MRP Planning Actions Research: Best Practices Survey
Summary
This surveys how best-in-class manufacturing ERPs model MRP action messages /
planning exceptions — the full set of planning actions beyond just "create an
order" — and how those actions are routed to and worked by buyers/planners. The
motivation: Carbon's MRP today emits exactly one suggestion, "Order" (a computed,
non-persisted quantityToOrder), and cannot tell a planner to expedite, defer, or
cancel existing supply.
The consensus across SAP, Microsoft Dynamics 365 (SCM and Business Central), Oracle NetSuite, Epicor Kinetic, and Infor (SyteLine/LN) is remarkably tight. Every one of them separates two concept classes: (1) actionable messages on orders — create a new order, pull-in/expedite, push-out/defer, cancel, and (in some) change-quantity; and (2) advisory exceptions/warnings — below safety stock, negative on-hand, cannot-meet-requested-date, master-data broken. All of them gate reschedule noise behind a tolerance window so trivial date shifts don't spam the worklist, and all of them partition the worklist by an ownership code (SAP "MRP controller" for planning + "purchasing group" for buying; Epicor "Buyer ID"; BC "planner"; LN "planner"). The pivotal enabling concept everywhere is firming: a suggestion an engine freely rewrites only ever needs "create"; the moment an order can be committed/firmed, you need message-to-a-human actions because the engine may no longer silently move it.
Competitors Surveyed
- SAP S/4HANA (and ECC) — the enterprise reference; its 8-group numbered exception-message catalog (esp. Group 7: reschedule-in 10 / reschedule-out 15 / cancel 20 / plan-process 30) is the model every other ERP echoes.
- Microsoft Dynamics 365 SCM (F&O) — cleanest directional action taxonomy (Advance / Postpone / Increase / Decrease / Derived) plus the "Delays/futures" cannot-meet-date exception as a first-class output.
- Microsoft Dynamics 365 Business Central — cleanest enum to emulate: Planning Worksheet action messages New / Change Qty. / Reschedule / Resched. & Chg. Qty. / Cancel, orthogonal on (date, quantity) axes.
- Oracle NetSuite Supply Planning — Reschedule In / Reschedule Out / Cancel + numeric planning-exception codes; bulk approve/reject from a Planning Workbench.
- Epicor Kinetic — New PO Suggestions vs Change PO Suggestions (Expedite / Postpone / Cancel / Qty change), Buyer-ID-scoped worklists, reschedule-in/out delta tolerances.
- Infor SyteLine (CSI) & LN — planned orders + exception messages (Reschedule In / Reschedule Out / Cancel Order), firm/confirm to release, per-planner exception configuration.
Key Consensus Patterns
1. Two concept classes: actionable messages vs. advisory exceptions
- SAP: Group 7 messages (10/15/20/30) are actions on orders; Groups 4/5/6/8 are advisory (excess stock, below safety stock, no BOM, planning terminated).
- Dynamics 365 SCM: "Actions" (Advance/Postpone/Increase/Decrease) modify an existing order; "Delays/futures" is a separate cannot-meet-date exception.
- Business Central: the
Action Messageenum is the actionable set; the separateWarningfield carries Emergency / Exception / Attention severities. - NetSuite: order recommendations (Reschedule In/Out, Cancel, Create) are distinct from coded "Planning Action Messages" (100 below-zero, 110 below safety stock, 130 late PO, 140 late WO).
- Infor LN: order-planning messages (Reschedule In/Out, Cancel Order) sit in a broader exception taxonomy alongside quantity/lead-time/safety-time exceptions.
- Rationale: an actionable message maps 1:1 to a document edit a buyer/planner performs; an advisory flag needs human judgement and may not resolve to a single order edit. Modeling them separately (but linked) keeps the worklist crisp.
