description: MRP (Material Requirements Planning) — run flow, data model, planning UI paths: - "packages/jobs/src/inngest/functions/scheduled/mrp.ts" - "packages/jobs/src/inngest/functions/scheduled/mrp-companies.ts" - "packages/planning/src/mrp/" - "packages/database/src/mrp-engine.ts" - "packages/utils/src/planning-sizing.ts" - "apps/erp/app/modules/{production,purchasing}/ui/Planning/" - "apps/erp/app/modules/production/planning-action-claims.ts" - "apps/erp/app/modules/settings/ui/Planning/**" - "apps/erp/app/routes/x+/{production,purchasing}+/planning*.tsx" - "apps/erp/app/routes/x+/settings+/planning.tsx" - "apps/erp/app/modules/production/production.service.ts" - "apps/erp/app/modules/production/production.server.ts" - "apps/erp/app/modules/purchasing/purchasing.service.ts" - "apps/erp/app/modules/settings/settings.service.ts" - "apps/erp/app/modules/settings/settings.models.ts" - "apps/erp/app/routes/api+/items.$id.$locationId.forecast.ts" - "apps/erp/app/hooks/useMrpScheduleDescription.ts" - "packages/planning/src/index.ts"

MRP (Material Requirements Planning)

MRP nets demand against supply per item/location/period and projects on-hand forward so users can create planned purchase orders (purchasing) and jobs (production). It runs IN-PROCESS in Node via runMrp (exported from @carbon/planning, source packages/planning/src/mrp/mrp.ts), driven by an Inngest scheduled cron, a manual route POST, or a status change on a document that moves demand or supply (below) — NOT a Supabase edge function (the old mrp Deno function and its config.toml entry were DELETED), and NOT Trigger.dev. runMrp(client, db, payload) takes an injected service-role Supabase client (PostgREST reads) and a Kysely handle (the atomic Phase-7 write) and throws on failure.

Run flow (inputs → compute → outputs)

  1. Scheduled job — packages/jobs/src/inngest/functions/scheduled/mrp.ts. inngest.createFunction({ id: "mrp", retries: 2 }, { cron: "*/15 * * * *" }, …) — a tick every 15 minutes, on which a company is due either every 3 hours (the default) or once a day at companySettings.mrpRunTime (a TIME on the company's own clock, company.timezone; set in Settings → Planning → MRP Schedule (MrpScheduleCard, intent setMrpSchedule), where the form offers whole hours plus the stored time when it is not on the hour — an MCP-set 14:30 saves back unchanged rather than cut to 14:00 — mrpScheduleValidator, normalised to HH:MM:SS; the Recalculate tooltip names the company's timezone). Setting a time REPLACES the 3-hourly runs for that company. The rule is the pure isMrpDue(tick, { timezone, mrpRunTime }) (scheduled/mrp-companies.ts, unit-tested): the default is "UTC hour divisible by 3, minute 0"; a daily time is due on the FIRST tick at or after the run time's instant, tested against the instant (not the local hour) so a spring-forward day still runs once and a fall-back day does not run twice, and checked for yesterday's date too (23:50 is first reached at 00:00). The tick is mrpTick(event.ts) — the cron's own timestamp plus one minute, floored to the 15-minute slot (the minute absorbs a cron that fires just before the boundary), so a retried step answers for its own slot; with no event.ts it falls back to now("UTC"). A tick with nobody due returns early, before the plan lookup — and a tick between the 3-hourly runs with no company on a daily time returns before company is read at all (the mrpRunTime read comes first for that reason). A failed mrpRunTime read throws (defaulting would plan a daily company at the wrong hours and skip its own); an unparseable timezone/time falls back to the default cadence for that one company. A find-companies step selects all rows from company, narrowed to the due ones and then by companiesWithPlanningWork (scheduled/mrp-companies.ts): one UNION over the open demand/supply views, demandProjection, and the rows an earlier run wrote (planningAction, demandForecast with forecastMethod = 'mrp', demandForecastSource, supplyForecast, non-zero actuals), plus the stock-only sources: an itemPlanning row with a positive floor its policy reads (minimum reserve; safety stock on Demand-Based Reorder; reorder point on Fixed Reorder Quantity / Maximum Quantity) and negative itemStockQuantities — the planning actions size an Order / Make from on-hand alone. A company in none of them would read nothing and write nothing, so it is skipped; a failed lookup plans for every due company. Then one step.run per company (mrp-<companyId>) calls runMrp(serviceRole, getJobDatabaseClient(), { type: "company", id, companyId, userId: "system" }) in-process (runMrp throws on failure; the loop try/catches per step and returns { companies, failed }). Every Inngest step is one HTTP request to /api/inngest, so a step's ceiling is that Vercel function's max duration — set project-wide in the Vercel dashboard (Settings → Functions), NOT via a route config export: a maxDuration in the route config splits a second server bundle in the @vercel/react-router preset and the Vite 8 css-post plugin fails the build ("Unable to get file name for unknown file"). All companies in ONE step was one invocation, hit FUNCTION_INVOCATION_TIMEOUT as the tenant count grew after the company-enumeration change below, and every retry restarted from company #1. There is no location-scoped cron — only company-wide.

