Batch Release & Batch-Aware Scheduling

Status: in-progress Author: Claude (with Brad, 2026-09-04; independent Fable review same day) Date: 2026-09-04 Research: .ai/research/2026-09-04-batch-release-and-scheduling.md (confirmatory — all four core choices have clear precedent; no contradictions: SAP PP-PI phase release, APS campaigning, p-batch/s-batch resource typing, quantity-equivalence split)

  • .ai/research/job-operation-batching-competitors.md (2026-08-31 survey) Builds on: .ai/specs/2026-08-21-job-operation-batching.md (the batching feature this extends — its locked decisions are preserved, not replaced) Requirement: REQ-FUN-PRODUCTION-005 (Must, Daily) Tracking issue: https://github.com/crbnos/carbon/issues/1010 Branch: feat/job-operation-batching-v2

TLDR

Today an operation can only be planned into a batch after its job is released to the floor — because the batch planner and the shop floor read the identical visibility predicate (job status ∈ Ready/In Progress/ Paused; "Released" is only a UI relabel of Ready, not a stored state). So every operation that should be batched spends the window between release and batch-creation sitting on the floor as a naked, individually-runnable operation — the wrong thing sent to production. The leak is structural, not a timing bug: the only way to make an operation visible to the planner is to make it visible to the floor at the same instant.

This spec decouples planner visibility from floor visibility and makes a batch independently releasable:

  1. The planner widens to show operations from jobs in any live status (Draft/Planned/Ready/In Progress/Paused), so batches are composed before release.
  2. The batch gains a pre-floor state. Lifecycle becomes Planned → Active → Completing → Completed; "Release batch" is the new Planned → Active transition (Active keeps its meaning "live on the floor", relabelled "Released" in the UI, exactly as jobs relabel Ready). A Planned batch lives only in the planner.
  3. Floor visibility becomes a membership handoff. An operation is floor-visible iff — if it belongs to a batch, that batch is Released; if it belongs to no batch, its job is released (today's rule). Once a batch owns an operation, the batch's release state governs it instead of the job's. Nobody is ever blocked: to run a batched op solo you remove it from the batch and job-gating takes over.
  4. The scheduler becomes batch-aware. A Released batch is scheduled as one unit — one coalesced capacityReservation on one work center — and its duration follows a new process.batchType (Simultaneous = oven/furnace, members run in parallel, duration = setup + max(run); Sequential = saw/laser, members run one after another, duration = setup + Σ(run)). Members are pinned to the batch window, not placed individually — which also closes the existing HIGH risk that per-op reservations N×-over-book a batch work center.

The cost/time split at completion is unchanged — it slices the actual recorded timer proportionally to member quantity, which is physics-agnostic. Only the planned duration uses the max-vs-sum formula.

Problem Statement

get_batchable_operations (the batch planner RPC, 20260821024449_job-operation-batching.sql:328-346) gates candidates on j."status" IN ('Ready','In Progress','Paused'). The MES floor — get_active_job_operations_by_location (:189) and getOpenJobs (apps/mes/app/services/operations.service.ts:53, via activeJobStatuses, packages/database/src/utils.ts:17) — gates on the same set. There is no stored "Released" flag; Ready is released, relabelled in apps/mes/app/routes/x+/jobs.tsx:94.

Consequences:

  • You cannot see an operation in the planner without also putting it on the floor. Batching can only happen after the op is floor-eligible, so there is always a window where a should-be-batched operation is a loose, individually-dispatchable operation. An operator can sign into it and run it the wrong way (N setups instead of one shared run) before the planner ever touches it.
  • A batch has no release concept. jobOperationBatch.status is Active → Completing → Completed and is Active (live) the instant it is created (20260821024449…:53, …index.ts:682). You cannot compose a batch ahead of time, review it, and release it as a unit; and you cannot release a batch's operations to the floor before their jobs are released, even though the batch is ready to run.
  • The scheduler is batch-unaware (the existing spec's HIGH risk). capacityReservation is per-operation, so N batch members each reserve the full run time on one work center — N×-over-booking it — and nightly replan can split a batch across work centers. There is no model for the simultaneous-vs-sequential physics of batch resources: today's planned duration is hardcoded "shared setup + summed labor/machine" (.claude/rules/mes-job-operation-ui.md), i.e. it silently assumes every batch is sequential and over-estimates every furnace/oven load.

Proposed Solution

1. The membership-handoff floor gate

One governing rule replaces the single job-status predicate:

An operation is floor-visible iff:

  • it belongs to a batch → the batch is Released (Active/Completing), or
  • it belongs to no batch → its job is released (Ready/In Progress/Paused) — today's rule.

(In both cases the operation itself must not be Done/Canceled.)

