Demand-forecast ↔ actual-demand audit (branch mrp-action-suggestions)
Audited 2026-09-11 by a read-only Explore agent as Phase 0 of the demand-forecast-consumption
feature run (.ai/runs/2026-09-11-demand-forecast-consumption.md). Findings below are the
agent's report, verbatim.
Headline verdict
The belief that same-period netting already works is REFUTED. There is no netting, no max(), no consumption of any kind between forecast and actual demand — anywhere in the stack. Forecast and actual demand are summed in four independent places. A forecast of 10 plus sales orders of 10 in the same week produces gross demand of 20.
1. SCHEMA
Two look-alike tables — input vs. output
| Table | Role | Written by |
|---|---|---|
demandProjection |
Input. The authored forecast ("we expect to sell 40 in March") | Planner, via the Demand Forecasts screen |
demandForecast |
Output. MRP's BOM-exploded child/component demand (forecastMethod = 'mrp') |
runMrp, wiped + rewritten every run |
demandProjection — packages/database/supabase/migrations/20251020183630_mrp-projections.sql:3-25:
itemId TEXT NOT NULL, locationId TEXT, periodId TEXT NOT NULL,
forecastQuantity NUMERIC NOT NULL DEFAULT 0,
forecastMethod TEXT, -- 'manual','statistical','ml' — never written by the UI
confidence NUMERIC(3,2), -- never written by the UI
notes TEXT, companyId TEXT NOT NULL,
createdBy/createdAt/updatedAt/updatedBy
PK (itemId, locationId, periodId) + UNIQUE (itemId, locationId, periodId, companyId)
A surrogate id TEXT DEFAULT id() was added later (20260527110002_demand-forecast-source.sql:12-17) so demandForecastSource can FK to it. Note: mrp.ts:464 cites a migration filename 20260527115843_demand-projection-source.sql that does not exist — minor comment drift.
demandForecast — 20250610000433_demand-planning.sql:37-55: identical column shape; PK (itemId, locationId, periodId), plus UNIQUE (itemId, locationId, periodId, companyId) from 20260527110002_demand-forecast-source.sql:1-3.
demandActual — same file, lines 105-120: PK (itemId, locationId, periodId, sourceType) where demandSourceType is 'Sales Order' | 'Job Material'. Mirror tables supplyForecast / supplyActual (supplySourceType = 'Purchase Order' | 'Production Order') exist for the supply side.
demandForecastSource — 20260527110002_demand-forecast-source.sql:30-95: lineage/pegging for BOM-derived rows. Surrogate PK, sourceType enum 'Job Material' | 'Sales Order' | 'Demand Projection', exactly one of jobId/salesOrderLineId/demandProjectionId enforced by CHECK. redirectedFromItemId added in 20260618171234_material-supersession.sql.
Period granularity
period table (20250610000433_demand-planning.sql:26-34): id, startDate DATE, endDate DATE, periodType ('Week'|'Day'|'Month'). No companyId — periods are globally shared across tenants.
Granularity is calendar week, Sunday-start (en-US locale), 7 days wide, anchored on "today" in the company timezone for MRP and the location timezone for the UI:
- MRP:
packages/ee/src/planning/mrp/mrp.ts:105-107→datetime.today(await getCompanyTimeZone(db, companyId)), thengetStartAndEndDates(today, "Week")atmrp.ts:1069-1097→startOfWeek(today, "en-US"), 7-day buckets,WEEKS_TO_FORECAST = 18 * 4 = 72weeks (mrp.ts:32). - UI:
apps/erp/app/modules/shared/shared.server.ts:498-560(getOrCreatePeriods) → identicalstartOfWeek(today, "en-US")but withgetLocationTimeZone. 'Day'and'Month'boththrow new Error("Not implemented")(mrp.ts:1090-1093).