    It enumerated companyPlan until 2026-08-26. MRP is not in FEATURE_PLANS, so that was never a billing gate — just a convenient list of companies — but the table is only written by Stripe checkout and is seeded nowhere, so every self-hosted, community and local-dev install had an empty work list and silently never ran MRP, reporting a green Inngest run. Do not reintroduce it: the work list is company, and a company with no plan row must still run. On Cloud only, companies whose stripeSubscriptionStatus is 'Canceled' are skipped: the company is on its way out (Stripe removes the plan row when the subscription ends, and weekly.ts then deletes the planless company). The selection rule is the pure selectCompaniesForMrp (scheduled/mrp-companies.ts), unit-tested in its sibling .test.ts. Every tick with someone due logs Companies scheduled for MRP (company / due / scheduled counts), and a warn fires when companies were due but the plan and planning-work filters left none. A tick with NOBODY due returns [] without a log — most ticks are like that. An EMPTY company read warns (No companies found to plan for) before that return: the read happens only on a 3-hourly tick or when a company set a time, so empty there is a broken work list — the companyPlan failure above — never a quiet tick.

    All three reads (companySettings.mrpRunTime, company, companyPlan) go through fetchAllFromTable with a stable .order("id") — the same reason every engine read pages (below): max_rows = 1000 truncates a bare select, and the dev stack does not enforce the cap, so a dropped tail is invisible locally. A failed mrpRunTime or company read throws; returning would make the step succeed having planned for nobody (or for the wrong companies), which is this function's whole bug class. A failed companyPlan read does not — it leaves plans null and plans for everyone, which is the fail-safe direction.

  2. Manual trigger — POST apps/erp/app/routes/api+/mrp.ts (permission update: "inventory"). Reads the ?location query param, confirms it belongs to the company (requireCompanyRecord), then calls runMRP(getCarbonServiceRole(), getDatabaseClient(), { type: locationId ? "location" : "company", id: locationId ?? companyId, companyId, userId }). runMRP(client, db, params) lives in apps/erp/app/modules/production/production.service.ts; it dynamic-imports runMrp from @carbon/planning, calls it in-process with the Kysely handle the route passed in (never built in the service file), and preserves the { data, error } shape (catching the throw). The planning tables submit to this via path.to.api.mrp(locationId). The API / MCP's production_runMRP (runMRP in production.server.ts) runs the same with the service role and the same update: "inventory".

    Event triggers — the same runMRP runs after a document changes demand or supply: job status changes (x+/job+/$jobId.status.tsx, and releaseJobs in production.server.ts), PO status changes (x+/purchase-order+/$orderId.status.tsx), sales order confirm (x+/sales-order+/$orderId.confirm.tsx) and kanban (api+/kanban.$id.tsx). The demo template's planDemoCompany (packages/jobs/src/demo-planning.ts) calls runMrp directly. None of these is affected by mrpRunTime, which only governs the cron.

  3. In-process engine — packages/planning/src/mrp/mrp.ts (runMrp(client, db, payload), Node, ~1390 lines). Reads go through the injected service-role Supabase client (PostgREST); the atomic Phase-7 write goes through the injected Kysely handle. Payload validator accepts type: "company" | "location" | "item" | "job" | "purchaseOrder" | "salesOrder", id? (required for non-company), companyId, userId. Computation engine is packages/database/src/mrp-engine.ts (explodeBom(...), @carbon/database/mrp-engine), also used by getMethod (production.service.ts).

