PM Task Duration & "Takes Equipment Offline" — CMMS/EAM/APS Survey

Research on how best-in-class CMMS / EAM / APS model two PM-task attributes and how they flow into scheduling: (1) estimated duration, and (2) whether the PM takes the asset offline / reserves production capacity.

Summary

Two distinct worlds. CMMS/EAM (Fiix, UpKeep, Limble, MaintainX, Maximo, SAP PM) store an estimated duration/labor estimate on the PM plan or job-plan/procedure template, and that estimate copies down onto each generated work order (usually overridable). Units are wall-clock time (min/hr) and/or labor-hours (per-craft, summed across assignees). None of the pure-CMMS tools treat "this PM makes the machine unavailable for production" as a first-class capacity reservation — they carry an asset status (Online / Offline / Out-of-service) and a "planned downtime" event category used for OEE/availability reporting, which is reporting, not a block a production scheduler honors.

Reserving capacity is an EAM↔ERP/APS integration concern. Maximo Scheduler loads work-order duration + craft hours onto a resource Gantt. SAP PP-PM integration surfaces the PM order in the production planning board so the work center shows unavailable, and SAP APO models a maintenance order as downtime on the resource — the cleanest example of a PM consuming finite capacity. In APS tools generically, planned maintenance is a resource-calendar exception / capacity block: a fixed window (start + duration) on the machine calendar, which the finite-capacity engine schedules production around. The block is a time window by construction, so a duration is inherently required to bound it; CMMS "offline" status has no such requirement because it isn't feeding a scheduler.

Per-vendor

Vendor Duration defined on… Copies to WO? Units "Takes offline" concept Feeds a capacity scheduler?
Fiix Task/PM template ("estimated time"); parts/SOP attached Yes → generated WO min/hr, labor time Asset status + downtime tracking for OEE/availability No native production scheduler; via ERP/FactoryTalk integration
UpKeep PM/procedure template (est. time) Yes min/hr Asset status; downtime logging No finite production scheduler
Limble PM template / task type; est. time Yes min/hr Asset status; planned-downtime reporting No; labor-oriented only
MaintainX Maintenance plan / procedure ("estimated completion time"); workload-based scheduling Yes min/hr, labor Asset status; downtime for OEE Labor capacity (staff workload), not machine/production capacity
IBM Maximo Job Plan (task-level durations, e.g. 30 min inspect / 2 h op / 8 h overhaul) + craft/labor est. Yes → WO/PM hr + labor-hours per craft Asset status; downtime history Yes — Maximo Scheduler loads WO duration + crafts on a resource Gantt (note: resource loading can desync if WO duration is edited in the activity view)
SAP PM/EAM Maintenance order operations (work + duration, per work center/craft) Yes (order from plan/task list) hr + labor (work) PP-PM integration: PM order shown in PP planning board → work center unavailable Yes, via PP planning board; SAP APO models the maintenance order as resource downtime
Oracle / Infor EAM Job-plan / operation standard hours Yes → WO operations hr + labor-hours Asset status; downtime codes Via ERP production scheduling integration
APS (generic) n/a (not authored there) — fixed window (start + duration) Resource-calendar exception / capacity block (hard by default) on the machine calendar Yes, by definition — finite-capacity engine schedules production around it

Answers to the key questions

  • Template vs per-WO: Duration lives on the PM plan / job-plan / procedure template and copies to each generated work order (overridable per WO). Per-WO-only entry is the exception, not the norm.
  • Explicit "offline" flag vs OEE category: Pure CMMS do not expose a first-class "reserves production capacity" flag distinct from the OEE/downtime reporting category — they use an asset status (Online/Offline/Out-of-service). A true capacity-reserving flag only exists where the PM order flows into a production scheduler (SAP PP-PM / APO, Maximo Scheduler, APS).
  • How declared downtime reserves capacity: In schedulers it's a fixed window (start + duration) realized as a resource-calendar exception / capacity block — typically a hard block the production sequence must route around (soft/preemptible blocks are rarer). SAP APO's "maintenance order = resource downtime" is the canonical shape.
  • Require a duration when offline? Not enforced in CMMS (status is a boolean-ish state). In an APS/scheduler context the block is a bounded window, so a duration is required by construction to close the interval.

Recommendations for Carbon

  1. Store duration on the PM plan/template, copy to the generated maintenance work order (keep it editable per WO). This matches every EAM surveyed and the copy-down type chain Carbon already uses. Use existing numeric-precision helpers; store as an internal-scale duration (minutes or hours) — never a JS Date diff.
  2. Add an explicit takesEquipmentOffline (production-impact) flag on the PM plan, distinct from any OEE/downtime reporting category. It is the signal that the PM should reserve the work center's capacity, not just log availability.
  3. When takesEquipmentOffline is true, require a duration — the block must be bounded. Enforce in the zod model (.refine): offline ⇒ duration > 0. This is the one hard validation the survey supports.
  4. Reserve capacity as a resource-calendar exception / hard block (start + duration) on the work center/resource, so Carbon's finite-capacity scheduler routes production around it — mirroring SAP APO and generic APS. Represent it the same way as a shift/calendar exception on the resource timeline the scheduling module already renders, not as a bespoke object.
  5. Keep OEE/availability reporting separate from the capacity block: the block drives the schedule; a downtime/availability category (if added later) drives reporting. Do not overload one field for both.

Sources