Scoping
companyId is a column on demandProjection/demandForecast/demandActual with RLS on inventory_view/inventory_create/inventory_update/inventory_delete. locationId is nullable in the DDL but part of the PK (so effectively NOT NULL). MRP skips any row with a null locationId rather than writing "" and violating the FK — mrp.ts:446-451, 483, 521, 368, 396.
UI to author forecasts
Route tree apps/erp/app/routes/x+/production+/:
demand-forecasts.tsx— list; loadsgetProductionProjectionsRPC overWEEKS_TO_PROJECT = 12 * 4(line 26). Plan-gated byusePlanGate({ feature: "FORECAST" })(line 90) withForecastUpgradeOverlay.demand-forecasts.new.tsx,demand-forecasts.$itemId.$locationId.tsx(52-week grid;WEEKS_TO_PROJECT = 52at line 19),demand-forecasts.delete.$itemId.$locationId.tsx.- Components:
apps/erp/app/modules/production/ui/DemandProjection/DemandProjectionForm.tsx(382 lines, 52 cells in 4 quarter tabs + live chart) andDemandProjectionTable.tsx. - Services:
production.service.ts:4657upsertDemandProjections(zero → delete, non-zero → upsert onitemId,locationId,periodId,companyId),:857getDemandProjections,:521deleteDemandProjections. Parallel*DemandForecastsfunctions exist at:497,:843,:4624but operate on the MRP output table. - Server writes go through
requirePlan({ feature: "FORECAST" }).
Forecasting configuration
There is none, specific to forecasting. No item-level "forecast consumption period" flag, no company planning setting, no forecast horizon config. forecastMethod and confidence are schema placeholders the UI never writes. The only planning config is on itemPlanning (20230330024716_parts.sql:847-877 + later ALTERs): reorderingPolicy, safetyStockQuantity, safetyStockLeadTime, demandAccumulationPeriod (default forced to 30 by 20250610000433_demand-planning.sql:9-10), demandAccumulationSafetyStock, reorderPoint, reorderQuantity, minimumOrderQuantity, maximumOrderQuantity, orderMultiple, maximumInventoryQuantity, responsibleEmployee. demandReschedulingPeriod was dropped in 20250616131548_production-planning.sql:1. Company level: only companySettings.rescheduleToleranceDays (20261006130000_mrp-planning-actions.sql:109-110).
Note: apps/erp/app/modules/production/forecast.server.ts / forecast.test.ts are capacity/scheduling forecast (non-working intervals for the Gantt), unrelated to demand forecasting. Same for routes/x+/scheduling+/forecast.tsx.
2. DEMAND SOURCES in runMrp
All in packages/ee/src/planning/mrp/mrp.ts. Phase 1 bulk-loads at :125-183 (all paginated via fetchAll). Phase 4 (:419-552) merges into a single map:
// mrp.ts:424
const grossDemand = new Map<string, number>(); // key = locationId ␟ periodId ␟ itemId
| # | Source | View/table | Loaded | Merged | Date → period |
|---|---|---|---|---|---|
| 1 | Demand projections (the forecast) | demandProjection |
:161-171 |
:442-477 |
Row already carries periodId — no date mapping |
| 2 | Sales order lines | openSalesOrderLines |
:132-138 |
:480-515 |
promisedDate ?? today → findPeriod (:485-488) |
| 3 | Job materials | openJobMaterialLines |
:139-145 |
:518-552 |
job.dueDate − item leadTime → findPeriod (:523-526) |
| 4 | BOM-exploded child demand | derived | — | inside explodeBom |
parent period index − ceil(leadTime/7) weeks, floored at period[0] |
| 5 | Open jobs (supply, not demand) | openProductionOrders |
:146-152 |
:363-389 → jobSupplyByLocationPeriodItem |
dueDate, or today+30d if deadlineType = 'No Deadline', else today |
| 6 | Open POs (supply) | openPurchaseOrderLines |
:153-160 |
:393-417 → poSupplyByLocationPeriodItem |
promisedDate ?? orderDate+leadTime ?? today+leadTime |
Safety stock is NOT a demand source in runMrp. It enters only downstream, in the reorder-policy sizing (calculate_quantity_to_order in SQL / computePlanningOrders in TS) via demandAccumulationSafetyStock and reorderPoint.