Membership transfers the gate from the job to the batch. Verified against every case:

Op in a batch? Batch state Job state Floor-visible?
No — Released Yes happy path — a batchable op nobody batched still runs; never blocked
Yes Released Unreleased (Draft/Planned) Yes a released batch pulls its members ahead of their jobs
Yes Released Released Yes —
Yes Planned Released No the leak, closed: an op planning pulled into a not-yet-released batch is held by it
No — Unreleased No nothing says go
any any any No if op Done/Canceled —

The fourth row is the leak fix and it is not a block: the op was deliberately pulled into a batch during planning; the batch is the intended vehicle; releasing it is one click. To genuinely run it solo, remove it from the batch (existing remove/dissolve) and job-gating resumes. Membership is simultaneously the leak-prevention and the escape hatch — there is no separate "override" concept.

2. Batch lifecycle: a pre-floor state + release

Planned ──release──> Active ──complete(phase 1)──> Completing ──phase 2──> Completed
   │                   │
   │  (unrelease,      │  (add/remove/work-center while no productionEvent)
   │   no event yet)   │
   └── dissolve ───────┘   (deletes the batch; members return to job-gating)
  • Planned (new default on create): composed in the planner, not on the floor. Fully editable (add/remove members, set/clear work center, dissolve). Its members are invisible to MES (membership handoff: batch not Released).
  • Active (= today's live state, UI label "Released"): on the floor. Members are floor-visible. Still editable until the first productionEvent (unchanged boundary). Timers run here.
  • Completing / Completed: unchanged two-phase completion.

New transitions on the batch-operations edge function:

  • release — guarded Planned → Active. Requires a workCenterId (a batch with no work center has nowhere to run) and ≥1 member. Makes members floor-visible. The ERP action wrapping it mirrors the job-release ordering: first recalculateJobRequirements for member jobs still in Draft/Planned (a batch can pull a Draft job's op onto the floor — its BOM quantities must be fresh, same safety recalc job release performs; no MRP run), then the edge-fn flip, then notifyScheduleInputsChanged (the flip must be persisted before the wave reads it — the same load-bearing ordering as job release).
  • unrelease — guarded Active → Planned, allowed only while no productionEvent exists for the batch (symmetric with the add/remove boundary). Pulls the batch back off the floor. Triggers a reschedule.

Membership/work-center mutations (add/remove/update) widen from "Active only" to "Planned or Active, pre-event" — a Planned batch must be fully composable or the planning state is useless. dissolve and the completion path are unchanged (planBatchCompletion already throws for any status other than Active/Completing, so a Planned batch can never complete).

Server-side enforcement, not just list-visibility (Fable review finding): today MES has no status gate at all on the operation view or the start route — start.$operationId.tsx checks only companyId, and the operation loader treats a non-Active batch as "no batch", rendering a plain runnable operation. Floor gating is purely which lists an op appears in. So the handoff rule must also be enforced where work actually starts:

  • operation.$operationId.tsx loader: an op in a Planned batch redirects away with a flash ("part of batch BAT…, not yet released to the floor"); an unbatched op whose job is unreleased redirects the same way.
  • start.$operationId.tsx: the same check before writing any productionEvent.

Without these, the leak survives via direct URL or a stale tab.

Create supports the singleton happy path: the builder creates Planned by default, with a "Create & Release" affordance that inserts Active and schedules in one step (for the furnace op that doesn't need to wait for company).

dissolve stays the pre-start "never mind" (deletes the row; members drop back to job-gating). Completion is unchanged; planBatchCompletion throws for any status other than Active (slice) / Completing (resume) — a Planned batch has no timers so it can never reach complete.

3. Planner widening

get_batchable_operations drops the released-only job filter. Candidates are operations of the (batchable) process at the location that are unstarted (op status Todo/Ready/Waiting, no productionEvent), unbatched, whose job is in any live status (Draft/Planned/Ready/In Progress/Paused — i.e. not Completed/Closed/Cancelled). The NOT EXISTS productionEvent guard and the "existing batch members as lanes" behaviour are unchanged; the lanes now include Planned batches (the ones you are still composing) as well as Active/Completing.

The route wrapper's RELEASED_JOB_STATUSES "hidden ops" attribution (api+/production.batchable-operations.ts:26) is retired — an unreleased job is no longer a reason to hide a candidate.

4. Batch-aware scheduling

process.batchType — a new enum on the process master data, next to batchable: Simultaneous | Sequential (default Sequential — the conservative sum-time assumption; over-reserving a machine is safer than under-reserving it). Meaningful only when batchable = true.

