Scheduled Maintenance: Expected Duration + Takes-Work-Center-Offline
Status: implemented (verified locally; not yet merged) Author: Brad Barbin (design), agent-assisted Date: 2026-08-17
TLDR
A preventive-maintenance (PM) plan (maintenanceSchedule) can already store an
estimatedDuration (minutes), but it has no way to declare that the PM takes
the machine offline, and the nightly generator throws the duration away — every
generated PM dispatch gets only a plannedStartTime (noon UTC), no
plannedEndTime, and takesWorkCenterOffline = false. On the capacity-planning
branch, an open dispatch flagged takesWorkCenterOffline subtracts its
plannedStartTime → plannedEndTime window from the work center's scheduling
capacity — so generated PMs currently reserve no capacity and describe no
expected window. This spec adds a single takesWorkCenterOffline boolean to the
schedule and wires the schedule's duration + offline flag into generation, so a PM
plan can say "this blocks the machine for ~45 minutes" and the finite scheduler
honors it ahead of time.
Problem Statement
The individual maintenance dispatch already carries everything needed to reserve capacity:
plannedStartTime/plannedEndTime— the expected window.takesWorkCenterOffline(BOOLEAN, added20260720121629_capacity-planning.sql) — the real capacity block. DB comment: "While this dispatch is open, its work center(s) contribute no scheduling capacity between (actualStartTime ?? plannedStartTime ?? createdAt) and (actualEndTime ?? plannedEndTime ?? open-ended)."
The scheduled maintenance that spawns dispatches does not:
maintenanceSchedulehasestimatedDuration(INTEGER minutes, nullable) but notakesWorkCenterOfflinecolumn — a planner cannot declare that a PM makes the machine unavailable for production.packages/jobs/src/inngest/functions/scheduled/dispatch.ts(generateDispatchesForSchedule) inserts each dispatch with onlyplannedStartTime(the due date at noon UTC). It never readsschedule.estimatedDuration, never setsplannedEndTime, and never setstakesWorkCenterOffline(it falls to the column defaultfalse). It does hard-codeoeeImpact = 'Planned', butoeeImpactonly feeds the displayisBlockedbadge (status = 'In Progress' AND oeeImpact IN ('Down','Planned')), not the scheduler.
Net effect: a shop can define "tear down and rebuild the press, 3rd Monday of the month, ~2 hours, machine down" and the finite scheduler will still happily plan production onto that press during those two hours, because the generated PM reserves nothing and has no end time.
Concrete example (today, broken): a monthly PM on work center WC-PRESS with
estimatedDuration = 120 generates a dispatch at 2026-09-21T12:00Z with
plannedEndTime = null, takesWorkCenterOffline = false. The capacity view shows
WC-PRESS fully available on 9/21. After this spec, with the schedule flagged
offline: the dispatch generates with plannedEndTime = 2026-09-21T14:00Z,
takesWorkCenterOffline = true, and the scheduler subtracts that 2-hour window.
Proposed Solution
- Add one column to
maintenanceSchedule:takesWorkCenterOffline BOOLEAN NOT NULL DEFAULT false. - Require
estimatedDurationon the schedule only whentakesWorkCenterOfflineis true (zodsuperRefine), so an offline PM always produces a bounded capacity block — never an open-ended one. - In the generator, copy the schedule's
takesWorkCenterOfflineonto each generated dispatch, and setplannedEndTime = plannedStartTime + estimatedDurationwhenever the schedule has a duration (regardless of the offline flag).oeeImpactstays hard-coded'Planned'for all generated PMs — unchanged, independent of the new flag. - Surface the offline toggle on the schedule form; validation enforces the duration coupling. Show the flag in the schedules table.
Copy-down is a snapshot at generation — consistent with how the generator already snapshots priority, procedure, and spare-part items. Editing a schedule affects only future generated dispatches; existing open dispatches keep their copied-down values and remain individually editable on the dispatch form.
