MRP v2: Planner UI & Data/Workflow Model — Best-Practices Survey

Summary

Surveyed how eight MRP systems generate planned orders, cascade them through multi-level BOMs, and present the plan to a planner — to inform Carbon's move from a quantity-sorted per-item reorder worklist (get_production_planning + calculate_quantity_to_order) to real planned-order MRP (spec .ai/specs/2026-08-22-mrp-v2-planned-order-generation.md). The enterprise systems (SAP, Oracle, NetSuite, Dynamics 365, Infor LN/M3) are strikingly consistent on the data/workflow model — planned order → firm → release, low-level-code single-pass explosion, pegging, action/exception messages, the six-row time-phased record, and a lot-sizing-then-modifiers pipeline whose output (not the raw net requirement) explodes to children. The SMB cloud tools (Katana, MRPeasy, Fishbowl) diverge sharply on UI: they hide the time-phased grid behind a single derived date ("stockout" / "order-by" / "days-of-cover"), present each shortage as a dated, decision-ready row sorted by urgency with a one-click Make/Buy → pre-filled draft → approve path, and show the multi-level chain as a drill-down rather than a matrix. The recommendation: adopt the enterprise data model and standard terminology, but lead the UI with the SMB dated-decision pattern, offering the full time-phased matrix as an expert drill-down.

Competitors Surveyed

  • SAP S/4HANA (+ ECC) — the enterprise reference; MRP Live, MD04/MD05/MD07, MD09 pegging, exception messages, planning time fence, lot-sizing procedures.
  • Oracle Fusion Cloud Supply Planning / Planning Central (+ legacy ASCP) — order modifiers precedence, hard/soft pegging, Planner Workbench.
  • NetSuite Supply Planning (MRP) — the closest enterprise peer to Carbon's SMB audience running a full multi-level MRP; Supply Planning Workbench, action messages, lot-sizing methods.
  • Microsoft Dynamics 365 SCM (Planning Optimization) — regenerative-only cloud engine, coverage groups/codes, action + futures messages, explosion/pegging tree.
  • Infor LN & M3 — Planned→Firm Planned→Confirmed→Released lifecycle; M3's coded A/B/C action-message taxonomy.
  • Katana MRP, MRPeasy, Fishbowl — the SMB/cloud UX cluster (same audience as Carbon); how they make MRP approachable for non-APICS planners.
  • Canonical MRP (APICS/ASCM) — the standard time-phased record, LLC, lot-sizing techniques, pegging, firm planned orders, action messages — the source of correct terminology.

Key Consensus Patterns

1. Planned order = first-class, disposable, typed suggestion

Every system generates planned orders typed by sourcing: planned production / planned purchase / planned transfer (SAP: planned order vs purchase requisition; Oracle/NetSuite/Dynamics/Infor: make/buy/transfer planned orders). A planned order is freely re-planned, rescheduled, or deleted by every run until firmed. Rationale: the plan must be disposable so regen can rebuild it without destroying human decisions — exactly the durable-planned-order layer the Carbon spec proposes (validates the new plannedOrder entity over the period-bucketed supplyForecast).

2. Lifecycle: Planned → Firm → Released/Converted

Universal three-state lifecycle. Firm freezes quantity + timing against re-planning but the order still explodes to components and still emits messages (SAP firming indicator *; Oracle/NetSuite firm checkbox; Dynamics manual/auto/query firming; Infor LN "Firm Planned"→"Confirmed"). Release/convert turns it into a real work order / PO / transfer (SAP CO40/CO41/MD15; Oracle/NetSuite/Dynamics "release"/"firm"; Infor "Confirm → transfer to execution"). Rationale: planners override the computer to honor supplier minimums, level load, or protect commitments, without leaving MRP logic. Validates Carbon's Planned/Firm/Released.

3. Auto-firm inside a planning time fence (the "nervousness" guard)

Every enterprise system has a near-term planning time fence / firming horizon inside which MRP stops auto-creating or rescheduling orders — protecting the shop from "nervousness" (small demand changes cascading into churn). SAP firming types P1–P4; Dynamics firming time fence (evaluated on order/start date, not due date — a documented trap); Infor firm-planned status acting as a fence. Not in the current Carbon spec — recommend adding the hook (per-location firm-horizon days), even if v1 ships manual-firm-only.