2. The actionable message taxonomy — six primitives
Every product implements the same core set (names vary):
| Primitive | SAP | D365 SCM | Business Central | NetSuite | Epicor | Infor LN |
|---|---|---|---|---|---|---|
| New buy order | new planned order / PR | planned purchase order | New | create/release | New PO Suggestion | Confirm planned PRP order |
| New make order | new planned order | planned production order | New | create/release | New Job (unfirm) | Confirm planned prod order |
| Pull in (earlier) | 10 reschedule in | Advance | Reschedule | Reschedule In | Expedite | Reschedule In |
| Push out (later) | 15 reschedule out | Postpone | Reschedule | Reschedule Out | Postpone | Reschedule Out |
| Cancel | 20 cancel process | (Decrease→0) | Cancel | Cancel | Cancel | Cancel Order |
| Change quantity | (42 changed / 25-26 excess) | Increase / Decrease | Change Qty. (+ Resched. & Chg. Qty.) | via reschedule/qty | Change PO Suggestion (qty) | Qty < Min / > Max / <> Increment |
- Directional vs. combined: BC combines date+qty into
Resched. & Chg. Qty.and leaves reschedule direction implicit; D365 SCM and SAP/Epicor/LN bake direction into the type (Advance/Postpone, expedite/de-expedite, reschedule-in/out). Direction-in-the-type is more legible to a buyer. - Cancel vs. Decrease-to-zero: most products have an explicit Cancel; D365 SCM notably folds it into Decrease. Explicit Cancel reads better.
- Rationale: these six span the two axes a planner can change on any supply order — its date (earlier/later) and its quantity (more/less/none) — plus the create/cancel endpoints.
3. A reschedule proposal is a message + a proposed date, not a new order
- SAP: a reschedule (10/15) is not a new element — it's an exception message hung on the existing firmed receipt, plus a rescheduling date (the date MRP suggests moving it to), shown in a dedicated MD04/MD05 column.
- NetSuite / Epicor / LN: same — the recommendation references the existing order and carries a new suggested date/qty.
- Rationale: the buyer needs "move this PO line to this date", so the message must reference the concrete existing document + the target date/qty, distinct from a freestanding new-order proposal.
4. Tolerance windows gate reschedule noise
- SAP: the rescheduling check only proposes a reschedule when the mismatch exceeds configured forward/backward tolerance values (in days) within a rescheduling horizon.
- D365 SCM:
Advance margin/Postpone margincap and gate reschedules; action calculation is off unless within the action message time fence. - Business Central: dampener period / dampener quantity suppress trivial messages.
- Epicor: separate reschedule-in delta and reschedule-out delta (days).
- Infor LN: per-planner exception-type configuration decides which fire.
- Rationale: without a tolerance, every 1-day drift generates a message and the worklist becomes noise the planner learns to ignore. This is a hard requirement, not a nice-to-have.
5. Firming is the concept that makes change-actions necessary
- Universal: an MRP engine freely creates, moves, and deletes its own planned proposals every run. Once a proposal is firmed (SAP asterisk / manual edit / planning-time-fence) or converted to a real PO/job, MRP must no longer silently touch it — so instead it raises a reschedule/cancel message to a human. SAP: 10/15/20 fire on firmed receipts; 30 fires on planned ones MRP can still auto-reschedule.
- Conversion / "Carry Out" / "Firm" / "Confirm": the accept-and-convert step turning a proposal into a real document. SAP MD14/MD15 (planned→PR), CO40/CO41 (planned→production); BC "Carry Out Action Message" after ticking "Accept Action Message"; Epicor "Buy"/"Firm"; LN/SyteLine "Confirm"/"Firm".
- Rationale for Carbon: Carbon already creates real POs (status
Planned) and jobs directly from planning — there is no persisted "planned order" the engine owns. That means Carbon's change-actions (expedite/defer/cancel) in necessarily operate on already-real purchase orders and jobs, which is exactly SAP's "firmed receipt" case. Carbon effectively has no unfirmed tier, so every existing-supply action is a message-to-a-human by construction.
6. Owner-scoped, filterable, bulk-actionable worklists
- SAP: MD06 (snapshot) / MD07 (live) collective worklists filtered by MRP controller (planning) and purchasing group (buying); a processing indicator lets a planner tick off reviewed materials.
- D365 SCM: Master planning workspace + planned-orders lists filtered by vendor / coverage group / buyer group; group-by-vendor+buyer-group on firm.
- Business Central: Planning Worksheet (planners) vs Requisition Worksheet (buyers); Carry-Out can copy PO proposals into the Requisition Worksheet — the primary planner-vs-buyer routing mechanism.