Planned duration of a Released batch (used for the reservation and the builder/MES estimate), where run_i = max(labor_i, machine_i) per member, net-of-progress for a partially-complete member exactly as single ops are today:

setup = max(member setup_i)                 // shared load setup, both regimes
run   = Simultaneous ? max(run_i)           // parallel load — the cycle time
      : Sequential   ? Σ(run_i)             // serial queue — one after another
duration = setup + run

This replaces the hardcoded-sequential MES aggregate, fixing an existing latent over-estimate for simultaneous processes.

The batch is one scheduling unit (mechanics refined by the Fable review against the real engine):

  • Batch pre-pass. Before the per-job forward passes, a batch-placement pass places every Released batch at the location: duration from batchDuration(batchType, members) (net-of-progress like single ops — remaining-work scaling, setup counted done once any batch event exists), anchored at max(now, max over members of their predecessor op's persisted projectedCompletionAt) — the engine's own last-wave forecasts, read from the DB at wave start (precedent: the need-by pass already reads stored dueDate pins). A predecessor placed later than the batch start in this wave surfaces as a conflict flag on the member, and the next wave converges. Earliest feasible slot on the batch's workCenterId given existing reservations.
  • One reservation, tagged. capacityReservation.operationId/jobId are NOT NULL, so the batch reservation carries a new nullable jobOperationBatchId tag column and anchors its NOT NULL columns on the deterministic first member (min member op id). Consequences wired in: the per-job regen delete (scheduling-engine.ts:1201) adds AND "jobOperationBatchId" IS NULL (a member job's own regen must not destroy the batch's reservation), the not-yet-run snapshot exclusion (master-data-provider.ts:497) keeps batch-tagged rows visible (the batch is already placed; its members must see it as fixed), and the pre-pass owns delete + rewrite of batch-tagged rows for the location.
  • Members are pinned to the batch window — startDate / projectedCompletionAt are the batch's; no per-member placement, no per-member WC reservation. Implementation hook: the engine already supports an op that skips placement and keeps a fixed window (the pinned Outside-Processing path, date-calculator.ts:34-43, work-center-selector.ts:378 chains successors after a pinned end) — batch members generalize that path rather than adding a new mode.
  • Each member's downstream operations depend on the batch's single projectedCompletionAt — all members leave the batch together (slightly conservative for a sequential batch's early-finished part; fine for v1).
  • Planned batches schedule as today — members placed individually. The residual per-op over-booking for a Planned batch is bounded (pre-floor, planning state) and disappears at release; coalescing only Released batches keeps the pre-pass input stable (membership and WC can still churn on a Planned batch).
  • Work-center reservation only in v1. The pre-pass does not reserve an employee for ability-gated batchable processes (a single op would); a batch is one crew on one machine and v1 accepts the slight optimism. Documented gap.

Scheduler job-loading widens so a released batch can pull unreleased-job members onto the schedule: the location pass (run-schedule.ts:77 loads status IN ('Ready','In Progress','Paused')) additionally loads any job with a member operation in a Released batch, deduped into the same deterministic order. Those jobs run the engine like active jobs (their upstream ops claim real capacity — a released batch commits its inputs, and the schedule should say so); their non-batched ops remain floor-invisible via the handoff rule.

Simultaneous capacity stays advisory. workCenter.batchCapacity already exists and is advisory (fill bar in the builder). The scheduler does not split an over-capacity simultaneous batch into back-to-back reservations in v1 — it warns and reserves one block (consistent with the "never block" principle). Splitting a load is a separate future spec.

MRP is unaffected. Batch release is a floor-visibility + scheduling event; it does not change buy-vs-make decisions (materials still come from each job's own BOM, planned at job level). No MRP or requirements-recalc runs on batch release.