    • Periods: generates/fetches weekly period rows 72 weeks forward from today on the company's clock (WEEKS_TO_FORECAST = 18 * 4, "Week" granularity).
    • Inputs (demand): views openSalesOrderLines, openJobMaterialLines, plus the user-entered demandProjection. Don't conflate it with the output: MRP reads demandProjection (user-entered) and writes demandForecast (rebuilt each run — see Outputs below).
    • Forecast consumption (forecast-consumption.ts, wired in Phase 4): actual demand consumes the projections for the same (item, location) — own weekly bucket first, then backward companySettings.forecastConsumptionBackwardPeriods (default 4) then forward forecastConsumptionForwardPeriods (default 1) buckets. Only the unconsumed remainder enters gross demand/contributors; SO lines consume at openSalesOrderLines.quantityToConsume (PRE-job-dedup, so an MTO line covered by its job still consumes) while demand still uses the deduped quantityToSend; job materials consume at quantityToIssue. Runs BEFORE the Phase-4.5 supersession redirect on purpose (read paths don't redirect either). Phase 7 persists demandProjection.consumedQuantity (batched UPDATE … FROM (VALUES …), an UPDATE never an upsert) and every read path nets with GREATEST("forecastQuantity" - "consumedQuantity", 0): both planning RPCs, generatePlanningActions' union, get_inventory_quantities, and the item forecast API (api+/items.$id.$locationId.forecast.ts, which nets the raw projections getItemDemand returns). Regenerative: nothing to un-consume — cancelled orders/edited forecasts re-net on the next run. Consumption is re-netted only inside MRP's window, so a PAST week keeps its last leftover: every read path must stop at the current week. The planning RPCs do by their periods argument; get_inventory_quantities joins period and keeps endDate >= location_today(...) (without it the Inventory screen's Demand Forecast grew by each past week's leftover). Unit tests: forecast-consumption.test.ts. Spec: .ai/specs/implemented/2026-09-11-demand-forecast-consumption.md. Backlog consumes nothing (actualConsumesForecast): an SO line promised, or a job material whose job is due, before the first period is still demand in that period, but the forecast that predicted it was for a week that is gone. Consuming this week's forecast with it left this week's predicted customers unplanned. Job materials are judged on the job's due date, not the lead-time-shifted required date.
    • Inputs (supply): views openProductionOrders, openPurchaseOrderLines.
    • Inputs (on-hand): the itemStockQuantities table (trigger-maintained, 20260812002454) — an indexed per-company read, replacing the old full itemLedger GROUP BY that grew with total history. Excludes Rejected tracked stock (matching get_inventory_quantities); the raw scan counted it.
    • Reads paginate: every PostgREST read goes through fetchAll (@carbon/database/fetch-all, 1000-row pages + stable .order()) — production max_rows = 1000 truncates bare .select("*") reads, and the dev stack does NOT enforce the cap, so truncation is invisible locally.
    • Writes are atomic: the Phase-7 delete-and-rewrite of demandForecast/demandForecastSource/supplyForecast + actual inserts runs in ONE Kysely transaction — a failed run leaves prior planning data intact.
    • Key encoding: every composite map key goes through makeKey / makeLocationItemKey / makeActualKey in packages/database/src/mrp-engine.ts (joined on KEY_SEP = "\x1f"). Never build ${a}-${b} keys — ids are caller-supplied TEXT (imports mint hyphenated UUIDs); "-"-joined keys truncated them on parse and MRP 500'd for those tenants (Postgres 21000). Regression tests: packages/database/src/mrp-engine.test.ts.
    • BOM explosion: for Make items, explodes the active make method to derive child demand with low-level-code ordering, per-period inventory netting, and lead-time offsetting. A line with quantity 0 is left out (bomChildren, packages/planning/src/mrp/bom-children.ts), never defaulted to 1: a configured item carries every configuration's lines at 0 except the default's, and || 1 exploded all of them per parent.
    • Outputs (DB writes): deletes prior MRP forecast rows — including EVERY supplyForecast row at the company's locations (MRP never inserts supplyForecast; the planning.update routes do) — then batch-inserts (500/chunk) demandForecast (forecastMethod: "mrp"), demandForecastSource (lineage), demandActual, and supplyActual, and persists demandProjection.consumedQuantity. Writes are stamped with the payload userId ("system" for cron).
    • Planning actions: after the Phase-7 transaction commits, runMrp calls generatePlanningActions (planning-actions.ts), which diff-writes the planningAction worklist in its own transaction. That transaction takes pg_advisory_xact_lock on planning-actions:<companyId> BEFORE it reads the existing rows: nothing else serialises runMrp per company (the cron and the five route-triggered runs can overlap), and two runs that both read "no row" for a natural key both insert — the second fails on planningAction_natural_key_idx and rolls the whole write back. Under the lock the second run reads the first run's rows and updates them in place. Its errors propagate, so a run whose actions failed reports failure even though the forecast rows are already committed. The write is writePlanningActionDiff (RecordingDriver-tested in planning-actions.write.test.ts): its DELETE and UPDATE skip Actioned rows themselves, because the run read the actions before diffing and a row applied in between would otherwise be deleted or reopened. Updates go as one UPDATE … FROM (VALUES …) per set of changed columns (cast through PATCH_COLUMN_TYPES), never one per row, and each row keeps its own patch — writing every column would drift a dismissed row's stored quantity so a changed need never reopens it. The shared sizing (computePlanningOrders, @carbon/utils) suggests nothing when a policy's order quantity comes out 0 — a Fixed Reorder Quantity item with reorder point and quantity both 0 used to emit an "Order 0" action for every short week.

Planning data model (tables — all in newest schema)

Base tables defined in 20250610000433_demand-planning.sql; lineage table in 20260527110002_demand-forecast-source.sql.

Table PK Key cols Notes
period id startDate, endDate, periodType enum 'Week'|'Day'|'Month'; no companyId (uniform RLS)
demandProjection (itemId, locationId, periodId) forecastQuantity, consumedQuantity user-authored forecast; consumedQuantity is MRP-written derived state (20261006130001), never user-edited
demandForecast (itemId, locationId, periodId) forecastQuantity, forecastMethod MRP writes forecastMethod='mrp'
demandActual (itemId, locationId, periodId, sourceType) actualQuantity, sourceType sourceType enum demandSourceType = 'Sales Order'|'Job Material'
supplyForecast (itemId, locationId, periodId) forecastQuantity, forecastMethod written by planning.update routes (planned POs/jobs); MRP never inserts it but DELETES every row at the company's locations in Phase 7
planningAction (id, companyId) type, status, suggestedQuantity, suggestedDate, horizonDate, latestOrderDate, purchaseOrderLineId / jobId, assignee the MRP worklist (20261006130000). type enum planningActionType = Order / Make / Expedite / Defer / Cancel / Increase / Decrease / Release; status = Open / Dismissed / Actioned. Diff-written by generatePlanningActions; one non-Actioned row per (item, location, type, and the target order — or, for a new Order / Make, its week) via a partial unique index on COALESCE(purchaseOrderLineId, jobId, periodId). naturalKey matches rows the same way, with every week up to the current one as one "now" (keyPeriodFor), and the diff updates periodId in place — so a dismissal or a hand-set assignee survives the weekly roll of the first period
supplyActual (itemId, locationId, periodId, sourceType) actualQuantity, sourceType sourceType enum supplySourceType = 'Purchase Order'|'Production Order'
demandForecastSource surrogate id sourceType, jobId/salesOrderLineId/demandProjectionId, parentItemId, quantity MRP lineage; enum demandForecastSourceType = 'Job Material'|'Sales Order'|'Demand Projection'; CHECK exactly one source id set
itemPostingGroupResponsibility (id, companyId) locationId, itemPostingGroupId, responsibleEmployee one rung of the action owner ladder (20261006130000): the owner of an item group AT a location; UNIQUE (companyId, locationId, itemPostingGroupId); RLS employee read, settings_update writes (20261006130100). Written by upsertItemPostingGroupResponsibility (a null employee deletes the row)

