Open-source manufacturing ERP, MES and QMS. Quoting, MRP, inventory, shop floor, quality and lot/serial traceability on one Postgres schema, with a REST API and MCP server. Self-host or use Carbon Cloud.
Job Operation Batching Research: Best Practices Survey
Researched 2026-08-31, against the feat/job-operation-batching-v2 implementation
(batch builder, jobOperationBatch entity, signature-based suggestions, MES batch
mode, completion slicing). Question: what would make Carbon's batching genuinely
competitive with Steelhead, and how should the builder and auto-suggestion evolve.
Summary
Surveyed Steelhead (metal finishing MES — the named competitor), SAP S/4HANA
(order combination / campaign planning / batch management), and job-shop peers
Fulcrum, Epicor Kinetic, and Plex. Three headline findings. (1) Carbon's
architecture is already the industry-consensus shape — a wrapper batch entity
that preserves member-order identity, executes once, and distributes results
back at completion is exactly SAP's MILL_OC combined order and Fulcrum's work
order; Epicor's irreversible whole-routing batching is the cautionary tale we
already avoid. (2) The biggest gap is a capacity model: every competitor
that batches to a physical vessel (Plex mixers, Steelhead racks, Fulcrum
sheets) carries a per-workcenter capacity number, and Carbon's workCenter has
none. (3) Nobody ships a configurable compatibility-rule engine — every
product either hard-codes the keys (Fulcrum: material+thickness+machine) or
leaves it to operator discipline (Epicor) — so per-process hard/soft rule
configuration is an open differentiator, and auto-suggestion beyond Fulcrum's
filtered due-date list is essentially unclaimed territory.
Competitors Surveyed
- Steelhead Technologies — MES/ERP purpose-built for plating, anodizing, powder coat, heat treat job shops; the direct competitor named in the request. Sourced largely from Wayback captures of their (now offline) docs site.
- SAP S/4HANA (PP, PP-PI, PP/DS, Mill Products) — the enterprise reference: order combination, production campaigns, setup matrices, block planning.
- Fulcrum — modern job-shop MES; the best-documented auto-suggestion flow (nest planning) and proportional cost allocation.
- Epicor Kinetic (Advanced Production) — deepest practitioner detail on job batching, including its failure modes.
- Plex (Rockwell) — the reference model for vessel capacity (batch size per workcenter).
Key Consensus Patterns
1. A batch is a wrapper; members keep their identity
- SAP: MILL_OC creates a combined production order — a real order that executes once; actual costs and confirmations collect on it, then settle back to the original orders via a Quantity Distribution step at final confirmation. Goods receipt, inspection lots, and material batches stay on the originals.
- Epicor: batch job consolidates selected jobs' operations/materials into a new parent job with demand links back — but batching is irreversible, must span the routing to one end of the BOO, leaves orphaned closed jobs, and flow-back of completed quantities is config-fragile.
- Fulcrum: a "work order" groups like operations across jobs into one schedulable unit with one timer and one completion.
- Rationale: execution is shared; accountability (GR, certs, costing, traceability) is per member order. Carbon's operation-scoped membership + dissolve + per-member event slicing already matches the good half of this pattern and avoids Epicor's traps.
2. Capacity is a per-workcenter vessel number
- Plex: workcenters carry Capacity and Minimum Batch Size; given a scheduled quantity the system computes batch count and last-batch size per vessel (e.g. 1,750 lbs → 3×250 on a 300-lb mixer + 2×500 on a 500-lb mixer), with component quantities auto-scaled per batch.
- Steelhead: Rack Types carry
Default Parts Per Rack(whole pieces only) plus Rack Type Occupancy (how many racks of a type fit a station) and a per-part Station Occupancy % ("a 747 wheel occupies 30% of a block"). Notably NO weight/surface-area/amp-hour capacity was found anywhere public. - SAP: capacity categories per work center; base UoM can be pieces/kg/area when quantity-limited; PP/DS bucket capacity in quantities; campaign profiles cap max orders per campaign.
- Fulcrum: sheet capacity delegated to external nesting software; Fulcrum verifies sheet sizes and tracks remnants back into stock.