Design Decisions

Decision Choice Rationale
Core reframe Decouple planner-visibility from floor-visibility; the batch is the vehicle that carries batchable ops across the floor gate The single shared predicate IS the leak; two gates is the only structural fix. Precedent: SAP PP-PI treats "make a sub-unit executable" (phase release) as a gate separate from order release
Floor gate Membership handoff: op in a batch → batch's release state governs; op in no batch → job's release governs Satisfies "never block a batchable op nobody batched" AND "show a released batch's members on an unreleased job" AND "no leak" — one rule, all three. This is APS campaigning: members are "spoken for" by the campaign and stop appearing as loose ops, which is how double-dispatch is avoided by single ownership
Escape hatch Remove-from-batch (existing remove/dissolve); no new "run solo" override Membership is the only switch; fewer states, and the ERP cardinal sin (blocking) is avoided by a cheap, existing action
Batch pre-floor state Add Planned before Active; Active keeps meaning "live/released", UI relabels it "Released" Minimal churn — completion/resume (planBatchCompletion), RPC predicates, and MES all key on Active/Completing and stay as-is. Renaming Active→Released was considered and rejected (touches every consumer for a label)
Release action New edge-fn release (Planned → Active), requires workCenterId + ≥1 member, triggers a schedule A batch with no work center has nowhere to run; scheduling must react to the new floor unit
Un-release New edge-fn unrelease (Active → Planned), allowed only while no productionEvent Maximum flexibility (Brad) without corrupting a run — same boundary as add/remove
Create default Planned, with a "Create & Release" one-step affordance Planning-first is the whole point; the one-step path preserves the singleton happy path (batch of one on a furnace)
Planner visibility Any live job status (Draft/Planned/Ready/In Progress/Paused); unstarted + unbatched unchanged Compose batches before release; still never offer started or completed work
Simultaneous vs sequential process.batchType enum (Simultaneous|Sequential, default Sequential) on the process, beside batchable Same home as the capability flag; the machine determines the physics (furnace parallel, saw serial). This is the scheduling literature's p-batch (parallel) vs s-batch (serial), defined as a property of the machine/resource — heat-treat is the canonical p-batch example
Planned duration setup(max) + run where run = max(run_i) for Simultaneous, Σ(run_i) for Sequential; run_i = max(labor,machine) The only place the two regimes differ; fixes the hardcoded-sequential MES estimate
Batch as schedule unit One coalesced capacityReservation on one work center; members pinned to the window; downstream anchored to batch projectedCompletionAt Resolves the existing HIGH over-booking risk directly; matches "schedule the batch, not the members" (Brad)
Scheduler job-loading Location pass includes jobs with a member in a Released batch, even if the job is not in activeJobStatuses Required for the "released batch on an unreleased job" case
Simultaneous capacity Advisory only in v1 (warn, never split/block) Consistent with "never block" and the existing advisory batchCapacity; load-splitting is a separate spec
MRP on release None — batch release is floor + schedule only Materials are per-job BOM, planned at job level; batching changes execution, not procurement
Multi-tenancy No new tables; Planned enum value + batchType enum/column reuse existing composite-tenant scoping Additive to the existing batching schema
Backward compatibility Planned appended to the enum; batchType defaults Sequential; floor/planner predicate changes are the only behavioural deltas — a company with no batches is byte-for-byte unchanged (every op is "in no batch" → job-gating) The handoff rule reduces to today's rule when jobOperationBatchId IS NULL

Data Model Changes

No new tables. Two additive migrations (Fable review: a value added by ALTER TYPE … ADD VALUE cannot be referenced later in the same transaction, and the migration runner wraps each file in one — so the enum add and its first uses must be separate files). The batching feature's 20260821024449 migration is on this branch but fix forward — do not edit it.

-- ── Migration A: enum values + batchType + reservation tag ──────────────────
-- Batch pre-floor state. BEFORE 'Active' keeps enum sort = lifecycle order.
ALTER TYPE "jobOperationBatchStatus" ADD VALUE IF NOT EXISTS 'Planned' BEFORE 'Active';

-- Simultaneous vs sequential batch physics (process master data).
-- (CREATE TYPE has no IF NOT EXISTS — guard with a DO block in the real file.)
CREATE TYPE "batchType" AS ENUM ('Sequential', 'Simultaneous');
ALTER TABLE "process" ADD COLUMN IF NOT EXISTS "batchType" "batchType" NOT NULL DEFAULT 'Sequential';
-- Recreate the "processes" view from its NEWEST definition (DROP + CREATE, not
-- REPLACE — a new p.* column cannot be appended by REPLACE) so it exposes batchType.

-- Batch reservation tag: operationId/jobId are NOT NULL on capacityReservation,
-- so the coalesced batch reservation anchors those on the deterministic first
-- member and carries this tag as its semantic key.
ALTER TABLE "capacityReservation" ADD COLUMN IF NOT EXISTS "jobOperationBatchId" TEXT;
ALTER TABLE "capacityReservation" ADD CONSTRAINT "capacityReservation_jobOperationBatchId_fkey"
  FOREIGN KEY ("jobOperationBatchId", "companyId")
  REFERENCES "jobOperationBatch"("id", "companyId")
  ON DELETE SET NULL ("jobOperationBatchId");   -- PG15 column-list form, per lesson
CREATE INDEX IF NOT EXISTS "capacityReservation_jobOperationBatchId_idx"
  ON "capacityReservation" ("jobOperationBatchId") WHERE "jobOperationBatchId" IS NOT NULL;

-- ── Migration B: everything that REFERENCES 'Planned' ───────────────────────
ALTER TABLE "jobOperationBatch" ALTER COLUMN "status" SET DEFAULT 'Planned';
-- Re-declare get_batchable_operations (fork 20260821024449, the newest def):
--   job filter  → j."status" NOT IN ('Completed','Closed','Cancelled')
--   batch lanes → b."status" IN ('Planned','Active','Completing')
--   output      + j."status" AS "jobStatus"  (builder chips need it)
-- Re-declare get_active_job_operations_by_location (fork 20260831170323, the
-- newest def) with the membership-handoff predicate (below).