locationId is declared TEXT (no NOT NULL) on the five original planning tables (demandProjection, demandForecast, demandActual, supplyForecast, supplyActual; planningAction declares it NOT NULL outright), but it is part of the PRIMARY KEY of every one of them (see the PK column above), so Postgres makes it implicitly NOT NULL — a null locationId raises 23502, and it is also an FK to location(id), so a bogus value (e.g. the empty string runMrp used to write via a ?? "" key fallback for a source line with no location) raises 23503 *_locationId_fkey and rolls the whole run back. runMrp therefore SKIPS any source line (sales/job-material/production/PO/projection) with no locationId rather than fabricating one. Audit cols (createdBy/At, updatedBy/At) present except on period and demandForecastSource (created-only).

Planning split functions

Latest definition of BOTH, and of get_inventory_quantities: 20261006130001_demand-forecast-consumption.sql. get_production_planning supersedes 20260715195226; get_purchasing_planning and get_inventory_quantities are forked from the guarded 20260925121735 bodies and open with assert_company_access. Their demand_data CTEs read the projection arm net of consumption (GREATEST("forecastQuantity" - "consumedQuantity", 0)).

  • get_purchasing_planning(company_id, location_id, periods[]) — items where replenishmentSystem != 'Make' (includes "Buy" and "Buy and Make"), itemTrackingType != 'Non-Inventory', active.
  • get_production_planning(company_id, location_id, periods[]) — items where replenishmentSystem = 'Make' (same other filters).
  • Both union supplyActual+supplyForecast and demandActual+demandForecast, project on-hand period-by-period (week1…week52), and compute quantityToOrder via calculate_quantity_to_order(...), which branches on reorderingPolicy: 'Manual Reorder' → 0; 'Demand-Based Reorder'; 'Fixed Reorder Quantity'; 'Maximum Quantity'. Demand-Based Reorder applies the minimum and the order multiple to the week's need and sizes each ORDER by the smaller of lotSize and maximumOrderQuantity (demandBasedPerOrder in planning-sizing.ts; the SQL total is the whole need, 20261013004700) — a maximum never caps the week. Fixed Reorder Quantity ignores lotSize; Maximum Quantity uses it only as a rounding multiple. In computePlanningOrders each Demand-Based Reorder batch is due in the week its share is needed (the first week the projection plus every earlier batch is under safety stock), not all in the window's first short week: deriveChangeActions dates a PO line by the first demand it covers, so later batches dated in week 1 were Deferred as soon as they were raised.
  • An item is included when it has demand in the window, a stock-driven policy (reorder point on Fixed Reorder Quantity / Maximum Quantity), OR open supply in the window (supply_data with supply > 0, 20261013004600). The third arm is what lets generatePlanningActions reach deriveChangeActions for a surplus-only item — a job whose forecast was deleted gets its Cancel — and keeps that item on the Material Planning screens.

"Buy and Make" coercion + BOM decision

In mrp-engine.ts, effectiveReplenishment() coerces "Buy and Make" → "Buy" before processing, so "Buy and Make" items are never exploded — their demand flows to purchasing planning. Only replenishmentSystem = 'Make' items explode their BOM to child demand. Note current methodType enum is 'Make to Order' | 'Pull from Inventory' | 'Purchase to Order' (NOT the old 'Make'/'Pick'/'Buy' names).

Source views (open demand/supply)

Newest defs: openPurchaseOrderLines in 20260811123616_widen-purchasing-scale.sql, openProductionOrders in 20260811123619_widen-sales-production-scale.sql, openJobMaterialLines in 20260926093417_open-job-material-lines-invoker.sql, openSalesOrderLines in 20261006130001_demand-forecast-consumption.sql. All join through itemReplenishment to expose replenishmentSystem, leadTime, itemTrackingType.

  • openSalesOrderLines — salesOrderLineType != 'Service', status IN ('To Ship','To Ship and Invoice'). Newest def: 20261006130001_demand-forecast-consumption.sql. Make to Order lines ARE included, but their quantityToSend is netted down by the remaining output (quantity − quantityReceivedToInventory − quantityShipped) of live jobs linked via job.salesOrderLineId (statuses Planned/Ready/In Progress/Paused — the same set as openJobMaterialLines, so each unit is counted exactly once: SO line while unjobbed, job materials once a job is released, inventory once produced). Draft/Cancelled jobs do not suppress line demand. The view also exposes quantityToConsume — the PRE-job-dedup open quantity, used only by forecast consumption (a job-covered MTO line still consumes forecast).
  • openJobMaterialLines — job status IN ('Planned','Ready','In Progress','Paused'), methodType != 'Make to Order'.
  • openProductionOrders — job status IN those 4, salesOrderId IS NULL (make-to-stock jobs only); quantityToReceive = productionQuantity − received.
  • openPurchaseOrderLines — purchaseOrderLineType != 'Service', status IN ('To Receive','To Receive and Invoice','Planned'); dueDate = the line's requiredDate, promisedDate = the line's promised date, else the order delivery's receiptPromisedDate.