Research (.ai/research/scheduled-maintenance-duration-downtime.md) confirms this
shape: best-in-class CMMS/EAM (Fiix, UpKeep, Limble, MaintainX, Maximo Job Plans,
SAP PM) store the duration estimate on the PM template and copy it down to each
generated work order; where planned maintenance actually reserves production
capacity (Maximo Scheduler, SAP APO), it is modeled as a fixed start+duration
window on the resource calendar, and a duration is required precisely because it
bounds that block. Carbon's takesWorkCenterOffline window is exactly this
resource-calendar exception.
Design Decisions
| Decision | Choice | Rationale |
|---|---|---|
| How duration becomes the dispatch window | Generator sets plannedEndTime = plannedStartTime + estimatedDuration (minutes) |
The scheduler blocks plannedStartTime → plannedEndTime; without an end an offline PM is an open-ended capacity hole. |
| Duration required when offline? | Required iff takesWorkCenterOffline is true (superRefine) |
An offline PM with no duration = unbounded block. Off-line PMs keep duration optional/informational. Matches CMMS/APS: duration is required only when it bounds a scheduler block. |
Set plannedEndTime for non-offline PMs too? |
Yes — whenever a duration is present, regardless of the flag | Makes every generated PM self-describing ("~45 min job"); the scheduler only reacts to the window when takesWorkCenterOffline is true. Null end only when no duration (only possible for non-offline PMs). |
Relationship to oeeImpact |
Independent. Add only takesWorkCenterOffline; generator keeps oeeImpact = 'Planned' for all generated PMs |
A scheduled PM is "Planned" downtime for OEE regardless of whether it fully blocks the center. oeeImpact = display/reporting; takesWorkCenterOffline = capacity. Keeping them separate matches the existing dispatch model and the research. |
| Propagation on schedule edit | Future-only. No cascade to already-generated open dispatches | Matches copy-once generation (items/procedure/priority are never re-synced); a dispatch is an independent work order once created; avoids silently moving/erasing a capacity block the scheduler already planned around. |
| New column shape & default | takesWorkCenterOffline BOOLEAN NOT NULL DEFAULT false |
Mirrors the dispatch column exactly; existing schedules backfill to false (non-blocking) — safe, no behavior change until a planner opts in. |
| Heuristic 1 (multi-tenancy) | N/A — altering an existing table; maintenanceSchedule already has companyId + composite-safe PK, RLS, audit |
No new table. |
| Heuristic 2 (service shape) | Extend existing upsertMaintenanceSchedule (client-first, {data,error}) |
No new service function. |
| Heuristic 3 (RLS) | N/A — column add inherits table RLS (resources_*) |
No policy change. |
| Heuristic 4 (permission scoping) | Unchanged — schedule routes already use resources_create / resources_update |
No new route. |
| Heuristic 5 (form pattern) | Existing ValidatedForm + maintenanceScheduleValidator + existing new/edit route actions |
Add one Boolean field + a superRefine. |
| Heuristic 6 (module layout) | All changes in resources.models.ts / resources.service.ts / ui/MaintenanceSchedule/ + the jobs generator |
Single module + its generator. |
| Heuristic 7 (backward compatibility) | No FROZEN/STABLE surface touched; NOT NULL DEFAULT false backfills silently |
Additive column, additive generator logic. |
Data Model Changes
Single additive migration (pnpm db:migrate:new scheduled-maintenance-offline,
randomized HHMMSS). No new table.
-- Add the offline/production-impact flag to the PM plan, mirroring
-- maintenanceDispatch."takesWorkCenterOffline".
ALTER TABLE "maintenanceSchedule"
ADD COLUMN "takesWorkCenterOffline" BOOLEAN NOT NULL DEFAULT false;
COMMENT ON COLUMN "maintenanceSchedule"."takesWorkCenterOffline" IS
'When true, PM dispatches generated from this schedule are created with takesWorkCenterOffline = true and a bounded plannedEndTime (plannedStartTime + estimatedDuration), so the finite scheduler subtracts that window from the work center''s capacity. Requires estimatedDuration to be set.';
View / RPC redefinition (required — see feedback_view_redefinition). The
schedule list reads through the maintenanceSchedules view
(20251226000001_maintenance_schedule_days.sql) and the
get_maintenance_schedules_by_location RPC
(20251231003301_scheduled-maintenance-fix.sql). A view/RPC SELECT freezes its
column list at definition time, so both must be forked from their newest
definitions and recreated to expose takesWorkCenterOffline (preserve every
existing attribute — estimatedDuration, day-of-week flags, derived locationId,
procedureId, etc.). Without this, the loader can't read the new column even
though the base table has it.