- NetSuite: Supply Planning Workbench views grouped by subsidiary/location, header-checkbox bulk approve/reject ("Perform Selected Actions").
- Epicor: Buyer Workbench (POs) / Planning Workbench (jobs); Buyer ID resolved Part-Site → Part-Class → system default partitions the worklist.
- Infor: per-planner exception sessions; planner code + buyer on the item.
- Rationale: exception management only scales when each buyer/planner pulls "my materials" and can act in bulk; a single global list doesn't get worked.
Answers to Research Questions
Full catalog of action messages (beyond "Order")? — Six primitives (§2): New buy, New make, Expedite/pull-in, Defer/push-out, Cancel, Change quantity — plus advisory exceptions (below safety stock, excess/over-supply, cannot-meet-date, late order, master-data broken). SAP's canonical action set is 10/15/20/30; BC's is New / Change Qty. / Reschedule / Resched.&Chg.Qty. / Cancel; D365's directional set is Advance / Postpone / Increase / Decrease.
New order vs. change to existing order? — Distinct outputs everywhere (§3). A new proposal is a freestanding planned order/requisition with its own dates; a change is a message referencing an existing (firmed/real) order + a proposed new date/quantity. SAP's "rescheduling date" is a first-class column.
How planners work them? — Owner-scoped, filterable worklists with accept/convert and bulk actions (§6): SAP MD06/MD07, BC Planning/Requisition Worksheet + Carry Out, NetSuite Workbench bulk approve, Epicor Buyer/Planning Workbench.
Assignment to buyers/planners? — A per-item/portfolio ownership code (§6): SAP MRP controller (mandatory MRP-1 material-master field) + purchasing group; Epicor Buyer ID (Part-Site → Part-Class → default); BC planner + worksheet split; Infor planner code + buyer. Carbon has no buyer/planner field today — only a generic document
assignee(present onpurchaseOrder, not populated by the planning path). This is the second gap the rewrite fills.Firming / conversion? — §5. Firming protects a proposal from auto-change; conversion turns it into a real document. Carbon skips the unfirmed tier — it creates real
Planned-status POs and real jobs directly — so its change-actions inherently target real documents (SAP's firmed-receipt case).Tolerance to suppress noise? — Yes, universal (§4): SAP rescheduling-check tolerance days + horizon, D365 advance/postpone margins, BC dampeners, Epicor reschedule-in/out deltas. Must-have for Carbon's expedite/defer messages.
Competitor-Specific Details
SAP S/4HANA / ECC
8 exception groups; priority-1 messages on the results screen, priority-2 on drill-in. Group 7 = actions: 10 reschedule in (firmed receipt later than need), 15 reschedule out (firmed receipt earlier than need), 20 cancel process (firmed receipt with no matching requirement), 30 plan process (planned receipt, demand inside lead time). Priority order 10 → 20 → 15. Rescheduling date computed by the rescheduling check within tolerance/horizon; can occasionally flag msg 10 with no computable date. Worklists MD06 (snapshot, processing indicator) / MD07 (live) / MD04 (single-material live cockpit). MRP controller = mandatory 3-char MRP-1 material-master field; purchasing group = analogous buy-side field. Firming via manual edit / planning time fence; conversion MD14/MD15 (→PR, auto-firmed), CO40/CO41 (→production).
Microsoft Dynamics 365 SCM (F&O)
Master planning nets to planned orders (proposals). Actions:
Advance / Postpone / Increase / Decrease / Derived (propagate down to
components), gated by the action message time fence and advance/postpone
margins. No explicit Cancel (Decrease→0) and no Create action (a planned
order is the create). Delays/futures: a delayed (futures) date + delay
days when earliest fulfillment is later than requested — a first-class
cannot-meet-date exception, governed by the futures time fence; only propagates
to components once the top-level order is firmed. Firming: manual, auto
(firming time fence), or query-based batch; firmed PO is set to Approved.