The item planning chart reads the live lines

api+/items.$id.$locationId.forecast.ts builds the chart's supply bars from openPurchaseOrderLines / openProductionOrders bucketed by purchaseOrderLineArrivalDate / jobCompletionDate (both exported from @carbon/planning) through the pure bucketSupplyByPeriod (items/ui/Item/planningSupplyDemand.ts, tested) — overdue in the first week, past the horizon dropped, summed per (week, source). It no longer reads supplyActual / supplyForecast, which only a run refreshes: a PO raised or increased from the drawer moves the projection at once, and a new order never replaces the week's existing bar. Each PO row in the Supply & Demand list carries that arrival date as its dueDate (the promise alone left a planned line as "No due date"). The legend is a what-if: projectedChange (same file) leaves a hidden series out of the running projection, stockout and below-safety detection, as removing a suggested order does.

When a PO line arrives — one rule

purchaseOrderLineArrivalDate (packages/planning/src/mrp/supply-date.ts, pure, tested): promised date, else required date, else order date + lead time (7 days when the item has none; from today when the order has no date). Both runMrp (which week the supply lands in) and generatePlanningActions (the order's "current date" for Expedite / Defer) call it. They used to disagree — the projection never read the required date, the check read it first — so applying an Expedite, which writes the required date, moved the action and left the projected shortage and its Order suggestion in place. Never date a PO line anywhere else.

A PROMISED date (the line's, else its delivery's receiptPromisedDate) is the supplier's, and planning writes only the required date, which a promise outranks. So an Expedite / Defer on a promised line is requiresManualAction ("Review on PO", OpenSupplyOrder.dateIsPromised), and both planning routes refuse to move its date: Apply sends it to review, and the drawer's inline due date edit returns 409 (promisedDateOf, purchasing+/planning.update.tsx). Applying it used to mark the action done, move nothing, and get the same action back from the next run. Quantity actions on a promised line are unaffected.

When a job finishes — one rule

jobCompletionDate (same file, tested): the job's due date, else today + 30 days for a No Deadline job (the default on a new job), else today. Both engines call it. The reschedule check used to skip an undated job that the projection counted as supply, so the two saw different supply and the job was never offered a Cancel, Defer or Expedite.