No enum, no RLS, no audit changes (column inherits the table's existing RLS and audit columns).
API / Service Changes
apps/erp/app/modules/resources/resources.models.ts
- Add
takesWorkCenterOffline: zfd.checkbox()tomaintenanceScheduleValidator. - Add a
.superRefine(or.refine) on the schedule schema: whentakesWorkCenterOfflineis true,estimatedDurationmust be present and> 0; attach the error to theestimatedDurationpath (message e.g. "Estimated duration is required when the PM takes the work center offline"). Off-line schedules leaveestimatedDurationoptional.
apps/erp/app/modules/resources/resources.service.ts
upsertMaintenanceSchedule(insert + update branches): includetakesWorkCenterOfflinein the written columns.
packages/jobs/src/inngest/functions/scheduled/dispatch.ts
- Extend the local
MaintenanceScheduleinterface (currently ~L26–43) withestimatedDuration: number | nullandtakesWorkCenterOffline: boolean. - Ensure the schedule-fetching query
select(...)includes both columns. - In the dispatch
insert(~L204–230):takesWorkCenterOffline: schedule.takesWorkCenterOffline.- Compute
plannedEndTimefrom the already-computed noon-UTC start whenschedule.estimatedDurationis set, using@internationalized/date:startZdt.add({ minutes: schedule.estimatedDuration }).toAbsoluteString()(reuse the sametargetDate.set({ hour: 12, ... })ZonedDateTime the start is derived from — no JSDate, perdate-handling.md). LeaveplannedEndTimeunset whenestimatedDurationis null.
oeeImpactremains'Planned'— no change.
No route loader/action signature changes (the new/edit schedule routes already
call validator(maintenanceScheduleValidator) and upsertMaintenanceSchedule).
UI Changes
apps/erp/app/modules/resources/ui/MaintenanceSchedule/MaintenanceScheduleForm.tsx
- Add a
Booleanfieldname="takesWorkCenterOffline"labelled "Takes Work Center Offline" (match the dispatch form's wording inMaintenanceDispatchForm.tsx), placed nearestimatedDuration. - The existing
estimatedDurationNumberstays; thesuperRefinesurfaces the "required when offline" error throughValidatedForm's normal validation. (Optional polish: show the "(required)" hint on the duration label when the toggle is on — not required for correctness since server validation enforces it.)
apps/erp/app/modules/resources/ui/MaintenanceSchedule/MaintenanceSchedulesTable.tsx
- Add a column/indicator for
takesWorkCenterOffline(e.g. a "Blocks machine" badge or boolean cell), next to the existingestimatedDuration("X min") column, so planners can see at a glance which PMs reserve capacity.
No MES changes — schedules are ERP-only; the MES dispatch surface already handles
takesWorkCenterOffline on the dispatch itself.
Acceptance Criteria
- Migration adds
maintenanceSchedule.takesWorkCenterOffline BOOLEAN NOT NULL DEFAULT false; existing schedules read backfalse.pnpm run generate:typesregeneratespackages/database/src/types.tswith the column. - The
maintenanceSchedulesview andget_maintenance_schedules_by_locationRPC exposetakesWorkCenterOffline(the schedule list loader returns it). - Creating/editing a schedule with "Takes Work Center Offline" ON and Estimated Duration blank fails validation with the error attached to the duration field; with duration set it saves.
- Creating/editing a schedule with the flag OFF saves with or without a duration (duration remains optional).