Notes:

  • The batch-operations create case changes its inserted status from 'Active' to 'Planned' (honouring release: true for "Create & Release"); the column default flip is belt-and-braces on top.
  • No change to jobOperation.jobOperationBatchId, productionEvent, or the sequence.
  • After the migrations: pnpm run generate:types before typechecking.

Behavioural (not new tables) — the predicate changes are the heart of this spec:

  • get_batchable_operations — replace j."status" IN ('Ready','In Progress','Paused') with the live-job set (NOT IN ('Completed','Closed', 'Cancelled')); include Planned batches in the members-as-lanes union.
  • get_active_job_operations_by_location (feeds the ERP schedule board AND the MES kanban) — change the relevant_jobs CTE from the job-status filter to the membership-handoff predicate:
    • include an operation when jobOperationBatchId is in an Active/ Completing batch, regardless of job status; OR
    • when jobOperationBatchId IS NULL and the job is in activeJobStatuses.
    • A Planned batch's members are excluded (not on the floor) even if the job is released.
  • getOpenJobs (operations.service.ts) — the job list widens to include a job that has an operation in a Released batch even if the job is not in activeJobStatuses (so a Draft job with a released-batch member appears, with only that operation actionable).
  • The scheduler's job-loading query (packages/ee/src/planning/scheduling/ run-schedule.ts) widens the same way (jobs with a Released-batch member).

API / Service Changes

batch-operations edge function (new intents)

Add to the discriminated union (.claude/rules/workflow-edge-function.md shape; requirePermissions(..., { update: "production" }) unchanged):

  • { type: "release", batchId, companyId, userId } — re-read the batch under companyId; assert status = 'Planned', workCenterId IS NOT NULL, ≥1 member; guarded flip Planned → Active (WHERE status = 'Planned', rollback if 0 rows); after commit call notifyScheduleInputsChanged(companyId, "work-center", "batch released", batchId?) (kind TBD at plan — a batch is a work-center-scoped change). Returns { released: true }.
  • { type: "unrelease", batchId, companyId, userId } — assert status = 'Active' and no productionEvent tagged with the batch; guarded flip Active → Planned; reschedule. Refused (named error) once any timer exists — "production has been recorded — complete the batch instead".
  • { type: "create", ..., release?: boolean } — insert status: release ? 'Active' : 'Planned' (default Planned). When release, apply the same workCenterId-required guard and trigger a schedule.

create's existing assertEligible already does not gate on job status (the RPC did), so widening the planner needs no edge-fn eligibility change — members from Draft/Planned jobs were always acceptable to the gate.

production.service.ts (ERP)

releaseJobOperationBatch(client, { batchId, companyId, userId })     // type: "release"
unreleaseJobOperationBatch(client, { batchId, companyId, userId })   // type: "unrelease"
// createJobOperationBatch gains an optional `release` passthrough

production.models.ts: extend jobOperationBatchStatus const with Planned; createJobOperationBatchValidator gains optional release: zfd.checkbox(); new releaseJobOperationBatchValidator / unreleaseJobOperationBatchValidator (batchId only).

resources module

processValidator gains batchType: z.enum(["Sequential","Simultaneous"]) (default Sequential); upsertProcess passes it through; ProcessForm gains the selector (only shown when batchable is on).

Scheduling engine (packages/ee/src/planning/scheduling/)

Design-level contract (engine internals to be detailed in /plan):

  • Job-loading widens to include jobs with a Released-batch member.
  • Batch placement: a Released batch is placed as one unit on its workCenterId for batchDuration(batchType, members); write ONE capacityReservation for the batch, not per member. Recommended shape: a batch-placement pass that runs before the per-job forward passes, then the per-job passes treat batched member ops as pinned (already placed) with their downstream deps anchored to the batch's projectedCompletionAt.
  • Duration helper batchDuration lives in the shared scheduling code (and, if the builder/MES estimate needs it, mirror via @carbon/utils next to batch-time-split), so the reservation, the builder estimate, and the MES plan bar cannot disagree.
  • notifyScheduleInputsChanged is the only sanctioned trigger (never write startDate/projectedCompletionAt directly) — release/unrelease fire it.

MES (apps/mes/app/services/)

  • getOpenJobs and the display board reads adopt the membership-handoff predicate (above). A Planned batch's members never appear; a Released batch's members appear regardless of their job's status.
  • No change to the batch run/complete flow (batch.$batchId.complete.tsx, BatchCompleteModal) — completion still operates on Active/Completing.