Bucketing helper — mrp.ts:1056-1067:
function findPeriod(date, today, periods) {
if (date.compare(today) < 0) return periods[0]; // anything past dumps into week 0
return periods.find(p => p.startDate.compare(date) <= 0 && p.endDate.compare(date) >= 0);
}
A date outside the 72-week horizon returns undefined and the line is silently dropped (:376-377, :404-405, :488-489, :526-527).
3. NETTING LOGIC — it does not exist
The decisive code
packages/ee/src/planning/mrp/mrp.ts:438-477 — the projection (forecast) loop. The variable is named netDemand but nothing is netted from it:
// Demand projections. Do NOT net firm job/PO supply here — supply is
// credited exactly once by explodeBom's running balance ...
for (const projection of demandProjections.data ?? []) {
if (!projection.itemId || !projection.forecastQuantity || !projection.locationId) continue;
const netDemand = projection.forecastQuantity; // ← line 453: no netting at all
if (netDemand > 0) {
const key = makeKey(projection.locationId ?? "", projection.periodId, projection.itemId);
grossDemand.set(key, (grossDemand.get(key) ?? 0) + netDemand); // ← line 461: ADD
mrp.ts:480-492 — the sales-order loop writes to the same key and adds again:
const key = makeKey(line.locationId ?? "", period.id ?? "", line.itemId);
grossDemand.set(key, (grossDemand.get(key) ?? 0) + line.quantityToSend); // ← line 492: ADD
There is no Math.max anywhere in packages/ee/src/planning/mrp/ except two unrelated clamps (planning-actions.ts:210, :704). Grep for Math.max across mrp.ts and mrp-engine.ts returns zero hits.
The only netting in explodeBom is demand vs. on-hand + firm supply — packages/database/supabase/functions/lib/mrp-engine.ts:244-256:
for (const period of periods) {
running += jobSupply.get(periodKey) ?? 0;
const grossQty = grossDemand.get(periodKey) ?? 0;
if (grossQty <= 0) continue;
const netRequirement = Math.max(0, grossQty - Math.max(0, running));
running = Math.max(0, running - grossQty);
grossQty is the already-summed forecast+actual figure. There is no second dimension to reconcile.
The same addition repeats in the read path — 4 sites total
(a) get_production_planning — latest definition packages/database/supabase/migrations/20260715195226_planning-reads-demand-projections.sql:130-158:
demand_data AS (
SELECT "itemId","periodId",
SUM(COALESCE("actualQuantity",0) + COALESCE("forecastQuantity",0)) AS "demand"
FROM (
SELECT ... FROM "demandActual" WHERE ... -- line 137
UNION ALL
SELECT ... FROM "demandForecast" WHERE ... -- line 143
UNION ALL
SELECT ... FROM "demandProjection" WHERE ... -- line 153
) combined
GROUP BY "itemId","periodId"
)
(b) get_purchasing_planning — 20260831190142_purchasing-planning-reads-demand-projections.sql:115-145, byte-identical union.
(c) generatePlanningActions — packages/ee/src/planning/mrp/planning-actions.ts:527-574, with a comment that states the design:
// ── demand per (item, location, period): actual + forecast + projection,
// the same union the planning RPCs read
...
byPeriod.set(periodId, (byPeriod.get(periodId) ?? 0) + (Number(quantity) || 0)); // line 560-563
called three times, once per table (:566-574).
(d) get_inventory_quantities — 20260316000000_inventory-demand-forecast.sql:141-153: demandActual + demandForecast (notably omits demandProjection, inconsistent with (a)–(c)).