4. Multi-level cascade = one low-level-code sweep; the lot-sized qty explodes

LLC processing (each item planned at its deepest BOM appearance, top-down) makes a single pass correct for acyclic BOMs — no iteration — because every parent is processed before the child, so the child's gross requirements are complete when it nets (SAP LLC; canonical topological-sort proof). Critically, the lot-sized order quantity — not the raw net requirement — is what explodes to components (SAP: dependent requirement = inflated parent order qty × BOM qty; canonical: planned-order-release drives child gross requirements). SAP labels the surplus that pegs to nothing "quantity without source" (MD09). Validates the spec's core engine change and the fix to mrp-engine.ts:269.

5. Pegging: bottom-up + top-down, single-level + full, soft vs hard

Pegging links supply↔demand as an audit trail ("why does this exist / what does it support"). Single-level (immediate parent) vs full/multi-level (chained to the top independent demand). Soft peg (a supply serves one-or-many demands) vs hard peg (dedicated supply for a specific customer/project — SAP account-assignment/individual segment, Oracle hard peg, Infor hard pegging). Surfaced as a graphical tree (Oracle Graphical Pegging, Dynamics Explosion form, NetSuite hierarchical drill-down, SAP MD09). Validates plannedOrderPeg; note Carbon already hard-pegs MTO jobs to sales-order lines (job.salesOrderLineId).

6. Action / exception messages — the planner's real worklist

The plan is worked as a message queue, not an item list. The canonical set, with each vendor's names:

Canonical SAP Dynamics Infor M3
Release (release/convert) Firm A1/A2 Release
Reschedule-in / Expedite 10 Bring forward Advance B1/B3 Reschedule in
Reschedule-out / De-expedite 15 Postpone Postpone B2/B4 Reschedule out
Cancel 20 Cancel (Decrease→0) B7 Delete order
Increase / Decrease qty 42 changed Increase/Decrease B5/B8
Past due 06/07 date in past (Delays) C1 delayed
Delay / Futures warning — Futures → "Delays" C2/C3 will be delayed

Two design-critical points: (a) reschedule/cancel messages apply to real open orders (scheduled receipts), not just planned orders — MRP prefers rescheduling an existing job/PO over creating a new planned order; (b) messages are grouped/prioritized and the highest-priority one shows on the element line (SAP), the rest on drill-down.

7. Time-phased record — the six canonical rows (enterprise) vs one derived date (SMB)

The standard MRP record (canonical + SAP MD04 "period totals" + Oracle Horizontal Plan + Dynamics "Period" tab): Gross Requirements · Scheduled Receipts · Projected Available Balance · Net Requirements · Planned Order Receipts · Planned Order Releases, computed left-to-right per bucket (PAB end-of-period; scheduled receipts = real open orders; planned orders = suggestions). SAP MD04 pairs this with an individual-lines view — a running available-balance ledger sorted by date, exception message on the line where the balance goes negative. The SMB tools deliberately omit this grid and substitute a single stockout date / order-by date / days-of-cover per item.

8. The SMB "dated decision row" is the UX the quantity worklist lacks

Katana's Replenishment screen and MRPeasy's Critical On-Hand are the models: each row is a dated decision — item, supplier (resolved), shortage qty, stockout date, suggested order-by date, suggested qty, cost — sorted by urgency (time), not quantity, containing only items needing action, with a one-click Buy/Make → pre-filled draft → approve path (individually or batched, Katana up to 50). Multi-level shows as a drill-down: an ingredient's "Not available" expands to the missing sub-parts, and the Expected date is literally the linked PO's arrival or sub-MO's deadline. Katana adds priority-based availability (dragging MO priority live-recomputes every order's availability — a lightweight allocation/peg substitute). None expose a formal firm flag; MRPeasy's "in-progress" status is the de-facto lock.