UI Changes

Surface Change
Process form (resources/ui/Processes/ProcessForm.tsx) When batchable is on, show a Batch type selector: Sequential ("parts run one after another — saw, laser table") vs Simultaneous ("parts run together in one load — furnace, oven, plating"). Default Sequential
Batch builder (ui/Batches/BatchBuilder.tsx) Candidate list widened to unreleased jobs (a job-status chip distinguishes Draft/Planned from Released so the planner sees what they're pulling forward). Review step: "Create" (Planned) and "Create & Release" (Active). The run-time estimate uses batchDuration(batchType, …) (max vs Σ) instead of the hardcoded sum
Batches list + detail drawer (ui/Batches/…) New Released (was "Active") label; a Planned status badge; a Release action (Planned rows, requires a work center — the action is disabled with a hint if none) and an Unrelease action (Active rows with no production event). Status filter gains Planned
Operations schedule board / batch card (BatchItemCard) The batch card renders in its work-center column for Released batches; members are not drawn individually (Brad: show the batch, not the members). Amended at implementation (Fable, for veto): Planned batches do NOT appear on the board — the board reads the floor RPC (shared with the MES kanban), and widening it would put planning-state work on a dispatch surface, the exact ambiguity this feature removes. Planned batches are managed on the Batches list + builder (status filter, Release action, drawer). The card ships a dashed Planned variant, dormant unless a planner lane is added later
MES kanban / floor Unchanged UI, but a Released batch's members now appear even when their job is unreleased; a Planned batch's members do not appear even when their job is released. A batchable op not in any batch on a released job appears normally (happy path)
Job detail A job with unbatched batchable operations after release surfaces an informational "N operations awaiting batching" line (not a block) so a planner knows those ops are held for the planner, not lost

Acceptance Criteria

  • A process can be marked batchable with Batch type Sequential or Simultaneous; the field is hidden when batchable is off; existing processes default to Sequential.
  • The batch builder lists unstarted, unbatched operations of a batchable process whose job is Draft or Planned (not only released jobs); a job-status chip distinguishes them; Completed/Closed/Cancelled jobs never appear.
  • Creating a batch with "Create" yields status = 'Planned'; its member operations do not appear on the MES floor even if their jobs are released; the batch is fully editable (add/remove/work-center/dissolve).
  • "Create & Release" (or the Release action on a Planned batch) requires a work center, flips the batch to Active ("Released"), triggers a schedule, and makes its members floor-visible even if their parent jobs are Draft/Planned (unreleased-job + released-batch case).
  • A batchable operation on a released job that belongs to no batch appears on the floor and is individually runnable (happy path — never blocked).
  • An operation pulled into a Planned batch does not appear on the floor even after its job is released (the leak, closed); removing it from the batch (or dissolving) restores job-gating and it appears again once its job is released.
  • Unrelease returns an Active batch with no production events to Planned (members leave the floor, reschedule fires); it is refused with a named error once any batch timer exists.
  • A Planned batch cannot be completed (planBatchCompletion rejects it); completion behaviour for Active/Completing is unchanged (two-phase, resumable, proportional slice).
  • For a Simultaneous batch (members A/B/C with run times 40/70/50 min, setups 10/10/10), the scheduled reservation is 10 + max(40,70,50) = 80 min; for the same members on a Sequential batch it is 10 + (40+70+50) = 170 min.
  • A Released batch occupies its work center as one capacityReservation for the batch duration (not N per-member reservations); member operations are pinned to that window; each member's downstream operation depends on the batch's single projectedCompletionAt; nightly replan keeps the batch on one work center (no member split).
  • Job costing / estimates-vs-actuals for each member job is unchanged — the completion split still slices the actual recorded timer proportionally to member quantity (Simultaneous/Sequential does not change the split).
  • A company with no batches behaves byte-for-byte as before (every op is "in no batch" → job-gating on the floor and released-only in the planner is the only behaviour that changed, and it is a widening).
  • pnpm exec turbo run typecheck --filter=erp --filter=mes and --filter=@carbon/ee, lint, and tests pass; batchDuration has a unit test covering both regimes and net-of-progress; new MES/ERP strings extracted across locales.