The three numeric cases
Take item X, location L, week W. Authored demandProjection.forecastQuantity = 10.
| Case | Authored forecast | Open SO lines | MRP grossDemand[L␟W␟X] |
RPC demand_data |
Correct answer under consumption |
|---|---|---|---|---|---|
| A | 10 | 10 | 20 | 20 | 10 |
| B | 10 | 5 | 15 | 15 | 10 |
| C | 10 | 12 | 22 | 22 | 12 |
Trace for case A: mrp.ts:461 sets the key to 10; mrp.ts:492 adds 10 → 20. explodeBom (mrp-engine.ts:248-251) reads grossQty = 20 and drives 20 units of component demand down the BOM. On the read side, the SO's 10 was written to demandActual (mrp.ts:494-503 → :821-835), and the projection's 10 still sits in demandProjection, so demand_data sums 10 + 10 = 20 again.
So: which formula is it?
None of the netting formulas. It is plain forecast + actual — pure addition. Not max(forecast, actual), not (forecast − actual) + actual.
Period boundary
Calendar week, Sunday-start, en-US locale, derived from startOfWeek(datetime.today(companyTimeZone), "en-US") and materialized as explicit period rows with startDate/endDate DATE columns. Matching is an exact periodId equality join on the read side (d."periodId" = periods[n]) and an exact map-key match in TS. It is not a date range between forecast entries and it is not a sliding window.
4. JOBS
Make-to-stock jobs (not linked to a sales order)
They are supply, never demand, and they do not consume forecast. openProductionOrders (current definition, 20260811123619_widen-sales-production-scale.sql, forked from 20260417000300):
WHERE j."status" IN ('Planned','Ready','In Progress','Paused')
AND j."salesOrderId" IS NULL
They land in jobSupplyByLocationPeriodItem (mrp.ts:363-389), get merged with PO supply into jobAndPoSupplyByLocationPeriodItem (mrp.ts:618-626), and are credited once in the explodeBom running balance (mrp-engine.ts:246) and again on the read side via supplyActual (mrp.ts:877-897) → the RPC's supply_data CTE.
The practical consequence: a make-to-stock job reduces the projected balance, not the forecast. With forecast 10 + SO 10 = 20 demand and a 10-unit stock job, netRequirement = 20 − 10 = 10, and MRP suggests another 10 — the double count is untouched.
Sales-order-linked jobs — yes, deliberately excluded, but on the supply side
Two complementary guards prevent SO↔job double counting:
openProductionOrdersdropssalesOrderId IS NOT NULLjobs from supply entirely (above).openSalesOrderLines(current, forked from20260710051147_mto-sales-lines-drive-demand.sql) reduces the SO line's demand by its linked jobs' outstanding quantity:
CASE
WHEN sol."methodType" = 'Make to Order' THEN GREATEST(
sol."quantityToSend" - COALESCE((
SELECT SUM(GREATEST(j."quantity" - j."quantityReceivedToInventory" - j."quantityShipped", 0))
FROM "job" j
WHERE j."salesOrderLineId" = sol."id"
AND j."companyId" = sol."companyId"
AND j."status" IN ('Planned','Ready','In Progress','Paused')
), 0), 0)
ELSE sol."quantityToSend"
END AS "quantityToSend"
openJobMaterialLinesexcludesjm."methodType" != 'Make to Order'(a sub-job will be spawned), andexplodeBomskips writingbomDerivedDemandfor MTO+Make children for the same reason (mrp-engine.ts:264-267, 288-293).
This proves the codebase already knows how to prevent double counting between two demand-ish sources — it just applies that logic only between an SO line and its own job, never between a forecast and an SO.
Also note the SO gate: openSalesOrderLines requires so."status" IN ('To Ship','To Ship and Invoice'). A Confirmed or In Progress sales order contributes zero demand to MRP.
5. THE GAP BUG — CONFIRMED (as a special case of "no consumption at all")
A sales order due in a period with zero forecast consumes nothing from any adjacent period. There is no backward consumption, no forward consumption, no consumption window at all.