Reads and the horizon in generatePlanningActions

  • The generator's reads are grouped: the responsible-employee resolver and the two open-supply views in one Promise.all, then the three demand tables, on-hand and the open jobs in a second (five Kysely reads at once — getJobDatabaseClient() shares the 16-connection process pool, so a bounded group leaves room for the run's other work). They were six waits in a row.
  • The two planning RPCs are read through fetchAll with .order("id"), like every other read in the run. A bare client.rpc(...) stops at PostgREST's max_rows (1000); an item missing from those rows has no candidates, and the diff then deletes its existing actions, dismissals and assignee overrides included.
  • Change actions are derived BEFORE new-supply sizing, and sizing reads projectionsWithExpedites: the projection with every open order counted from its need week — every Expedite done, and an order late by no more than the reschedule tolerance (no Expedite) counted from its first need too (firstNeedPeriodByOrder, the same walk as deriveChangeActions). Sized on the raw projection, a shortage an Expedite covered also got an Order for the same week; and a need this week covered by a PO landing a few days into next week read as short, so sizing ordered it again and the fold made it "Increase from 100 to 200" on that very PO — then a Decrease on the next run.
  • Release (deriveReleaseActions, migration 20261006210557): every line of a Planned PO and every Planned job gets one, dated releaseByDate — the order's due date (purchaseOrderLineArrivalDate / jobCompletionDate) less the item's lead time less one day, so due in 8 days with a 7-day lead time is today. A PO is released once, so all its lines carry the EARLIEST line's date (earlierRelease). It is raised only from RELEASE_NOTICE_DAYS (1) before that date — every planned order has one, so raised weeks out it was a standing row nobody could act on; the diff-write deletes an Open one whose date moves back out. horizonDate is that date, isASAP once it has come, latestOrderDate null (not new supply), and an order MRP would Cancel gets none; it sits beside a change to the same order (the natural key includes the type). It is never applied by the planning routes (Apply Suggested Changes skips it, isApplyablePlanningAction, and both Apply routes refuse the type): the row's Release button runs the order's OWN release from the page through PlanningActionHandlers.onRelease — purchasing opens the PO's Finalize modal (usePurchaseOrderPlanningCommands().finalizePurchaseOrder), production posts the job to the jobs table's release route (useJobPlanningRelease → path.to.bulkReleaseJob: the job page's readiness checks, the release, the location's schedule run). A host with no onRelease gets a link to the order instead. It applies only while the order is Planned — MRP stops raising it, and between runs the planning pages drop it once the order's live status moves on (isStaleRelease in usePlanningActions; the grid RPCs' Actions filter ignores it the same way, 20261006205037). It lights the Order button's dot red on and after its day and not before (every planned order has one); its date reads late only once the day has passed. In the drawer a change on the same order takes the row's one action slot (actionForOrder).
  • deriveChangeActions measures Expedite / Defer from the order's EXPECTED date: its due date, or today when it is overdue (laterDate). Measured from the old due date, a late order read as early and got a Defer to a date already past. The NEED date is clamped the same way: a need in the current week is needed today, not on the week's (past) start. Apply writes the suggested date onto the order, so an Expedite to last Sunday made the order overdue, read as arriving today, and with a tolerance under a week the same Expedite came back on every run. convertOrdersToIncreases compares both dates clamped.
  • Quantity suggestions are what the order will hold (quantityAfterApply). Apply writes a PO line in whole PURCHASE units (conversionFactor, read for the open lines whose factor is not 1), so a Decrease to 55 on a 10-per-box line wrote 60 and the next run asked for 55 again, forever. Decrease and Increase on a PO line are rounded up to the purchase multiple, and a line already at it gets no action. An Increase names the PO line's supplier, not the item's preferred one.
  • A frozen order is never Expedited, Increased or Decreased (isOrderFrozen): its due date less the item's lead time is before today — every overdue order, and one due sooner than a lead time away. It is already being made or shipped, so none of the three can be carried out. A shortfall it would have absorbed stays a new Order / Make (convertOrdersToIncreases skips it), and a frozen order late beyond the tolerance is left where it lands in the sizing projection (firstNeedPeriodByOrder's frozen argument), so the need it misses gets new supply instead of a silent gap. Defer, Cancel and Release are unchanged. Before this an overdue job got "Increase from 111 to 131" beside a Make for the same week.
  • Change actions keep the policy's order rules (orderSizingRules, the same definition the page split reads). A Decrease keeps the policy's minimum and lands on its whole multiples — orderMultiple, a Fixed Reorder Quantity order's fixed quantity, a Maximum Quantity order's lot size (reducedOrderQuantity, orderRules on deriveChangeActions). A new-supply suggestion folds into an open order only when the result fits the policy's maximum — a batch or the max order quantity, the fixed reorder quantity (maximumPerOrder on convertOrdersToIncreases); otherwise it stays a new Order / Make. Before this a 50-unit batch job was offered "Increase to 100" and a 40 on a multiple of 10 "Decrease to 37".
  • deriveChangeActions claims the policy floor (safety stock, reorder point, minimum reserve) FIRST — from on-hand, then the earliest orders — and an order holding part of it is never Cancelled, Decreased or Deferred. The floor has no date and never Expedites an order by itself. It used to take what the demand walk left, undated: an order holding safety stock was dated by a later demand and deferred, which put stock under the floor until that date.
  • deriveChangeActions gives NO verdict on an order due after the last planning week (WEEKS_TO_PLAN = 48; MRP itself plans 72). Its demand is not loaded, so it would otherwise read as "nothing needs it" and be offered for Cancel. Such an order is not pulled in to cover an earlier need either.
  • runMrp throws when the forecast-consumption settings cannot be read; the window decides what is persisted as consumedQuantity, so defaults are not a safe fallback.
  • A job order is measured in GOOD units — job.quantity less quantityReceivedToInventory, from one read of the company's open jobs (the same four statuses as openProductionOrders), never the view's quantityToReceive, which is productionQuantity (quantity + scrap) less received. A change action is applied to job.quantity, so on the view's figure every job with a scrap allowance read as over-supplied, got "Only 80 of 84 is required", and got it again after the Decrease was applied. updatePlanningJob restates scrapQuantity for the new quantity from the item's scrap rate, as insertJob derives it. (The projection itself still books productionQuantity as supply — a separate, older choice.)
  • The demandProjection.consumedQuantity write touches only rows whose value changed (IS DISTINCT FROM) and leaves updatedAt / updatedBy alone: consumption is derived, and the audit columns name the planner who entered the forecast.