Risks

Risk Severity Mitigation
Scheduling engine change (batch as a pinned unit, widened job-loading) is the deepest part and lives in EE, forward-ASAP, capacity-1 finite placement High Keep v1 to "one coalesced reservation + pin members + anchor downstream"; a dedicated batch-placement pass before per-job passes isolates the change; extensive batchDuration + placement unit tests; this directly resolves the existing spec's HIGH over-booking risk rather than adding a new one
ALTER TYPE … ADD VALUE 'Planned' transaction semantics (can't use the value in the same txn on older PG) Med Confirm Carbon's migration runner behaviour at plan time; isolate the ADD VALUE in its own statement/migration if needed
Widening getOpenJobs / get_active_job_operations_by_location regresses the floor for the common (no-batch) case Med The handoff predicate reduces to today's exact predicate when jobOperationBatchId IS NULL; smoke both boards + the MES floor with zero batches, one Planned batch, one Released batch on a Draft job
A released batch on a Draft job means a Draft job appears on the MES floor with only one actionable op — could confuse operators Low The op-level handoff makes only the batched op actionable; the job's other ops stay hidden until job release; document in AGENTS.md
Simultaneous batch exceeding physical capacity is only warned, not split Low Deliberate v1 scope (advisory capacity, never block); load-splitting is a named future spec; the fill bar already warns
Sequential-batch downstream anchoring is conservative (early-cut part waits for batch end) Low Accepted for v1; documented; refine only if customers need per-member early release
Batch anchor uses last-wave predecessor forecasts (stale by one wave for just-changed upstreams) Low Deterministic per wave; overruns surface as conflict flags; next wave converges — same self-healing contract the engine already has for conflicts
A batch member's job can be Paused (held) while the batch runs Low Batch governs visibility; member renders Paused via the existing coercion; operator excludes it at completion; documented

Open Questions

Resolved with Brad in the 2026-09-04 design conversation. Items marked (recommended — for veto) are ones the spec author settled from the agreed principles and are surfaced for Brad to override; the rest are Brad's explicit answers. Per Brad's working style, accept-and-document with a veto window.

  • How do we prevent the leak without blocking anyone? — Answer (Brad): the membership handoff — an op in a batch is governed by the batch's release state, an op in no batch by the job's. Never hard-suppress batchable ops; removing an op from a batch is the escape hatch.
  • Should a released job's un-batched batchable op still be runnable on the floor? — Answer (Brad): yes, always. "The cardinal sin in ERP is to block someone from doing something they need to do."
  • Should a released batch's members show on the floor even if their job is unreleased? — Answer (Brad): yes.
  • How to schedule simultaneous vs sequential batches? — Answer (Brad): distinguish them; oven = parallel (max run), saw/laser = serial (Σ run). Modeled as process.batchType; the batch is scheduled as one unit, members not shown individually.
  • batchType default and naming? — Answer (recommended — for veto): enum Sequential | Simultaneous, default Sequential (conservative over-reserve).
  • Reuse Active as the live/released state or rename to Released? — Answer (recommended — for veto): keep Active (UI label "Released"), add Planned — minimal churn to completion/RPC/MES consumers.
  • Create default Planned, with a one-step "Create & Release"? — Answer (recommended — for veto): yes — planning-first default preserves the singleton happy path.
  • Does batch release require a work center / trigger MRP? — Answer: originally "require a work center" (recommended); VETOED by Brad 2026-09-05 ("too much friction... the work center should be selected automatically... with load balancing"). Release requires only ≥1 member; the scheduler's batch pre-pass auto-selects earliest-finish among the process's work centers and persists it. Schedule trigger unchanged; still no MRP.
  • Provide unrelease (Active → Planned)? — Answer (recommended — for veto): yes, but only while no productionEvent exists (Brad's "maximum flexibility" without corrupting a run).
  • Simultaneous over-capacity: split or warn? — Answer (recommended — for veto): warn only (advisory), never split in v1.

The following were surfaced and resolved by the independent Fable review (2026-09-04, Brad delegated: "review the 6 recommendations and make the plan independently"). All six original recommendations were upheld; these are the completeness findings that review added:

  • MES has no server-side status gate today (direct-URL leak). — Fable: enforce the handoff rule in the operation.$operationId loader and start.$operationId route, not only in list RPCs. Without it a Planned-batch member is startable via URL/stale tab and the leak survives.
  • Does batch release refresh member-job requirements? — Fable: yes — recalculateJobRequirements for member jobs still Draft/Planned, before the flip (mirrors job release's safety recalc, same ordering); still no MRP.
  • How does the coalesced reservation coexist with NOT NULL operationId/jobId and the per-job regen? — Fable: nullable capacityReservation.jobOperationBatchId tag + anchor-member row; per-job delete adds AND "jobOperationBatchId" IS NULL; snapshot exclusion keeps batch-tagged rows; the pre-pass owns batch-row delete/rewrite.
  • What anchors the batch start when upstream ops aren't placed yet? — Fable: persisted last-wave projectedCompletionAt of member predecessors (max(now, …)), conflicts flagged on overrun, wave-over-wave convergence. (Precedent: need-by pass reads stored pins.)
  • Do Planned batches coalesce too? — Fable: no — members schedule per-op as today until release; bounded residual over-book, stable pre-pass input.
  • Are add/remove/update allowed on a Planned batch? — Fable: yes — widen the edge-fn guards from "Active only" to "Planned or Active, pre-event"; a Planned batch must be fully composable.
  • Employee finiteness for batch reservations? — Fable: WC-only in v1; documented optimism for ability-gated batchable processes.
  • Paused member job while its batch is Released? — Fable: the batch governs floor visibility (the op stays visible — it is part of a shared load); the job-paused coercion in the floor view still renders that member Paused, and the operator can exclude it at completion ("Not in this run"). Harmless inconsistency, documented.