Microsoft Dynamics 365 Business Central
Planning Worksheet action-message enum: New, Change Qty., Reschedule, Resched. & Chg. Qty., Cancel (spans purchase / production / assembly / transfer). Separate Warning field: Emergency / Exception / Attention. Dampener period/quantity suppress trivial messages. Planner ticks Accept Action Message then runs Carry Out Action Message (choose planned vs firm planned production orders; create POs/assembly/transfer). Planning Flexibility (Unlimited vs None) controls whether planning may touch a supply line. Planning Worksheet (planners) vs Requisition Worksheet (buyers) — Carry-Out can copy PO/transfer proposals into the Requisition Worksheet when separate teams handle purchasing vs production. Cleanest enum to emulate.
Oracle NetSuite Supply Planning
Supply plan lists suggested POs/WOs/transfers as planned orders. Order recommendations: Reschedule In, Reschedule Out, Cancel, plus create/release. Coded Planning Action Messages (100 QtyOnHand<0, 110 below safety stock, 120 above safety stock, 130 late PO, 140 late WO) on a Planning Messages subtab, reusable in saved searches. Supply Planning Workbench views grouped by subsidiary/location with header-checkbox bulk approve/reject (Perform Selected Actions). 2025.2 added Reschedule In Firm / Reschedule Out Firm / Cancel Firm views (recommendations now cover firm orders too).
Epicor Kinetic
Process MRP → manufacturing suggestions (Planning Workbench, unfirm jobs) and purchasing suggestions (Buyer Workbench). New PO Suggestions vs Change PO Suggestions (Expedite / Postpone / Cancel / Qty change). Reschedule-in delta and reschedule-out delta (days) gate expedite/postpone. Buyer clicks Buy to convert (optionally via requisition); planner firms unfirm jobs. Buyer ID resolution: Part-Site → Part-Class → system default; a buyer sees only their authorized buyers' suggestions/POs.
Infor SyteLine (CSI) & LN
SyteLine: planned orders on the Material Planner Workbench / Planning Detail; firm a planned order → job / PO / PO requisition / transfer; item carries planner code
- buyer. LN: planned orders with Order Status "To be released" / "Not to be released", turned real via Confirm Planned Order; exception messages Reschedule In / Reschedule Out / Cancel Order plus quantity/lead-time/ safety-time exceptions; configured and worked per planner (Exception Message Types by Planner / Exception Messages by Planner).
Carbon Current-State (grounding)
MRP is no longer an edge function — the old Deno mrp function was deleted.
MRP now runs in-process in Node via runMrp exported from @carbon/planning
(packages/planning/src/mrp/mrp.ts, ~1149 lines). The pure BOM-explosion core
(explodeBom) still lives in packages/database/supabase/functions/lib/mrp-engine.ts
and is reached via the @carbon/database/mrp-engine barrel.
Note: .claude/rules/supersession-system.md still references the old
functions/mrp/** path — it is stale for MRP's location.
- The engine emits no action messages.
runMrpwrites only forecast/actual buckets:demandForecast(forecastMethod='mrp'),demandForecastSource(lineage),demandActual,supplyActual. It deletes but never writessupplyForecast(that's written by the user-drivenplanning.updateroutes). - The single "Order" suggestion is computed downstream and never persisted.
SQL RPCs
get_purchasing_planning/get_production_planning+calculate_quantity_to_order(branching onreorderingPolicy) compute an ephemeralquantityToOrder, recomputed on every page load. A client-side mirrorcalculateOrders(ItemReorderPolicy.tsx) additionally emitspolicyName,isASAP, andtriggerValuesper suggestion — the only "why" metadata, thrown away after order creation. - Time horizon: engine forecasts 72 weeks (
WEEKS_TO_FORECAST = 18*4), weekly buckets only; purchasing planning route shows 48 weeks. Today =datetime.today(companyTimeZone). - Consuming action supports only
action === "order"—planning.update.tsx(purchasing + production) explicitly rejects anything else. Purchasing groups planned orders bysupplierId::periodId, finds-or-creates one PO per group (statusPlanned), merges lines, upsertssupplyForecast. Production inserts jobs + methods, upsertssupplyForecast,recalculateJobRequirements(). - No persisted suggestion / action-message table exists — no
purchaseSuggestion/materialRequirement/actionMessage/planningSuggestion. - Trigger: Inngest (not Trigger.dev/DB-cron). Scheduled every 3h
(
