Quote Lead Time Prediction (Capable-to-Promise) Research: Best Practices Survey

Summary

Surveyed how SAP (ATP, MATP, CTP/SBC), Oracle Global Order Promising, Microsoft D365 SCM and Business Central, job-shop ERPs (Epicor Kinetic, Infor SyteLine and VISUAL, JobBOSS², ProShop, Cetec), Odoo, and modern quoting tools (Fulcrum, MRPeasy, Katana, Paperless Parts, Xometry, Protolabs) compute a promised lead time for a make-to-order line. Three tiers exist: policy lead time (a typed days value, optionally with priced expedite tiers — Odoo, Paperless Parts, marketplaces); material-driven ATP (stock plus replenishment/BOM lead time, infinite capacity — SAP classic ATP and MATP, Oracle lead-time mode, BC CTP, D365 ATP); and capacity-driven CTP (a temporary order is exploded and finitely scheduled into the live plan and the earliest feasible finish returned — SAP CTP/SBC, Oracle Make-CTP, D365 CTP, Epicor, SyteLine, Fulcrum, ProShop). Every CTP product runs it on sales orders; only SyteLine, VISUAL and Cetec expose it on a quote/estimate line, and then as a date only. No vendor holds capacity for a quote. Lead time is universally counted in working days to ship, with pick/pack/transit added separately, and purchased-material lead time and capacity are two constraints of which the later wins.

Competitors Surveyed

  • SAP S/4HANA / APO — the reference: classic ATP with replenishment-lead-time fallback, MATP, finite CTP/SBC, backward-then-forward delivery scheduling.
  • Oracle Fusion GOP / EBS ASCP — three promising modes; Make-CTP with resource capacity; non-committal Check Availability vs committing Schedule.
  • Microsoft D365 SCM / Business Central — the delivery-date-control ladder; BC's what-if CTP with accept-to-reserve.
  • Epicor Kinetic, Infor SyteLine/VISUAL, JobBOSS², ProShop, Cetec — job-shop CTP as a temp-job simulation the estimator accepts.
  • Odoo 17 — pure lead-time policy; the counter-example.
  • Fulcrum, MRPeasy, Katana, Paperless Parts, Xometry, Protolabs — one-click finite simulation vs customer-selected expedite tiers.

Key Consensus Patterns

1. A ladder of promising modes, chosen per item and per line

  • D365: Delivery date control = None / Sales lead time / ATP / ATP + Issue margin / CTP / Batch CTP — global default, per-product override, per-line override. "At a minimum, CTP offsets delivery dates to the sales lead time."
  • Oracle: ATP-rule promising mode = Infinite / Lead time based / Supply chain availability search, plus a "Search components and resources" flag that turns on Make-CTP.
  • SAP: classic ATP (stock + receipts inside the replenishment lead time; beyond RLT everything is assumed available) → MATP → CTP.
  • Rationale: CTP is slow ("the CTP calculation isn't as fast as the ATP calculation") and only pays off for make/assemble-to-order items.

2. CTP = explode a temporary order and finitely schedule it into the live plan

  • SAP: "Temporary planned orders are created … Capacities are then taken into account. A feasible availability date is determined in PP/DS from the result of scheduling these planned orders." PP/DS modes: find slot (first gap in the planning direction), insert, squeeze in, infinite.
  • D365: "CTP functionality is based on the explosion function" — BOM + route through the dynamic plan, finite capacity inside the capacity time fence, purchase lead times, transport days, safety margins.
  • Epicor: CalculateCTP builds an unfirm job and rough-cut finite-schedules it, honouring production buffers, queue/move, Receive Time, planning time fence and constrained-material lead times; "runs against the actual schedule and drops in the operations where it can and then returns a date."
  • SyteLine: Get ATP/CTP inserts the demand "into a temporary copy of the APS plan" at the due date; finite APS gives a "worst case … against an already loaded schedule."
  • Fulcrum: "simulates when a job would get finished if scheduled at that moment … based on the priority level of the job."

3. Backward from the requested date; forward from today when infeasible

  • SAP SD: requested delivery − transit − loading − transportation lead time − pick/pack = material availability date; if that is in the past or unconfirmable, forward-schedule from the earliest ATP date and re-add the four times, each rounded on its own factory calendar.
  • BC: "requested delivery date − shipping time = planned shipment date; − outbound whse. handling time = shipment date"; if unavailable, calculate forward and write the earliest Shipment Date.
  • D365: the Available ship and receipt dates dialog pops when the requested date cannot be met and the user picks.
  • Rationale: "can we hit this date?" and "earliest feasible date" are one engine run in two directions.

4. Requested vs confirmed; the system writes the confirmed date, the user may only loosen it

  • SAP: confirmed schedule lines; the user may push the date later or reduce quantity, never earlier or larger.
  • Oracle: Requested vs Scheduled (GOP output) vs Promised (tracking) dates; EBS Promise Date modes include "First Schedule Date" (frozen) and "Dependent on Schedule Date" (recomputed).
  • D365: Confirmed ship/receipt date set on every save of a CTP line, but re-promised only when the existing promise can no longer be met — a smaller quantity keeps the original date.
  • SyteLine: Projected date is recomputed every APS run; the due date is never overwritten; a Late Alert compares the two.