- Rationale: batching without a fill limit is grouping, not load building. Piece-count capacity covers most cases (even Steelhead ships only that).
3. Compatibility is enforced by hard keys — but never configurable
- Steelhead: three enforcement layers — parts with non-identical recipes are auto-split onto separate work orders ("can't be run together"); at rack time, spec-field param ranges must overlap to share a rack (e.g. thickness min/max intersection); node-level gates block movement on missing specs or inapplicable treatments. Cross-customer mixing on one rack is explicitly supported.
- Fulcrum: nest candidates filtered by machine + material + thickness + due date — fixed system filters.
- Epicor: no validation at all; the engine even copies the FIRST selected job's time standards onto the whole batch, silently corrupting estimates.
- SAP: combinability checked per operation on work center, UoM, activity type, control key; planning-side grouping keyed on setup group keys and characteristics (block planning: steel grade, width, color).
- Rationale: hard rules prevent scrap (wrong parts in the tank); but every vendor hard-codes which keys. A per-process hard/soft/ignore configuration over BOM/BOP dimensions exists nowhere surveyed.
4. Auto-suggestion: a filtered, due-date-ranked candidate list
- Fulcrum (the only real suggester): nest planning "recommends work to nest together taking into account due dates," pulls candidates across all open orders for a machine+material, and suggests additional parts to add to a started nest. Geometric fit is delegated to external nesting software — Fulcrum decides which parts, the nester decides how they fit.
- SAP PP/DS: the optimizer sequences to minimize weighted setup time + setup cost + delay cost + storage cost, reading a setup matrix (state → state transition durations/costs, wildcard fallbacks); campaign optimization groups same-setup-group orders into campaign bars with profile-driven caps and auto-created setup/clean-out orders.
- Steelhead: advisory only — "see all upcoming paint colors so you can easily batch them"; humans compose loads, the system validates. Custom scheduling logic is an escape hatch (Power Scheduling, user TypeScript).
- Epicor: explicitly none.
- Rationale: the shipped state of the art is modest — hard-filter, rank by due date, let a human commit. SAP's weighted-objective machinery shows the scoring dimensions that matter: setup saved vs delay cost vs (for Carbon) capacity waste.
5. Time/cost fan-out: proportional beats even, and the basis matters
- Fulcrum: machine time and material allocated per part from the parsed nest sheet (actual area/time), setup allocated automatically; "all times are proportionally allocated back to the different jobs' costs."
- SAP: combined-order actuals settle back to originals; quantity distribution at final confirmation; campaign fixed costs (setup/clean-out) distributed across member orders.
- Steelhead: default even split by part count, then human-adjustable — drag tools to redistribute ("80/20"), per-segment % billed, step one work order out of a running multi-WO timer without stopping the rest.
- Epicor (the pain case): without batching, an operator clocked into 5 jobs allocates all 5 hours to each; with it, co-part apportionment by quantity — and forums show persistent dissatisfaction with the split basis and no settled answer for scrap allocation.
- Rationale: Carbon's completion slicing proportional to
operationQuantitymatches SAP/Fulcrum. Steelhead's manual redistribution is the flexibility ceiling to aim at later.
6. Batch-level quality feeds per-member certs — never one load cert
- Steelhead: measurements attach to Part Transfer Accounts; operators enter specs for a grouped panel once, fanned to member parts; certs are generated per customer order from the shared data ("Certify Multiple"). Coupons — test panels racked alongside production parts, spawning their own work orders — are the batch-level QA instrument.
- SAP: inspection lots are per order (origin 03 at release), never per machine run.
- Rationale: the run is where data is captured once; the order is where compliance lives. Matches Carbon's traceability model.
Answers to Research Questions
- Steelhead's load model — There is NO first-class Load entity. Carriers
are Racks (typed, QR-coded, nestable into Sub/Super racks ≈ flight
bars), the true grouping atom is the Part Transfer Account (identical-
state part group), and capacity is whole
parts per rack+ racks-per- station occupancy + per-part station-occupancy %. Lifecycle: rack (scan) → move rack node-to-node → unrack; recipes freeze once running. Weight/area/ amp-hour capacity: not found. - Steelhead compatibility — Enforced, not advisory: identical-recipe work-order splitting at order entry, spec-param range-overlap checks at racking, spec/treatment gates at each node. Emergent from recipe identity + treatments + spec params — not a configurable rule engine.