packages/jobs/src/inngest/functions/scheduled/mrp.ts,cron: "0 */3 * * *"), per-companyrunMrp(..., userId: "system"), Cloud skips Canceled subscriptions. Manual viaapps/erp/app/routes/api+/mrp.ts(POST,update: "inventory") →runMRPwrapper inproduction.service.ts. - No buyer/planner concept. Generic
assigneeFK exists onpurchaseOrder(and part/customer/supplier), but the planning path never sets it; planned POs carry status/supplier/currency/createdBy only. Supplier defaulting comes fromitemReplenishment.preferredSupplierId+supplierPart. - Relevant tables/enums:
itemReplenishment(per item):preferredSupplierId,purchasingLeadTime,purchasingUnitOfMeasureCode,conversionFactor,lotSize,manufacturingPolicy.itemPlanning(per item+location, unique(itemId, locationId)):reorderingPolicy,safetyStockQuantity,reorderPoint,reorderQuantity,reorderMaximumInventory,minimumOrderQuantity,maximumOrderQuantity,orderMultiple,demandAccumulationPeriod,demandReschedulingPeriod,critical.itemReplenishmentSystem='Buy' | 'Make' | 'Buy and Make'.itemReorderingPolicy='Manual Reorder' | 'Demand-Based Reorder' | 'Fixed Reorder Quantity' | 'Maximum Quantity'.- Planning tables
period,demandForecast,demandActual,supplyForecast,supplyActual,demandForecastSource,demandProjection.
Recommended Approach for Carbon
Modeled on SAP's exception-message split + Business Central's clean enum +
Epicor's Buyer-scoped worklist, adapted to Carbon's reality that it has no
unfirmed planned-order tier (it creates real Planned POs and jobs directly).
Persist a planning action-message / suggestion table keyed by
(itemId, locationId, periodId)(or per suggestion), with an action-type enum and the proposal payload. This is the central new artifact — Carbon's suggestion is ephemeral today.runMrpalready has net requirement, projected balance, supply timing, and lineage in Phase 5–7, so it can write these rows in the existing Phase-7 atomic transaction. Reuse the existingpolicyName/reason/triggerValuesshape (already onplannedOrderValidator) as the persisted "why".Adopt a directional action-type enum (direction-in-the-type reads best for a buyer): follow SAP/D365/Epicor rather than BC's implicit-direction enum. Proposed set: Order (new buy) · Make (new job) · Expedite (pull an existing PO/job in) · Defer (push an existing PO/job out) · Cancel (an existing PO/job no longer needed) · optionally Increase Qty / Decrease Qty. Keep a separate advisory-exception channel (below safety stock, excess/over-supply, cannot-meet-date/past-due, master-data broken) — do not overload the action enum with warnings. (Terminology to confirm with domain glossary — see Open Questions.)
Change-actions target real documents. Because Carbon has no unfirmed tier, Expedite/Defer/Cancel reference an existing
purchaseOrderLine/ job (SAP's firmed-receipt case). The message carries the proposed new date (and/or qty) — a first-class field (SAP's "rescheduling date"). Acting on it edits/cancels that real document.Gate reschedule messages behind a tolerance window (mandatory, §4). Add forward/backward tolerance days (candidate home:
itemPlanning, reusingdemandReschedulingPeriod, or a company-level default) so Expedite/Defer only fire past a threshold. Without this the worklist becomes noise.Add a buyer/planner ownership + assignment model. Follow Epicor's Buyer-ID idea but reuse Carbon's existing generic
assigneepattern where possible. Options to resolve in spec: (a) an owner field on the item (per-item or per-item-location, analogous to SAP MRP controller / purchasing group), with a resolution fallback; and/or (b) anassigneeon each action-message row that a lead can (re)assign. Populate the POassigneewhen an Order action converts. Let the planning worklist filter by assignee ("my actions") and act in bulk.Generalize the consuming action + UI. Extend
planning.update.tsxbeyondaction === "order"to handle expedite/defer/cancel (edit/cancel the referenced document), and extend the planning tables/drawers to render the action type, proposed date, reason, and assignee, with bulk accept/dismiss (NetSuite's Perform-Selected-Actions). Preserve the existing "Order" behavior as one action type among several.Keep the two module views (purchasing planning vs production planning) as the buyer/planner split (BC's Planning vs Requisition Worksheet analog): purchasing view shows buy actions to buyers, production view shows make actions to planners.
