PM Task Duration & "Takes Equipment Offline" — CMMS/EAM/APS Survey
Research on how best-in-class CMMS / EAM / APS model two PM-task attributes and how they flow into scheduling: (1) estimated duration, and (2) whether the PM takes the asset offline / reserves production capacity.
Summary
Two distinct worlds. CMMS/EAM (Fiix, UpKeep, Limble, MaintainX, Maximo, SAP PM) store an estimated duration/labor estimate on the PM plan or job-plan/procedure template, and that estimate copies down onto each generated work order (usually overridable). Units are wall-clock time (min/hr) and/or labor-hours (per-craft, summed across assignees). None of the pure-CMMS tools treat "this PM makes the machine unavailable for production" as a first-class capacity reservation — they carry an asset status (Online / Offline / Out-of-service) and a "planned downtime" event category used for OEE/availability reporting, which is reporting, not a block a production scheduler honors.
Reserving capacity is an EAM↔ERP/APS integration concern. Maximo Scheduler loads work-order duration + craft hours onto a resource Gantt. SAP PP-PM integration surfaces the PM order in the production planning board so the work center shows unavailable, and SAP APO models a maintenance order as downtime on the resource — the cleanest example of a PM consuming finite capacity. In APS tools generically, planned maintenance is a resource-calendar exception / capacity block: a fixed window (start + duration) on the machine calendar, which the finite-capacity engine schedules production around. The block is a time window by construction, so a duration is inherently required to bound it; CMMS "offline" status has no such requirement because it isn't feeding a scheduler.
Per-vendor
| Vendor | Duration defined on… | Copies to WO? | Units | "Takes offline" concept | Feeds a capacity scheduler? |
|---|---|---|---|---|---|
| Fiix | Task/PM template ("estimated time"); parts/SOP attached | Yes → generated WO | min/hr, labor time | Asset status + downtime tracking for OEE/availability | No native production scheduler; via ERP/FactoryTalk integration |
| UpKeep | PM/procedure template (est. time) | Yes | min/hr | Asset status; downtime logging | No finite production scheduler |
| Limble | PM template / task type; est. time | Yes | min/hr | Asset status; planned-downtime reporting | No; labor-oriented only |
| MaintainX | Maintenance plan / procedure ("estimated completion time"); workload-based scheduling | Yes | min/hr, labor | Asset status; downtime for OEE | Labor capacity (staff workload), not machine/production capacity |
| IBM Maximo | Job Plan (task-level durations, e.g. 30 min inspect / 2 h op / 8 h overhaul) + craft/labor est. | Yes → WO/PM | hr + labor-hours per craft | Asset status; downtime history | Yes — Maximo Scheduler loads WO duration + crafts on a resource Gantt (note: resource loading can desync if WO duration is edited in the activity view) |
| SAP PM/EAM | Maintenance order operations (work + duration, per work center/craft) | Yes (order from plan/task list) | hr + labor (work) | PP-PM integration: PM order shown in PP planning board → work center unavailable | Yes, via PP planning board; SAP APO models the maintenance order as resource downtime |
| Oracle / Infor EAM | Job-plan / operation standard hours | Yes → WO operations | hr + labor-hours | Asset status; downtime codes | Via ERP production scheduling integration |
| APS (generic) | n/a (not authored there) | — | fixed window (start + duration) | Resource-calendar exception / capacity block (hard by default) on the machine calendar | Yes, by definition — finite-capacity engine schedules production around it |
Answers to the key questions
- Template vs per-WO: Duration lives on the PM plan / job-plan / procedure template and copies to each generated work order (overridable per WO). Per-WO-only entry is the exception, not the norm.
- Explicit "offline" flag vs OEE category: Pure CMMS do not expose a first-class "reserves production capacity" flag distinct from the OEE/downtime reporting category — they use an asset status (Online/Offline/Out-of-service). A true capacity-reserving flag only exists where the PM order flows into a production scheduler (SAP PP-PM / APO, Maximo Scheduler, APS).
- How declared downtime reserves capacity: In schedulers it's a fixed window (start + duration) realized as a resource-calendar exception / capacity block — typically a hard block the production sequence must route around (soft/preemptible blocks are rarer). SAP APO's "maintenance order = resource downtime" is the canonical shape.
- Require a duration when offline? Not enforced in CMMS (status is a boolean-ish state). In an APS/scheduler context the block is a bounded window, so a duration is required by construction to close the interval.
Recommendations for Carbon
- Store duration on the PM plan/template, copy to the generated maintenance work order (keep it
editable per WO). This matches every EAM surveyed and the copy-down type chain Carbon already uses.
Use existing numeric-precision helpers; store as an internal-scale duration (minutes or hours) —
never a JS
Datediff. - Add an explicit
takesEquipmentOffline(production-impact) flag on the PM plan, distinct from any OEE/downtime reporting category. It is the signal that the PM should reserve the work center's capacity, not just log availability. - When
takesEquipmentOfflineis true, require a duration — the block must be bounded. Enforce in the zod model (.refine): offline ⇒ duration > 0. This is the one hard validation the survey supports. - Reserve capacity as a resource-calendar exception / hard block (start + duration) on the work center/resource, so Carbon's finite-capacity scheduler routes production around it — mirroring SAP APO and generic APS. Represent it the same way as a shift/calendar exception on the resource timeline the scheduling module already renders, not as a bespoke object.
- Keep OEE/availability reporting separate from the capacity block: the block drives the schedule; a downtime/availability category (if added later) drives reporting. Do not overload one field for both.
Sources
- Fiix PM & work orders: https://fiixsoftware.com/cmms/preventive-maintenance-software/ , https://fiixsoftware.com/cmms/work-orders/
- Limble task types / PM scheduling: https://help.limblecmms.com/en/articles/2982304-types-of-tasks-in-limble , https://limblecmms.com/learn/preventive-maintenance/schedule/
- MaintainX maintenance plans / workload scheduling: https://help.getmaintainx.com/about-maintenance-plans , https://www.getmaintainx.com/compare/maintainx-vs-upkeep
- Maximo PM & job-plan durations: https://info.banetti.com/maximo-preventive-maintenance/ , https://www.ibm.com/docs/en/masv-and-l/maximo-manage/cd?topic=module-preventive-maintenance
- Maximo Scheduler resource-loading vs WO duration: https://community.ibm.com/community/user/discussion/maximo-scheduler-resource-loading-is-not-updated-when-work-order-duration-is-updated-in-the-activity-view
- SAP PP-PM integration (PM order → work center unavailable): https://community.sap.com/t5/enterprise-resource-planning-q-a/pp-pm-integration/qaq-p/10917351 , https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/efc7922405fd4d56b7571930c5eaa798/d784b8535c39b44ce10000000a174cb4.html
- SAP APO maintenance orders as resource downtime: https://help.sap.com/docs/SAP_SUPPLY_CHAIN_MANAGEMENT/d8a0d82aa9c041028502c8c175143205/4d2bc95360267614e10000000a174cb4.html
- APS resource availability / maintenance windows / calendar exceptions: https://www.parsec-corp.com/blog/advanced-planning-scheduling-manufacturing , https://www.theaccessgroup.com/en-us/manufacturing/software/production-planning-and-scheduling/what-is-advanced-planning-and-scheduling/
- CMMS planned downtime + production scheduling coordination: https://www.fabrico.io/blog/cmms-software-prevent-planned-downtime-overruns-manufacturing/ , https://oxmaint.com/industries/manufacturing-plant/maintenance-impact-production-schedule-manufacturing