Planning UI

  • Production: apps/erp/app/routes/x+/production+/planning.tsx (view: "production") + ProductionPlanningTable under apps/erp/app/modules/production/ui/Planning/.
  • Purchasing: apps/erp/app/routes/x+/purchasing+/planning.tsx (view: "purchasing") + PurchasingPlanningTable under apps/erp/app/modules/purchasing/ui/Planning/.
  • Weeks are one column, not 48. Both grids render the per-period projection (week1…weekN) as a single Stock Availability strip (modules/production/ui/Planning/PlanningWeekStrip.tsx): a small column chart on a zero line — stock above it in a neutral tone, a shortfall hanging below it in red, a tick on the line for an exact zero, nothing when MRP wrote no projection. Red is the only hue, so a healthy row stays quiet and sign is carried by direction as well as colour (it replaced a flat red / grey / green strip that said nothing about depth and turned a short row into a wall of colour). Each row is scaled to its OWN range (planningWeekGeometry, planning-week-geometry.ts, unit-tested): heights compare along a row, not between rows. One tooltip per row follows the hovered week (the shared TooltipContent takes an anchor for this) and shows the week label, its date range and the projected quantity; the week label (strip tooltip, CSV headers, Demand Forecasts table) comes from usePlanningWeekLabel (ui/Planning/usePlanningWeekLabel.ts): "Present Week", "Week 2", … or, with companySettings.useCalendarWeeks, the ISO week of each period (planningWeekNumber, read three days into the Sunday-start period, tested). The hovered week is marked by an overlay band that is cleared on pointerleave — it used to stay on the last week touched. The per-week numbers stay in the CSV as exportOnlyColumns keyed week1…weekN, so an export is unchanged.
  • Suggested orders ARE the Order / Make actions. The order drawer's Suggested Orders / Suggested Jobs, the row's Order / Make button quantity and a bulk order for rows never opened all read the item's OPEN new-supply actions (openNewSupplyActions + plannedOrdersFromActions / productionOrdersFromActions, ui/Planning/planned-orders-from-actions.ts, tested by apps/erp/test/planned-orders-from-actions.test.ts): each action split back into the orders its policy sized, on the action's own week, in purchase units for a PO (rounded up by the chosen supplier part's factor). MRP sums the orders a week needs into one action (the natural key), so splitIntoOrders + orderSizingRules (@carbon/utils, by the action's policyName) restore them: Demand-Based Reorder one per batch (lotSize) spread across the week, Fixed Reorder Quantity one of that quantity per day, Maximum Quantity one of at most maximumOrderQuantity per day; Stock Only one order. A round-trip test pins the split to computePlanningOrders. One order per action turned a 120 on a batch size of 50 into one job of 120 and three fixed reorders of 100 into one order of 300. Each suggested job carries the action's policyName / reason / triggerValues (the chart's order popover reads them), and its isASAP is judged per job against the page's locationToday from its OWN start date — the action's flag is one per week as of the run (Maximum Quantity keeps the run's flag as a condition, since only the run knows the stock was short). It becomes the created job's deadlineType. They used to be sized again in the browser from the weekly projections (calculateOrders), which missed what MRP does after sizing — moving expedited supply, folding a shortfall into an open order as an Increase, summing each week into one action — so the drawer showed daily 10s against weekly 50s and offered a new order for the shortfall an Increase already covered. A dismissed Order is not offered; a shortfall whose Increase was dismissed gets no Order until MRP writes one, and the planner adds it by hand with New. The rows refresh when MRP runs.
  • Latest Order Date (both grids, after 1st Negative On Hand): the last day the row's next suggested order can be placed and still arrive on time — the grid RPC's latestOrderDate, the MIN order-by date of the item's open new-supply actions, so the cell, its sort and the drawer agree. Red once the day has passed (before the location's today); "-" when nothing needs ordering. The tooltip shows the required date (order-by date plus lead time) and the lead time; the CSV carries the ISO date. Cell: ui/Planning/LatestOrderDate.tsx.
  • Shared, not copied. The two grids differ only in their own columns (item link, supplier, lead time, quantity to order, the Order button) and wiring. Everything else lives once in production/ui/Planning/: usePlanningActions (the worklist fetcher and toast, fenced and filtered actions, the batched submit, and the actionHandlers the action lines and drawers spread), planningColumns (the shared column definitions, typed to each grid's row) and PlanningDrawerParts (PlanningPolicySummary with a slot for the purchasing drawer's supplier rows, BeyondFenceButton, periodIdFor). Change the shared piece; a copy in one grid drifts, as the untranslated labels in one drawer did.
  • One "today": the location's. Every planning surface that marks a date late — the Latest Order Date cell, the expanded action lines (PlanningActionLines) and the drawers — takes the loader's locationToday as a prop. None reads the browser's zone: a planner in another timezone saw an action red in one column and not in the next.
  • Both have a "Recalculate" button (mrpFetcher.Form POST to path.to.api.mrp(locationId)) whose tooltip comes from useMrpScheduleDescription (~/hooks): "MRP runs automatically every 3 hours…" or "…every day at 2:00 PM…" when the company set companySettings.mrpRunTime. The Inventory table's button uses the same hook.
  • Planning actions (the MRP worklist, spec §P1.7) live INSIDE each grid, not in a separate list. Both routes load the location's persisted planningAction rows (getPlanningActions, Buy/Make by kind) and pass them to the grid, which renders an Actions column (one ICON chip per open type with a count and the type name in a tooltip, a muted dismissed chip; always one line so busy rows are no taller than the rest; static type filter), a pulsing dot on the row's Order / Make button (planningActionDot, ui/Planning/planning-review.ts: only open actions that add or advance supply — Order, Make, Expedite, Increase — light it: red when one is ASAP, green otherwise; an Increase lights it with nothing new to order. A Decrease, Defer or Cancel never lights it, and is never drawn late in the expanded row either (isPlanningActionLate) — its date is where the order sits, not a deadline), and an expandable row (renderExpandedRow/canExpandRow, gated to items with actions) listing the item's actions as child lines — type, target PO/job hyperlink, quantity, DateTime (red when past), reason, assignee — each with ONE button: Apply (open change action on an uncommitted target), Review on PO/Job (requiresManualAction), or Order…/Make… (opens the grid's order drawer; Order/Make rows are fulfilled by the existing Order button, never applied as a change). A per-line ⋯ holds Assign to Me and Dismiss/Reopen. The