Open questions to carry into the spec
- Terminology: confirm action-type names against
@carbon/glossarydomain terms ("Expedite"/"Defer" vs "Reschedule In/Out" vs "Pull In/Push Out"; "Order" vs "New"). SAP/Epicor say expedite/de-expedite; NetSuite/LN say reschedule in/out. - Assignment axis: per-item owner (SAP MRP-controller style) vs per-message
assignee vs both? Where does the owner field live —
itemReplenishment(buy-side) /itemPlanning(per-location) / a newbuyer/plannerreference? - Do we introduce an unfirmed "planned order" tier, or keep creating real
PlannedPOs/jobs and treat every change-action as operating on real documents? (Recommendation: keep Carbon's real-document model; it's simpler and matches SAP's firmed-receipt semantics — but this is a scope decision.) - Persistence vs recompute: persist action messages (needed for assignment + bulk work + dismissal state) vs continue computing on read. (Recommendation: persist — assignment and dismissal state require it.)
- Change-quantity actions: include Increase/Decrease Qty, or fold into Expedite/Defer + Cancel like SAP does? (SAP folds; D365/Epicor split.)
- Advisory exceptions scope: which exceptions ship in v1 (below safety stock, over-supply, past-due/cannot-meet-date, master-data broken)?
- Tolerance home + defaults: company-level default days vs per-item override.
Sources
SAP
- MRP exception 30 vs 10 (firmed vs planned): https://community.sap.com/t5/enterprise-resource-planning-q-a/mrp-exception-message-difference-between-30-10/qaq-p/10550514
- KBA 1698291 — messages 10/15/20/26/30 not displayed in MD04: https://userapps.support.sap.com/sap/support/knowledge/en/1698291
- KBA 3542305 — msg 10 without reschedule date: https://userapps.support.sap.com/sap/support/knowledge/en/3542305
- KBA 2609209 — reschedule exceptions 10 and 30: https://userapps.support.sap.com/sap/support/knowledge/en/2609209
- Exception 20 vs 10 in MD04: https://community.sap.com/t5/enterprise-resource-planning-q-a/differences-between-exception-20-and-10-in-md04/qaq-p/10399918
- Froggy's SAP — exception messages 10/15/20: http://froggysap.blogspot.com/2014/07/sap-mrp-understanding-exception.html
- SAPinsider — manage MRP exception messages: https://sapinsider.org/manage-material-requirements-planning-exception-messages-in-sap/
- SAP supply chain — exception-minded business (8 groups, MD06 vs MD07): http://sap-supply-chain-ideas.blogspot.com/2012/05/moving-towards-exception-minded.html
- MD07 exception monitor: https://blogs.sap.com/2022/07/02/md07-mrp-exception-monitor-collective-stock-requirement-list/
- Converting planned orders → PRs (MD14, auto-firm): https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/9905622a5c1f49ba84e9076fc83a9c2c/49106354c08b063de10000000a441470.html
- Planned orders get firmed (PTF firming): https://community.sap.com/t5/enterprise-resource-planning-q-a/planned-orders-get-firmed/qaq-p/9599784
- Firming type in MRP types: https://www.stechies.com/what-is-firming-type-in-the-mrp-types/
- Define MRP controllers: https://www.saponlinetutorials.com/define-mrp-controllers-material-requirement-planning/
- Purchasing group vs MRP controller: https://community.sap.com/t5/enterprise-resource-planning-q-a/purchasing-group-and-mrp-controller/qaq-p/4888880
- MRP Exception Monitor (Fiori) PDF: https://help.sap.com/doc/80c6ad471d2d42598c766e3ef5c1fac4/2024.1/en-US/ERM-EN-PUBLIC.pdf
Microsoft Dynamics 365
- SCM master planning home: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/master-planning-home-page
- SCM delays (futures messages): https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/delays
- AX 2012 about action messages (Advance/Postpone/Increase/Decrease/Derived): https://learn.microsoft.com/en-us/previous-versions/dynamicsax-2012/appuser-itpro/about-action-messages
- SCM master planning performance (time fences): https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/master-planning-performance