Structural proof, three independent layers:
Key identity. Demand is stored in a flat map keyed on the exact triple
locationId ␟ periodId ␟ itemId(mrp-engine.ts:71-77). Reads aregrossDemand.get(periodKey)— a hash lookup on one exact key (mrp-engine.ts:248). Nothing inmrp.tsormrp-engine.tsever iterates neighbouring periods looking for forecast to draw down. The only code that does walk periods sequentially is the supersession on-hand draw-down (mrp.ts:575-606) and theexplodeBomrunning balance (mrp-engine.ts:244), and both consume inventory/supply, not forecast.SQL join.
demand_datain both RPCs groups by("itemId","periodId")and the recursiveprojectionsCTE joinsd."periodId" = periods[p.period_index + 1]— an equality join on a single period. A SQL window function or range join would be required for cross-period consumption; there is none.Nothing survives to a later stage that could do it. By the time
computePlanningOrders(packages/utils/src/planning-sizing.ts:66) runs, its input is a flatprojections: number[]of already-collapsed running balances (:49-50). The forecast/actual distinction has been destroyed by theSUM, so no downstream consumption is even expressible.
Compounding factor worth flagging: projections is a cumulative running balance (recursive CTE, 20260715195226_...:238-241 and :262-264: p."projection" + supply − demand). So a double count in week 3 depresses weeks 3 through 52, not just week 3. The over-ordering is permanent across the horizon, not a one-week blip.
The nearest existing analog to a window is itemPlanning.demandAccumulationPeriod, used by the Demand-Based Reorder branch of computePlanningOrders (planning-sizing.ts:91-120) to chunk periods for order sizing. It operates on the already-summed balance and cannot repair double counting — it only smears the inflated requirement across a wider window.
6. PLANNED ACTIONS — where a netting change propagates
runMrp commits forecasts/actuals in one transaction (mrp.ts:938-1032), then calls generatePlanningActions(client, db, { companyId, userId }) at mrp.ts:1039 in a separate transaction so the planning RPCs read committed data.
Inside packages/ee/src/planning/mrp/planning-actions.ts, the netted demand reaches planningAction by two distinct paths:
- New-supply actions (
Order/Make). Per location,client.rpc("get_purchasing_planning" | "get_production_planning", ...)at:679-690; theweek1..weekNprojected-balance columns are unpacked at:735-738and fed tocomputePlanningOrdersat:739-756. Those week columns are the recursiveprojectionsCTE output, i.e. the additively-summed demand. - Change actions (
Expedite/Defer/Cancel/Increase/Decrease). The in-Node additive union at:529-574buildsdemandByItemLocation, converted todemandPeriodsat:777-785and passed toderiveChangeActionsat:787-795. That function runs a chronological supply-consumption walk (:181-206) — demand draws down on-hand, then the earliest open orders — and emits exactly one action per document.
Candidates are then diff-written against planningAction on the natural key (item, location, type, period, target document).
A netting change must therefore land in three places to stay consistent — plus a fourth for UI truth:
mrp.tsPhase 4 (:442-515) — the gross-demand construction that drives BOM explosion.- Both SQL RPCs'
demand_dataCTE —20260715195226_...:130-158and20260831190142_...:115-145. planning-actions.ts:529-574— the in-Node union.- (
get_inventory_quantitiesdemand_forecastCTE,20260316000000_...:141-153, if the Inventory table'sdemandForecastcolumn should agree.)
Changing only one produces a grid and a worklist that disagree — exactly the failure mode the MRP-v2 spec calls out at .ai/specs/2026-08-22-mrp-v2-planned-order-generation.md:376.
7. LOOSE ENDS
No prior attempt at forecast consumption exists. Searches for consumption, consumeForecast, forecastConsum*, netting, and "double count" across packages/ee/src, packages/database/src, and the ERP production/items modules return only: accounting netting, scheduling remaining-work netting, explodeBom's inventory netting, and planning-actions.ts:181's supply-consumption walk. No consumedQuantity / consumptionPeriod / forecastConsumed columns exist on any table. No TODOs about forecast double counting.
