same completion time | ≈ fixed cycle time, independent of load size up to capacity. In pure theory, the max of member times; in practice a fixed cycle (preheat + soak) driven by the largest/heaviest member, not the count |
| Sequential (saw, laser table, cutting) | serial batch / s-batch | one after another | shared setup + the SUM of member run times |
Both are described explicitly as machine properties: "a p-batching machine allows several jobs to be processed simultaneously… all jobs have the same completion time"; "on an s-batching machine, the processing time of a batch is the sum of the processing times of all jobs." The regime lives on the resource, not on the item or the routing step — matching the design's decision to put a capability/regime flag on the process/resource.
Heat-treat is the canonical p-batch example in the literature ("very long processes such as diffusion in semiconductor manufacturing or heat treatments in metal fabrication are executed on BPMs"). Real furnace models make the cycle a function of cumulative weight (preheat) and max part size (soak) rather than of member count — useful nuance if Carbon later refines the fixed-cycle assumption, but the fixed-cycle-up-to-capacity model is the standard first-order approximation.
How capacity is reserved
- p-batch: ONE capacity block on the resource for the whole batch's cycle time, sized by capacity (weight/volume/count) not by summed time. Members load in parallel and share the single block.
- s-batch: ONE block spanning setup + summed run time; members occupy it serially.
In both regimes the resource is reserved as a single contiguous block for the whole batch, which is what the design intends (one schedule block, not N overlapping operation reservations).
How cost/time is attributed back to each order/member
SAP's joint production / co-products settlement is the closest ERP analogue to splitting one shared run across members. Cost is apportioned by equivalence numbers — proportional weights (e.g. 30:30:20:20). The default and simplest equivalence basis is output quantity, i.e. split the shared process cost proportionally to each member's quantity. That is precisely choice (d) — proportional-to-member-quantity cost split — and it is the mainstream ERP practice, not an invention. (SAP allows arbitrary equivalence weights as an override; Carbon's proportional-by-quantity default is the industry default, with room for the same override later if ever needed.)
Time attribution follows the same logic:
- p-batch: the cycle time is shared; each member is "charged" a proportional slice (by quantity/weight) of the single cycle — you do NOT multiply the cycle by member count.
- s-batch: each member is charged its own run time; only the shared setup is split proportionally.
Contradiction check against the four decided choices
| Design choice | Verdict | Precedent |
|---|---|---|
| (a) Batch release is a floor-visibility gate separate from order release | Confirmed | SAP phase-level release; APS campaign dispatch is its own object |
| (b) An op in a batch is governed by the batch's release state, not the order's | Confirmed | Phase/control-recipe gate; campaign "owns" pooled ops so they aren't loose |
| (c) Simultaneous/sequential is a property of the process/resource | Confirmed | p-batch vs s-batch is a machine property in the scheduling literature |
| (d) Cost split proportional to member quantity | Confirmed | SAP co-product equivalence numbers; quantity is the standard basis |
No contradictions found. The only refinements worth noting (not blockers): p-batch duration in the literature is technically max(member times) / a weight-and-size-driven cycle rather than a flat constant; and SAP permits non-quantity equivalence weights as an override on the proportional default. Both are supersets of the decided design, not conflicts.
Sources
- Releasing Process Orders — SAP Learning (header/operation/phase release levels)
- PP-PI Phase — SAP Community (phase = independent subdivision, planning object)
- Siemens Opcenter (Preactor) APS and ATS Preactor Advanced Scheduling (campaigning / changeover minimization across orders)
- A survey of scheduling with parallel batch (p-batch) processing — ScienceDirect (p-batch definition; heat-treat as canonical BPM)
- Scheduling parallel serial-batch processing machines — IJPR and Mixed batch scheduling — Journal of Scheduling (s-batch = sum of member times; furnace preheat/soak cost model)
- Joint Production in Product Costing — SAP Community and Equivalence number method — Wikipedia (proportional cost apportionment by equivalence number / quantity)