9. Lot-sizing: a small standard taxonomy + order modifiers

All converge on: lot-for-lot, fixed order quantity, period-of-supply / POQ / fixed-period, min/max (replenish-to-max), then order modifiers applied on top in precedence: minimum, maximum (split), multiple/rounding (round up), standard qty, scrap/yield. Carbon's four reorderingPolicy values map cleanly (see below). Dynamics bundles these into a reusable coverage group attached to items — heavier than Carbon needs (itemPlanning already holds them per item/location).

10. Regenerative-only, made fast + event-driven — net-change is being abandoned

Dynamics Planning Optimization dropped net-change entirely — regenerative-only, justified by being fast enough (in-memory cloud service) to regenerate during office hours. Validates Carbon staying regenerative (full company run) and investing in fast + event-driven scoped regen rather than building incremental net-change.

Answers to Research Questions

  1. Planned-order generation & multi-level cascade — Net requirements → lot-size → planned order → BOM-explode the lot-sized qty to children, processed in LLC order, one top-down pass (acyclic). Universal. (SAP, canonical.)
  2. Lifecycle (planned/firm/released) — Universal three states; firm freezes qty+date but still explodes and messages; release converts to real order. (All.)
  3. Pegging — Bottom-up + top-down, single vs full, soft vs hard; surfaced as a graphical tree. (Oracle, SAP, Dynamics, Infor.)
  4. Exception / action messages — Standard set = Release, Expedite/Reschedule-in, De-expedite/Reschedule-out, Cancel, Increase, Decrease, Past-due, Delay/Futures; worked as a filtered queue; apply to open orders too. (Canonical, SAP, Dynamics, M3.)
  5. Time-phased matrix — Six canonical rows (GR/SR/PAB/NR/POR/POL) in enterprise; SMB substitutes a single derived date. (Canonical, SAP; Katana/MRPeasy.)
  6. Lot-sizing — L4L / FOQ / POQ / min-max + modifiers (min/max/multiple/scrap); the modified qty explodes downstream. (All.)

Competitor-Specific Details

  • SAP — MD04 (live) vs MD05 (run snapshot); MD07 collective by MRP controller/exception group; Fiori "Monitor/Manage Material Coverage" cockpit; S/4HANA 2025 "Accept the MRP results" (mark reviewed); "quantity without source" = lot-sizing surplus that pegs to nothing; planning time fence firming types P1–P4.
  • Oracle — order-modifier precedence (Fixed Days Supply → FOQ → Fixed Lot Multiplier → Min → Max(split) → Rounding); hard vs soft peg as an item attribute; Graphical Pegging.
  • NetSuite — Supply Planning Workbench (review/modify/create/release, bulk approve, hierarchical peg drill-down); reschedule-in/out day thresholds; steers customers from legacy reorder-point + Time-Phased Planning to MRP.
  • Dynamics 365 — Planning Optimization (regenerative-only, in-memory); coverage group + coverage codes (Manual/Per requirement/Per period/Min-Max/Priority/Decoupling); Action messages (Advance/Postpone/Increase/Decrease/Derived) + Futures→"Delays"; Explosion pegging tree; firm on order-date not due-date.
  • Infor — LN Planned→Firm Planned→Confirmed→Released + Demand Pegging (hard/soft, up/down browsers); M3 coded A/B/C action messages worked in RPS001/002/005 with temporary deactivations.
  • Katana — Replenishment screen (supplier/stockout-date/missing/suggested-qty/cost/order-by, urgency-sorted), one-click Buy/Make → draft (batch ≤50), priority-based availability, sub-MO chain via Ingredients Availability drill-down.
  • MRPeasy — auto-cascades multi-level BOM (sub-assembly ops nested inside the parent MO), Critical On-Hand report = the shortage worklist, "Check Stock and Book Items" one-click MO/PO generation, in-progress = de-facto lock.
  • Fishbowl — reorder-point outlier (min-qty thresholds, auto-draft PO, exception reports, email/SMS alerts); markets itself as replenishment "without the complexity of full MRP."