The additive behavior is documented as intentional — apps/erp/app/modules/agent/kb/docs/reference/forecast.md:
"A projection's full
forecastQuantityenters gross demand at face value — it is not pre-netted against open production. ... Actual sales orders and job material demand are firm too — they're added in full alongside the projection."
That paragraph is accurate about the code and is the clearest statement that the "same-period netting" belief is mistaken. Note the doc also cites stale paths (ui/Projection/..., routes/.../projections.new.tsx) that are now ui/DemandProjection/... and demand-forecasts.new.tsx.
MRP v2 spec touches the area but does not fix it — .ai/specs/2026-08-22-mrp-v2-planned-order-generation.md:
:622describes gross demand as "independent demand (sales orders, demand projections)" — still additive.:851-868(§8) proposes suggested projections (trailing average,forecastMethod = 'suggested', CV gate), never auto-applied.:1230-1231explicitly says "demandProjectiongains no columns.":1225-1231relates the forecast tables to the proposedplannedOrderentity;plannedOrderPeg(:1027,:1122-1124) mirrorsdemandForecastSource.
Supersession interaction with forecasts — partially applied, and inconsistent. buildSupersessionRedirectMap (packages/database/supabase/functions/lib/supersession-pick.ts:33-84, re-exported via packages/database/src/supersession-pick.ts) is built at mrp.ts:256-259 gated on today, and Phase 4.5 (mrp.ts:563-608) redirects grossDemand — which by then includes projection demand — to the successor, stamping contributors with redirectedFromItemId (:595-599). So yes, supersession applies to forecasts inside the explosion.
But it does not apply on the read path:
demandProjectionrows still carry the olditemId, and the RPCs' third UNION arm reads that table raw. So in production/purchasing planning and inplanning-actions.ts, a projection for a superseded part shows up under the old part, not the successor.- Same for
demandActual:salesDemandByKey/jobMaterialDemandByKeyare populated atmrp.ts:494-503and:531-540, before Phase 4.5, and Phase 4.5 mutates onlygrossDemandandtopLevelContributors. Actuals are written under the pre-redirect item. base_itemsin the RPCs then filters superseded items out (20260715195226_...:216-231), so that demand can vanish from the grid entirely.
Other inconsistencies found:
getItemDemand(apps/erp/app/modules/items/items.service.ts:647-683, backingItemPlanningChartviaroutes/api+/items.$id.$locationId.forecast.ts) readsdemandActual+demandForecastbut notdemandProjection— so a top-level Make item whose only demand is a projection shows zero demand on its planning chart, while the planning grid shows it.get_inventory_quantitiesdemand_forecastCTE likewise omitsdemandProjection(20260316000000_...:141-153).mrp.ts:453const netDemand = projection.forecastQuantityis a vestigial name from a version that netted supply here; the comment at:438-441explains why that netting was removed but the variable name was never updated. Likely a source of the "netting already works" belief.mrp.ts:464cites a non-existent migration filename.getStartAndEndDatesis duplicated betweenmrp.ts:1069-1097andshared.server.ts:498-560(getOrCreatePeriods), differing only in company vs. location timezone — a company/location timezone mismatch can bucket the same date into different weeks for MRP vs. the authoring UI.- Horizon mismatch: MRP plans 72 weeks (
mrp.ts:32),generatePlanningActions48 (planning-actions.ts:37), the forecast list 48 (demand-forecasts.tsx:26), the forecast edit grid 52 (demand-forecasts.$itemId.$locationId.tsx:19), and the RPCs take up to 52weekcolumns.
Test coverage: only packages/database/supabase/functions/lib/mrp-engine.test.ts exercises the engine, and it contains no demandProjection / demandForecast / demandActual references — explodeBom is tested purely on gross demand + on-hand + supply. planning-actions.test.ts tests deriveChangeActions / convertOrdersToIncreases in isolation. No test pins the current additive behavior, so a netting change would not be caught (in either direction) by the existing suite.