Changelog

  • 2026-09-04: Created. Extends 2026-08-21-job-operation-batching.md with a releasable batch lifecycle (Planned state + release/unrelease), the membership-handoff floor gate, process.batchType (Simultaneous/Sequential), and batch-as-one-unit scheduling. Design resolved in a live conversation with Brad; recommended-and-surfaced items flagged for veto.
  • 2026-09-04: Confirmatory research reconciled (.ai/research/2026-09-04-batch-release-and-scheduling.md) — all four core choices (independent batch release, membership handoff, p-batch/s-batch resource typing, quantity-proportional split) have direct precedent (SAP PP-PI phase release, APS campaigning, scheduling-literature batch machines, SAP co-product equivalence); no contradictions. Two non-blocking future refinements noted (p-batch weight/size-driven duration; non-quantity override weights). Status: draft, pending Brad's veto pass on the recommended items, then /plan.
  • 2026-09-05: Browser verification caught a runtime bug in the floor RPC fork (unqualified "id" in the relevant_jobs CTE is ambiguous with the plpgsql OUT parameter — the function threw at first call); fixed by qualifying "job"."id". All 8 e2e scenarios then PASSED (leak closed incl. direct-URL guard; released-batch-on-Draft-job floor visibility; Sequential 120min vs Simultaneous 80min single coalesced reservations; zero member over-booking; unrelease refusal; unchanged proportional completion). Per Brad, the branch's nine incremental migrations were then consolidated into ONE final-state idempotent file: 20260905132037_job-operation-batching.sql.
  • 2026-09-06: "Released batch missing from the forecast" (BAT000005) root-caused to TWO stacked causes. (1) Environment: a stale Inngest dev-server app registration ("unreachable", 0 functions — recorded while the ERP was down during a stack restart) silently swallowed every schedule.inputs.changed event; fixed with a re-register PUT /api/inngest. (2) Engine: the batch pre-pass skipped any batch whose members carry zero setup/labor/machine time (durationSeconds <= 0 → continue) — no reservation, no auto work-center, invisible on the reservation-driven forecast. Fixed: a zero-estimate Released batch now emits a flagged 1h placeholder (NO_ESTIMATE_PLACEHOLDER_HOURS, workHours 0, never blocks), still auto-selects the work center, and members carry composeBatchNoEstimatesConflict ("add setup, labor, or machine time"). Verified e2e: wave run auto-assigned the Laser Table and the forecast renders "BAT000005 · 2 jobs" with the can't-be-scheduled flag + sidebar reason.
  • 2026-09-07: While verifying the dependency story (downstream ops chain after the batch window via placedEndByOperation + persisted member projectedCompletionAt; graph itself untouched), found the coalesced reservation had NO retirement path of its own — the sparing rules (per-job-delete skip + snapshot escapes) meant a Completed batch kept blocking the work center and an unreleased one double-booked it. Fixed with 20260907155426_cleanup-reservations-on-batch-exit.sql: a jobOperationBatch status trigger (mirroring the terminal-job cleanup) deletes tagged rows on → Completed and → Planned, plus a one-time orphan sweep; dissolve self-heals via the FK's column-list SET NULL. Both paths verified in a rolled-back transaction.
  • 2026-09-04: Implementation amendment (Fable, for veto): the priority board stays floor-pure — Planned batches render only on the Batches list/builder, not as board cards (the board + MES kanban share the floor RPC; a Planned card there would re-mix planning into dispatch). Card variant kept dormant.
  • 2026-09-04: Independent Fable review (Brad switched models and delegated the review + plan). All six recommendations upheld; one amended (#4 gains the member-job recalculateJobRequirements at release). Completeness findings folded in: MES loader/start-route handoff guards (no server-side status gate exists today — the leak was closable only at the list layer otherwise), capacityReservation.jobOperationBatchId tag + regen/snapshot predicate rules, batch anchor from persisted predecessor forecasts, Planned-batches-stay-per-op, add/remove/update widened to Planned, two-file migration split (enum-value same-transaction reference restriction), WC-only batch reservations, paused-member semantics. Grounded against run-schedule.ts:77, scheduling-engine.ts:1201, master-data-provider.ts:497, date-calculator.ts:34-43, work-center-selector.ts:378, start.$operationId.tsx, operation.$operationId.tsx:90-112, 20260720121629_capacity-planning.sql. Status: in-progress — planned at .ai/plans/2026-09-04-batch-release-and-scheduling.md.