- Certs fan-out — Inverse of "one load cert": shared measurements captured per group, certs generated per customer order/account; coupons ride racks for destructive/batch tests. (Heat-treat charge certs not publicly documented.)
- SAP order grouping — Four mechanisms: combined orders (MILL_OC / S/4HANA Cloud 2602 scope item 7TO; per-operation combinability checks; execute on wrapper, GR + settle back to originals), collective orders (vertical BOM networks — different thing), PP-PI campaigns (same-product process orders sharing setup/clean-out, fixed costs distributed), and PP/DS campaign optimization / block planning (setup-group keys, setup matrices, campaign profiles with max-order caps).
- Capacity units — Pieces (Steelhead racks, SAP campaign order caps), weight/volume per vessel (Plex mixers/blenders), sheet geometry delegated to nesters (Fulcrum), time as SAP's default with quantity UoMs available. Piece-count is the lowest common denominator every vendor supports.
- Auto-suggestion algorithms — Fulcrum: hard-filter (machine + material + thickness) → due-date-ranked candidate list → human selects → external optimizer packs. SAP: weighted-objective optimizer over a setup transition matrix, campaign grouping by setup group. Nobody scores soft compatibility, learns from history, or looks ahead to soon-ready operations.
Competitor-Specific Details
Steelhead
- Vocabulary: Rack/Rack Type/Super Rack, Flight bar, Process Node, Recipe (frozen per-WO process instance), Treatment/Treatment Group (finish options at order entry), Job Tag (they deliberately renamed "Traveler"), Received Batch (incoming lot), PTA, Workboard, Coupon, Spec Field Param.
- Shop-floor UX: Workboards (racking/super-rack/scanner variants), scan job tag → rack → QR-coded rack moves whole groups one click at a time; "Group Like Parts" organizes by "whether they can be moved together"; scanner lines enforce per-tank scans, dwell timers, wrong-load alerts.
- Timers run against Part Accounts / Racks / Stations / Sales Orders simultaneously; even split on stop, editable timeline with % billed.
- Line overhead rates capture utilities; Super Nodes collapse auto-line steps into one costed station.
- Docs site is offline (June 2025 Wayback snapshot is the source ceiling).
SAP
- Setup matrix rows are (predecessor state → successor state, duration, cost), charged to the successor; wildcard fallbacks avoid N×N matrices.
- Campaign profile (selected via setup group): max orders per campaign, auto-created setup/clean-out orders, board display.
- "Batch" in SAP = material lot only; batch determination (FEFO etc.) picks consumed lots, batch derivation copies attributes sender→receiver per ORDER even when execution was shared — the linkage follows the document chain, not the machine run.
- Open question SAP couldn't answer publicly: whether a MILL_OC combined order carries its own in-process inspection lot.
Fulcrum
- Does NOT nest geometrically — exports DXFs to SigmaNest/TRUMPF/Amada, then re-parses the returned setup sheet into per-part material usage, per-part machine time, setup count, and setup membership. Remnants become stock.
- Grouping is also used for bending, powder coat, paint — not only cutting.
Epicor (cautionary tale)
- Batching is irreversible, whole-routing-direction only, copies the first job's time standards, doesn't reschedule the batch job, leaves closed-job litter, and flow-back is config-dependent. Practitioners resort to an intermediate-part workaround (a "processed sheet" part) where the intermediate part IS the compatibility contract.
Plex
- Batch = one job's operation split into vessel-sized cycles (inverse of cross-job batching); workcenter carries Capacity + Minimum Batch Size; split types (Even), last-batch size computed; component quantities scale per batch with tolerance bands; deliberate over-scheduling to fill a vessel, excess packed off as WIP.