- Generating from a schedule with
estimatedDuration = 120and the flag ON produces a dispatch withtakesWorkCenterOffline = true,plannedStartTime= due date @ noon UTC, andplannedEndTime = plannedStartTime + 120 min— verified in the DB / on the dispatch form's planned window. - Generating from a schedule with a duration but the flag OFF produces a
dispatch with
takesWorkCenterOffline = falseand a populatedplannedEndTime(self-describing window), and the scheduler does not subtract it. - Generating from a schedule with the flag OFF and no duration produces a
dispatch with
plannedEndTime = null(unchanged from today). - An open generated dispatch flagged offline subtracts its
plannedStartTime → plannedEndTimewindow from the work center's capacity in the forecast/scheduler view; editing the parent schedule afterward does not alter that already-generated dispatch (future-only). -
pnpm --filter @carbon/erp typecheck,pnpm --filter @carbon/jobs typecheck, and the resources tests pass.
Risks
| Risk | Severity | Mitigation |
|---|---|---|
| Forgetting to redefine the view/RPC → loader silently can't read the new column | Med | Explicit acceptance criterion + task; fork newest view/RPC definitions with SELECT-column parity. |
Timezone bug computing plannedEndTime (JS Date drift) |
Med | Reuse the existing ZonedDateTime start and .add({ minutes }) from @internationalized/date; never construct a JS Date (date-handling.md). |
| Duration units mismatch (schedule stores minutes; someone assumes seconds/hours) | Low | estimatedDuration is documented minutes (form label "(minutes)"); .add({ minutes }) matches. |
| An existing schedule flipped to offline while future dispatches already generated leaves those unchanged, surprising a planner | Low | Documented future-only behavior; planner edits the individual dispatch (matches copy-once model). Consider a form helper note. |
| Client vs server validation drift on the coupling rule | Low | Single source of truth is the zod superRefine on maintenanceScheduleValidator, used by both ValidatedForm (client) and the route action (server). |
Open Questions
All resolved with the user on 2026-08-17 before this spec was written.
- How does the schedule's duration become the dispatch's blocking window, and
is duration required when offline? — Answer: Generator sets
plannedEndTime = plannedStartTime + estimatedDuration;estimatedDurationis required ifftakesWorkCenterOfflineis true (validatorsuperRefine), so an offline PM is always a bounded block. Corroborated by CMMS/APS research (duration bounds the scheduler block). - Should the schedule's offline flag also drive
oeeImpact? — Answer: No — keep them independent. Add onlytakesWorkCenterOffline; the generator keepsoeeImpact = 'Planned'for all generated PMs.oeeImpactis display/OEE;takesWorkCenterOfflineis capacity. - On schedule edit, do already-generated open dispatches change? — Answer: Future-only. No cascade; existing open dispatches keep their snapshotted values and stay individually editable.
- When a schedule has a duration but is not offline, still set
plannedEndTime? — Answer: Yes — always setplannedEndTimewhen a duration is present, regardless of the flag.plannedEndTimeis null only when no duration (non-offline PMs only, per the coupling rule above). - New column shape/default? — Answer:
takesWorkCenterOffline BOOLEAN NOT NULL DEFAULT false, mirroring the dispatch column; existing schedules backfill tofalse.
Changelog
- 2026-08-17: Created. Open questions resolved with the user before writing;
design reflects "duration required iff offline", "oeeImpact independent",
"future-only propagation", "always set plannedEndTime when duration present",
and the single
takesWorkCenterOfflinecolumn. Research at.ai/research/scheduled-maintenance-duration-downtime.md. - 2026-08-17: Implemented on
naveen/capacity-planningand verified locally. Migration20260817041453_scheduled-maintenance-offline.sqlapplied (column + view/RPC recreation; the view recreation also un-froze the schedule's ownlocationId/procedureIdcolumns and dropped the now-duplicatewc.locationIdalias).erp+@carbon/jobstypecheck pass; 476 jobs tests pass (erp has no unit-test runner). Browser+DB e2e proved: the "Takes Work Center Offline" toggle renders; a schedule saved with offline ON + 90 min persiststakesWorkCenterOffline=true, estimatedDuration=90; the "Blocks Machine" column shows OFFLINE; offline ON + blank duration surfaces the exact superRefine error; and forcing a due occurrence generated dispatch MAIN000001 withtakesWorkCenterOffline=trueandplannedEndTime = plannedStartTime + 90 min. All e2e test data cleaned up. Not yet merged (draft PR).