Recommended Approach for Carbon

  1. Keep the enterprise data model (validates the spec): plannedOrder (Make/Buy, typed, disposable) with Planned → Firm → Released; plannedOrderPeg (soft peg; MTO job↔sales-line is the existing hard peg). Adopt standard terms — planned order, firm planned order, release, low-level code, gross-to-net, planned order receipt/release, pegging, action message.
  2. Fix the engine as specced — single LLC sweep (the existing for level loop), seed reorder need at each item's level, and explode the lot-sized order quantity (computePlannedOrderQuantity), not raw net requirement.
  3. Map the four existing policies to standard names (keep the policies, no new enum): Manual Reorder→Manual · Demand-Based Reorder→lot-for-lot/net-requirement · Fixed Reorder Quantity→fixed order quantity · Maximum Quantity→min/max (replenish-to-max); modifiers (min/max OQ, orderMultiple, lotSize, scrap) applied on top. Note period-of-supply/POQ as a future addition, not v1.
  4. Lead the UI with the SMB dated-decision pattern — the default plan surface is a list of decision-ready rows sorted by urgency (order-by date), not quantity: item, supplier, shortage, stockout/order-by date, suggested qty, cost, status, one action chip; one-click Release (Make→job, Buy→PO) → pre-filled draft → approve, batch and whole-cascade. Only action-needed rows by default.
  5. Offer the full time-phased matrix as the expert drill-down — the six canonical rows (GR/SR/PAB/NR/POR/POL) per bucket + the SAP-style running-balance line view; this is view #3, not the landing page. Substitute a single stockout/order-by date on the worklist rows so non-experts never need the grid.
  6. Action messages are a computed worklist over planned orders AND open orders — adopt Release / Expedite (reschedule-in) / De-expedite (reschedule-out) / Cancel / Increase / Decrease / Past-due / Delay. v1 can ship Release + planned-order exceptions; deriving reschedule messages on real open jobs/POs is phase 2 (it interacts with the finite scheduler, which owns job dates).
  7. Cascade = drill-down tree (Katana model) — each level shows its Expected/order-by date pointing at the child planned order / linked PO; reuse the existing job/method BOM-tree rendering. Surface "quantity without source" (lot-sizing surplus) as a labeled node so over-production is explainable.
  8. Add a planning-time-fence hook — a per-location firm horizon inside which the engine auto-firms (or won't churn) planned orders; v1 may ship manual-firm-only but design the field. Evaluate the fence on the order's release/start date (Dynamics trap).
  9. Stay regenerative + event-driven (Dynamics Planning Optimization precedent) — don't build net-change; invest in fast full regen + notifyScheduleInputsChanged-style scoped re-plan on demand/supply changes.
  10. Small wins to copy — "mark reviewed / accept results" (SAP S/4HANA 2025) on a planned order; batch-release up to N (Katana); email/SMS shortage alert (Fishbowl) reusing Carbon's notification system.

Sources

SAP — Classic vs MRP Live · BOM explosion in MRP · Firming / Planning Time Fence · Firming types P1–P4 · MD09 pegging · MD04P pegging · Exception messages · MD04 vs MD05 · Manage Material Coverage F0251A · Lot-size calculations

Oracle — Planning Central datasheet · Order modifiers · Item attributes & order modifiers 25D · Planning exceptions · Graphical Pegging · Planner Workbench

NetSuite — Supply Planning Workbench · Supply Planning process · Action messages · Create orders from supply plans · MRP product page · Improved lot sizing / lead-time offset (RSM)

Dynamics 365 — Master planning architecture · Master plans · Planned order firming · BOM explosion · Net requirements & pegging · Coverage settings · Action messages

Infor — LN order statuses · LN Planned Orders session · LN item order data / lot-sizing · M3 action messages A/B/C · M3 planning policies/order types

SMB cloud — Katana replenishment & order suggestions · Katana AI replenishment · Katana MO priorities · Katana make-to-order / sub-MOs · Katana ingredients availability · MRPeasy multi-level BOM/scheduling · MRPeasy production planning · MRPeasy stock replenishment · Fishbowl MRP guide

Canonical (APICS/ASCM) — Time-phased record / rows · Scheduled receipt · MRP text Ch.4 (U. Houston) · Low-level code · Lot-sizing methods · Pegged requirements · Time fences