Grounding update (2026-08-31, post-merge of main)
Main shipped finite-capacity scheduling (#1151, merged into this branch), which changes the footing of several recommendations below:
- The scheduler now writes
jobOperation.projectedCompletionAt(forward forecast) andjobOperation.dueDate(backward need-by target) every regen, pluscapacityReservationrows per work center/employee. So:- "Arriving soon" (rec 4) is now data-backed for free: a candidate's
predecessor op has a real
projectedCompletionAt— no estimation needed. - Due-slack scoring (rec 3) already has its input:
op.dueDateIS the demand-anchored need-by; slack = need-by minus projected finish, both stored. The suggestion score can read them directly. - The builder's WC picker "N in queue" can graduate to real load from
capacityReservationspans instead of a count.
- "Arriving soon" (rec 4) is now data-backed for free: a candidate's
predecessor op has a real
- Work centers now carry operating hours (
workCenterShift/alwaysOn) and are finite (one op at a time) — but still have NO per-run load size, so rec 1 (batchCapacity) remains the gap; it composes cleanly since a batch already occupies the WC as one op. - The schedule routes moved (
x/schedule/*→x/priority/*); recurring load windows (rec above) could anchor onworkCenterShiftrows rather than a new schedule concept.
Recommended Approach for Carbon
Ordered by leverage; each names the pattern it follows.
- Work-center capacity (Plex/Steelhead pattern). Add optional
batchCapacity(numeric) +batchCapacityUnit(pieces first; weight/area later) and optionalminimumBatchQuantitytoworkCenter. Builder shows a fill meter per prospective batch against the selected WC; suggestions split oversized groups into multiple loads (Plex's batch-count computation). Piece-count only for v1 — that is all Steelhead ships, and it unlocks bin-packing. - Per-process compatibility configuration (unclaimed differentiator). A
JSONB config on
processmarking each batching dimension (substance, form, grade, dimension, finish, item) as hard / soft / ignored. Hard mismatches are excluded or blocked (Steelhead's spec-overlap enforcement justifies hard rules existing); soft mismatches score down but stay visible. Keeps the current signature as the default config so nothing changes until a process opts in. No surveyed vendor lets users configure this. - Suggestion algorithm v2 (Fulcrum list + SAP scoring). Replace exact-
signature buckets with scored groups:
score = setup minutes saved − w₁·soft-mismatch penalty − w₂·due-slack risk − w₃·capacity waste. Rank candidates due-date-first inside a group (Fulcrum), pack greedily to WC capacity (EDD bin-packing), and surface near-matches as "compatible with caveat" rows instead of hiding them. SAP's delay-cost term is the model for due-slack: score the earliest member's slack (due minus remaining routing time), not the raw due spread. - "Arriving soon" lane (nobody ships this). Candidates whose predecessor operation is In Progress, with projected ready time — so the planner can see that waiting 2 hours doubles the load instead of running half-empty today. Fulcrum's "suggest additional parts for a started nest" is the nearest precedent; extending a not-yet-started Carbon batch is the same move.
- Co-occurrence ranking (no precedent needed — cheap and honest). Rank
signature pairs that were actually batched together historically (query past
jobOperationBatchmembers) above theoretical matches. Encodes tribal knowledge with zero configuration; degrades gracefully to the score alone. - Batch-level quality capture (Steelhead pattern, later). One grouped spec-measurement entry fanned to member operations, and coupon-style test parts that ride a batch — mapping onto Carbon's existing quality module. Certs remain per member/customer order (unanimous across vendors).
- Keep and defend what already matches consensus. Operation-scoped membership, dissolvable batches, one shared timer, and completion slicing proportional to operation quantity are exactly the SAP/Fulcrum shape — and each is a documented Epicor pain point. Worth stating in marketing. Future flexibility ceiling: Steelhead's manual redistribution of a recorded split (80/20 drag) if customers ask.
- Terminology check. "Batch" is safe for job-shop execution grouping (Plex uses "Job Op Batches" literally); SAP reserves "batch" for material lots — Carbon already says "lot" for those, so no collision. Steelhead's "load" is informal even in their own product.