- SCM firm planned orders: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/planned-order-firming
- SCM coverage settings: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coverage-settings
- SCM maintain/filter planned orders: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/maintain-planned-orders
- BC about planning functionality: https://learn.microsoft.com/en-us/dynamics365/business-central/production-about-planning-functionality
- BC run MPS/MRP (action-message enum, Carry Out): https://learn.microsoft.com/en-us/dynamics365/business-central/production-how-to-run-mps-and-mrp
- BC planning journal action messages (plain-language): https://usedynamics.com/business-central/planning/action-messages/
Oracle NetSuite
- Planning Action Messages (coded exceptions, Reschedule In/Out): https://docs.oracle.com/en/cloud/saas/netsuite/ns-online-help/section_3865354301.html
- Supply Planning overview: https://docs.oracle.com/en/cloud/saas/netsuite/ns-online-help/section_159171867422.html
- Setting up Reschedule Out messages: https://docs.oracle.com/en/cloud/saas/netsuite/ns-online-help/article_162557605659.html
- Supply Planning Workbench: https://docs.oracle.com/en/cloud/saas/netsuite/ns-online-help/section_159187932855.html
- Creating a Planning Workbench View: https://docs.oracle.com/en/cloud/saas/netsuite/ns-online-help/article_164313117883.html
- NetSuite 2025.2 supply chain enhancements: https://www.netsuite.com/portal/resource/articles/supply-chain-management/netsuite-2025-2-optimizes-supply-chain-planning-and-execution-efficiency.shtml
- Rand Group — supply planning enhancements (bulk approve): https://www.randgroup.com/insights/oracle-netsuite/netsuite-supply-planning-and-allocation-enhancements/
Epicor
- New vs Change PO Suggestions: https://www.epiusers.help/t/opinions-wanted-new-po-suggestions-vs-change-po-suggestions/101881
- Change PO Suggestions: https://www.epiusers.help/t/change-po-suggestions/136427
- Expedite from Change PO Suggestions: https://www.epiusers.help/t/expedite-pos-from-change-po-suggestions-benefit-or-liability/90485
- Reschedule out/in delta parameters: https://www.epiusers.help/t/reschedule-out-and-reschedule-in-parameters-affect-on-po-sugestions/116671
- Buyer field / Part-Plant→Part-Class→default: https://www.epiusers.help/t/buyer-field-in-new-po-suggestions/44378
- Filtering PO Suggestions by Site and Buyer: https://www.epiusers.help/t/filtering-po-suggestions-with-different-sites-and-buyers/97142
- MRP unfirming jobs: https://www.epiusers.help/t/mrp-is-unfirming-jobs/102553
- Production Management (workbenches): https://tomerlin-erp.com/knowledge-production-management/
- Kinetic Planning & Scheduling: https://www.epicor.com/en-us/products/enterprise-resource-planning-erp/kinetic/planning-and-scheduling/
Infor
- SyteLine planning activity / firm planned orders / Order Action Report: https://csi.lamartcorp.com/syteline/language/en-us/mergedProjects/sl_invprod/forms/mrptopic/planning_activity.htm
- SyteLine APS overview: https://www.visualsouth.com/blog/advanced-planning-and-scheduling
- SyteLine PO requisitions from planned orders: https://inforcloudsuite.blogspot.com/2015/04/purchase-order-requisitions.html
- LN order/order-planning exception messages (Reschedule In/Out, Cancel Order): https://docs.infor.com/ln/10.5/en-us/lnolh/help/cp/onlinemanual/000069.html
- LN types of exception messages: https://docs.infor.com/ln/10.5/en-us/lnolh/help/cp/onlinemanual/000063.html
- LN Process Exception Messages (cprao1220m000): https://docs.infor.com/ln/10.3/en-us/lnolh/help/cp/rao/cprao1220m000.html
- LN Exception Message Types by Planner (cprao1110m000): https://docs.infor.com/ln/10.6/en-us/lnolh/help/cp/rao/cprao1110m000.html
- LN Planned Order (cprrp1600m000), Confirm/Order Status: https://docs.infor.com/ln/10.4/en-us/lnolh/help/cp/rrp/cprrp1600m000.html
- LN Planned Orders (cprrp1100m000): https://docs.infor.com/ln/10.5/en-us/lnolh/help/cp/rrp/cprrp1100m000.html