5. Temporary supply becomes real only on save/accept; quotes never hold capacity

  • SAP: CTP temporary orders "exist only in the check session; converted to permanent on save, deleted otherwise." Quotation schedule line BN "No MRP" transfers nothing; BP does, and the valid-to date does not release it — a known trap.
  • BC: accepting CTP dates creates "a planning line and a reservation entry"; declining leaves nothing.
  • D365: CTP writes planned orders and capacity reservations, but plan runs historically replanned them — hence "Keep supply for confirmed demand" (10.0.48) and "Protect confirmed CTP dates" (GA Sep 2026). "Delivery date control method is not supported for a sales quotation line."
  • Epicor: ConfirmCTP firms the job; cancel discards it; "quotes are not associated with a job." SyteLine: an accepted CO line is incrementally planned, but "estimate lines are not incrementally planned." Oracle EBS: scheduling level "ATP Only" for inquiry-type transactions.
  • Rationale: quote win rates are well below 100 %; holding capacity per quote starves real orders. Quote expiry is cosmetic everywhere (Odoo: a ribbon; Hubs: price "valid for 30 days").

6. Material lead time and capacity are separate constraints; the later wins

  • SAP MATP: each component checks against its own rule (a bought part with no stock confirms at the end of its RLT); the header is forward-scheduled from the latest component date.
  • Oracle: Buy-CTP applies supplier lead times as a hard constraint; Make-CTP checks resources; the promise is the max.
  • Odoo 17: days_to_prepare_mo = Compute → "the longest lead time among all the components listed on the BoM."
  • Cetec / VISUAL / Fulcrum: material availability gates operation start inside the finite engine.

7. Working days, calendars, and a post-production buffer

  • SAP: scheduling-margin-key floats (before/after production, opening period) in workdays; safety time in working days.
  • D365: receipt / issue / reorder margins on working-day calendars; issue margin = ship-prep buffer; transport days by mode of delivery.
  • BC: Offset (Time) + inbound/outbound warehouse handling + shipping time. Oracle: a non-business-day result moves to the previous working day.
  • Odoo: the outlier — "lead times are based on calendar days … do not consider weekends, holidays, or work center capacity."
  • Protolabs / Xometry: lead times in business days to ship; shipping assumed separately (1-day expedite / 2-day standard).

8. Expedite is a priority, priced as tiers

  • Paperless Parts: standard lead time plus "Days Faster" options each with a % markup, "expressed as relative days and percentage markup"; the customer picks; leaving standard blank gives each quantity break its own lead time.
  • Xometry: Economy / Standard / Expedited — "expedited orders receive prioritization in all aspects of order fulfillment." SyteLine: Expedited Fixed/Variable lead times feed Get CTP.
  • SAP / Oracle / D365: no named expedite mode; forward scheduling from today is the fastest date, and priority reallocation happens later (aATP backorder processing).

Answers to Research Questions

  1. Inputs — Routing standard times via work-center formulas (SAP, D365, Epicor, SyteLine, Fulcrum); the live finite load (all CTP products); component supply and supplier lead time (SAP MATP/RLT, Oracle Buy-CTP, Odoo days_to_prepare_mo, Epicor, Cetec); factory/shift calendars (all but Odoo); buffers (SAP floats + safety time, D365 margins, Odoo security leads, BC handling times, Epicor production buffers); a policy floor (D365 sales lead time, SAP RLT with no explosion, Protolabs per-process standard, SyteLine Fixed + Variable + Paperwork + Dock-to-Stock).
  2. Modes — Infinite (SAP classic ATP, Oracle Infinite/Lead-time, D365 Sales lead time/ATP, SyteLine infinite APS); finite earliest feasible (SAP CTP, Oracle supply-chain search + resources, D365 CTP, Epicor, SyteLine finite, Fulcrum, Cetec); "can we hit this date" (SAP backward scheduling, BC backward verify, D365 dialog on miss, SyteLine check-mark if projected ≤ due, ProShop phantom order); best case (job priority in Fulcrum; priced tiers in Paperless Parts/Xometry/Protolabs; Cetec conservative/optimistic; no ERP names a first-in-queue mode).
  3. Surfacing — A system-written confirmed/projected date beside the requested one, accepted or loosened (SAP, Oracle, D365, BC, SyteLine); a suggestion the estimator types over (MRPeasy "Estimate costs and dates", Katana auto deadline, Odoo read-only expected_date + editable commitment_date, Epicor's manual quote Lead Time field). Per quantity break only in Paperless Parts; Protolabs gives "the same quoted lead time" regardless of quantity. Recompute: D365 only when infeasible; SyteLine every APS run (reference only); Oracle frozen or live by mode; the rest on demand.
  4. Quote-time reservation — None. Temporary supply materialises on order save/accept (SAP, BC, D365, Oracle Schedule, Epicor ConfirmCTP, SyteLine CO line). SyteLine and Cetec answer on an estimate line but plan nothing; VISUAL loads quotes only as explicit what-if orders. Expiry releases nothing anywhere, and SAP BP quotes are a cautionary tale.
  5. Materials vs capacity, rounding, shipping — Promise = max(material date, capacity date), header forward-scheduled from the later (SAP MATP two-step, Oracle, Epicor). Working-day rounding on the factory/shift calendar (SAP, D365, BC, Oracle, SyteLine M-days); Odoo is calendar-day. Ship vs delivery separated by pick/pack + loading + transit (SAP), outbound handling + shipping time (BC), issue margin + transport days (D365); marketplaces quote days to ship.