Sources
Steelhead (Wayback captures of docs.gosteelhead.com, June 2025, + live marketing):
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/racks-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/workboards-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/processes-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/specs-and-certs-overview
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/received-batches-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/treatment-troubleshooting-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/part-labor-timers-1
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/super-nodes
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/product-updates-2025
- https://web.archive.org/web/2025/https://docs.gosteelhead.com/docs/margin-pricing-1
- https://gosteelhead.com/resource-library/redline-job-costing-steelheads-manufacturing-erp
- https://gosteelhead.com/resource-library/innovation-plating-and-anodizing-powered-steelhead
- https://gosteelhead.com/plating-anodizing-software
- https://gosteelhead.com/powder-coating-software
- https://gosteelhead.com/capacity-planning-and-scheduling
- https://finishingandcoating.com/index.php/new-technology/1761-steelhead-technologies-adds-nadcap-certification-scanner
SAP:
- https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-sap/combined-production-orders-in-sap-s-4hana-cloud-public-edition/ba-p/14397369
- https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-members/combined-production-order-processing-dimp/ba-p/13266644
- https://help.sap.com/docs/SAP_ERP/3a6bcf3eafa7475e813c7b1ec2e0fe0d/5bcec353b677b44ce10000000a174cb4.html
- https://help.sap.com/docs/SAP_S4HANA_CLOUD/4032610758dc437089f0c28320eec93f/09ccd8530439414de10000000a174cb4.html
- https://help.sap.com/docs/SAP_ERP/698b19fa88b846359bc611f11184c810/6f80bf53f106b44ce10000000a174cb4.html
- https://help.sap.com/doc/saphelp_scm700_ehp01/7.0.1/en-US/8e/4ec95360267614e10000000a174cb4/content.htm
- https://help.sap.com/doc/saphelp_snc70/7.0/en-US/cd/2a673b19f27654e10000000a114084/content.htm
- https://help.sap.com/doc/saphelp_snc70/7.0/en-US/d8/eb834014d26f1de10000000a1550b0/content.htm
- https://learning.sap.com/courses/exploring-advanced-production-planning-with-sap-s-4hana-pp-ds/exploring-the-usage-of-optimization-in-sap-s-4hana-pp-ds
- https://community.sap.com/t5/supply-chain-management-blog-posts-by-sap/product-definition-and-advanced-planning-in-the-mill-industries/ba-p/14271191
- https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-members/batch-derivation-in-production/ba-p/13261712
- https://community.sap.com/t5/enterprise-resource-planning-q-a/mill-oc-how-do-you-keep-the-costs-in-the-child-orders/qaq-p/590008
- https://help.sap.com/docs/SAP_S4HANA_CLOUD/d1e58be39d884a0dbf75a7526a9acbf4/1f14c453f57eb44ce10000000a174cb4.html
- https://sapinsider.org/streamline-your-production-changeovers-in-sequence-using-the-setup-matrix/
Fulcrum / Epicor / Plex:
- https://fulcrumpro.com/manufacturing-software/grouped-work-and-nesting
- https://fulcrumpro.com/article/streamline-production-with-work-orders-in-fulcrum
- https://fulcrumpro.com/article/product-showcase-video-nesting-workflows-in-fulcrum
- https://fulcrumpro.com/product-update/nesting-work-orders---looking-for-beta-users
- https://fulcrumpro.com/article/fulcrum-for-fabricators-workflows-for-custom-sheet-metal-shops
- https://www.epiusers.help/t/automatic-operation-batching/41522
- https://www.epiusers.help/t/questions-on-job-batching-advanced-production-module/99221
- https://www.epiusers.help/t/batching-jobs-for-a-single-operation-not-the-entire-job-split-burden-labor/131811
- https://www.epiusers.help/t/batching-jobs/113153
- https://www.epiusers.help/t/job-batching-scrap/136845
- https://www.epiusers.help/t/job-batching-coparts/120726
- https://plex.rockwellautomation.com/content/dam/plex/legacy/2023-03/10331_Plex_Batch_Management_DS.pdf
- https://plex.rockwellautomation.com/en-us/resources/plex-batch-management-basics.html