Competitor-Specific Details

SAP — Classic ATP never reads routing. MATP stores an "ATP tree", not a receipt. CTP is incompatible with safety stock, period lot sizes and backorder processing. S/4HANA SBC (2022+, aATP + ePP/DS licences) recreates supply on every MTO recheck.

Oracle — Infinite-availability time fence (beyond it, promise on request date) and ATP time fence (inside it, search existing supply before CTP). Resource need = qty × usage / (yield × efficiency × utilization). Fusion 25D pulls scheduled dates earlier when supply arrives early, gated by an Override Schedule flag.

Microsoft — D365 "Near real-time CTP" (10.0.41+) computes in the background per line save; "Batch CTP" every N minutes with a Not ready/Ready status. BC CTP applies only to the uncovered remainder ("10 ordered, 6 available → CTP on 4") and requires the item flagged Critical.

Job shops — SyteLine: lead-time start = due − FLT − int(VLT × qty / hrs per day + .499). VISUAL: the one scheduler that natively loads "planned orders and quotes." JobBOSS²: "auto-default the promise date to lead times" is still a user idea. ProShop: lead time typed; capacity checked by phantom job placement. Cetec Build Estimate: start + ship date from on-hand, component lead times and labour, view-only.

Odoo — expected_date = date_order + customer_lead, nothing else; MO/PO dates back-schedule from it; the MO Plan button forward-schedules work orders on work-center calendars but never moves the SO date.

Recommended Approach for Carbon

Carbon already has the hard part: a forward-ASAP finite scheduler over capacityReservation (packages/planning/src/scheduling/run-schedule.ts; runExpediteWhatIf with persist:false returning { projectedCompletionAt, cause }), quoteOperation rows carrying setup/labor/machine times and work centers column-for-column with jobOperation, itemReplenishment.leadTime for purchased parts, and an unused capacityReservation.scenarioId. What is missing is the glue.

  1. A mode ladder per line, not a replacement (D365). Keep the typed quoteLinePrice.leadTime as the policy mode and add a computed suggestion beside it, floored at an item/company minimum lead time.
  2. CTP = a what-if run of the existing engine seeded from quoteOperation, not a job (SAP temporary planned order; SyteLine "temporary copy of the plan"; Fulcrum). Generalise runExpediteWhatIf to take a synthetic operation set (quote make method × quantity) placed at end of queue over the live reservation snapshot, persist:false. Return { promiseDate, confidence, cause } — the getJobPromiseDate contract already exists with no caller.
  3. Two modes from one engine. Earliest feasible = end of queue; best case = the synthetic job ordered first (what the expedite what-if already does). "Can we hit this date?" = feasible ≤ requested, reporting cause (bottleneck work center vs material) — no surveyed vendor computes "what would have to move" for a quote, and neither should Carbon in v1.
  4. Material-driven floor (SAP MATP; Odoo days_to_prepare_mo). Take max over quoteMaterial Buy lines of itemReplenishment.leadTime net of on-hand at the quote location, start the synthetic operations no earlier than that, and say which constraint won.
  5. Per quantity break, on demand, frozen (Paperless Parts; Oracle "First Schedule Date"). Run per pricing-grid row when the estimator asks, write the accepted value into leadTime, and record leadTimeSource: 'system' | 'manual' next to the existing priceSource. Never auto-recompute a sent quote; on reopen offer "recalculate" with the delta.
  6. No quote-time reservation. Unanimous. Do not write scenarioId rows for quotes; a soft booking, if ever wanted, is a sales-order feature (D365 "Keep supply for confirmed demand").
  7. Working days plus a ship buffer. Convert the engine's completion timestamp to whole business days on the location shifts (need-by-calculator.ts workingDayTest), add a location shippingBufferDays (D365 issue margin; BC outbound handling), and fix convert/index.ts, which sets promisedDate = now + leadTime × 86 400 000 on calendar days. Prior art: quoteShipment.leadTime (migration 20260206061346) was reverted three days later — the quote header was the wrong grain; the per-quantity-break line is right.

Sources