bulk menu gains Apply Suggested Changes (every applyable action on the selected items, ONE batched request). Shared UI: modules/production/ui/Planning/PlanningActionLines.tsx; every mutation posts to the existing planning.update.tsx cases (apply/dismiss/reopen/assign). Cancel on a job runs cancelJob (production.server.ts), the job status route's own path: Cancelled (only from Draft / Planned here), then picked material back and picking lists closed. On a PO line it DELETES the line, in one statement that also requires a Draft / Planned PO and nothing received or invoiced; when that guard holds the row back the action goes back to Open as "Review on PO". Never shortClosePurchaseOrderLine — it recomputes the header status from the lines and turned an unsent Draft into "Completed". Apply is set-based. Purchasing: applyPurchasingPlanningActions(db, …) runs the whole batch in ONE Kysely transaction — the claim, one UPDATE … FROM (VALUES …) for dates, one for quantities, one DELETE for cancels, and the un-claim of refused rows — about five round trips for any batch size, all-or-nothing. Production: applyProductionPlanningDateActions does the same for Expedite / Defer (claim, the jobs, the jobs already on the target dates, one UPDATE of due date + priority via the pure nextJobPriority), then the route sends ONE schedule-inputs-changed event for the batch (a "reorder" event re-stamps the whole company whatever its job id). Increase / Decrease / Cancel on jobs call postings with their own transactions, so they stay per job — grouped by job, three jobs at a time (async.map), each claimed right before its own change. The claim and release inside a transaction live in modules/production/planning-action-claims.ts, shared by both services; the release reopens the row, or deletes it when an MRP run has meanwhile written a fresh Open row for the same need (the natural-key index). Tests: apps/erp/test/apply-purchasing-planning-actions.test.ts, apply-production-planning-date-actions.test.ts. Every Apply write carries its own Draft / Planned condition (updatePlanningJob, updatePurchaseOrderLineSchedule, the Cancel delete), so a job released or a PO sent between the route's status read and the write is left alone and the action goes to review — a read-then-write gate let it through. A failed write gives its claim back through releasePlanningActionClaim, which deletes the claimed row instead when an MRP run has meanwhile written an Open row for the same need (the reopen hits the natural-key index, 23505); a failed release is reported, not swallowed. Job Cancel holds its condition the same way: cancelJob flips the status first, guarded on Draft / Planned, and returns material only after it. Permissions: both planning.update routes make one service-function call per action (orderPlannedJobs, applyPlanningActions, … in production.server.ts; orderPlannedPurchases, applyPlanningActions, … in purchasing.server.ts). Each function's permission is the gate, and its body writes as the system: create for an order, update for everything else. Purchasing Apply deletes a PO line for a Cancel only when the caller also holds delete: "purchasing" (ctx.can). An assignee or responsible employee is saved only after isActiveCompanyEmployee (shared.service.ts), and planningAction is read-only through the API (manifest rule: read is anyOf("production_view", "purchasing_view"), since both planning pages read it with the user's client; MRP and these routes write it with the service role). The Actions column filter (filter=planningActions:eq:<type>) and the Assignee column's people filter (filter=planningAssignee:in:<userId>,… — the same people list every other assignee filter uses; the column is hidden by default and shows the row's assignees when turned on) are not grid RPC columns: the loader strips them with resolvePlanningActionScope (ui/Planning/planning-action-scope.ts, pure, unit-tested) and passes them to the grid RPC as ARGUMENTS (action_types, action_assignees), which keeps the items with a matching OPEN action inside the item's planning horizon. The loader then reads the actions for the rows ON THE PAGE (getPlanningActions with itemIds, paged). An earlier version loaded the location's first 500 actions and resolved item ids from them — it silently dropped items past the cap and could not see the horizon.
  • Reschedule tolerance. companySettings.rescheduleToleranceDays (INTEGER NOT NULL DEFAULT 7, 20261006130000) is read by generatePlanningActions as toleranceDays into deriveChangeActions: an open order gets an Expedite / Defer only when its date is STRICTLY more than the tolerance from the date it is needed, and a dismissed action stays dismissed while its date moves within the tolerance. Authored at Settings → Planning (RescheduleToleranceCard, intent setTolerance, rescheduleToleranceValidator in settings.models.ts, 0–365).
  • Planning ownership (the owner ladder). resolveResponsibleEmployee / loadResponsibleEmployeeResolver (packages/planning/src/mrp/responsible-employee.ts): itemPlanning.responsibleEmployee → itemPostingGroupResponsibility (the item group AT the location) → location.responsibleEmployee → companySettings.defaultResponsibleEmployee, first non-null wins. The diff re-resolves an action's assignee on every run unless assigneeOverridden (set by Assign) — and the UPDATE re-checks that flag on the row itself, so a planner who assigns between the run's read and its write still wins.
  • Settings → Planning (x+/settings+/planning.tsx, cards in apps/erp/app/modules/settings/ui/Planning/): ResponsibleEmployeeCard (intents setCompanyDefault, setLocation, setItemGroup; setLocation writes location, a resources table, so a user without resources_update matches no row under RLS and is told so rather than shown a success), RescheduleToleranceCard (setTolerance), PlanningPurchaseOrderApprovalCard (setPlanningPurchaseOrderApproval → companySettings.skipApprovalForPlanningPurchaseOrders, default on: a PO the planning Order button created — purchaseOrder.createdFromPlanning, cleared by any manual line change — finalizes without the approval rule), PlanningHorizonCard (setPlanningHorizon, planningHorizonValidator), ForecastConsumptionCard (setForecastConsumption, forecastConsumptionValidator, 0–52 weeks each), MrpScheduleCard (setMrpSchedule, mrpScheduleValidator) and CalendarWeeksCard (setCalendarWeeks → companySettings.useCalendarWeeks, default off: display only, see the week strip above). An employee id is saved only after isActiveCompanyEmployee; a bad value answers 400.
  • Planning horizon (time fence). itemPlanning.planningHorizonDays (per item + location, Part → Planning) else companySettings.defaultPlanningHorizonDays (Settings → Planning) else none. 0 means "no fence" at either level (NULLIF(COALESCE(item, company), 0) in the grid RPCs): an item's 0 is how it opts out of a company default, which an empty field would inherit. It is not "zero days" — that put the fence on today and hid nearly everything. It is a READ-TIME LENS, never an engine input: generatePlanningActions writes actions for the whole window and stamps each with horizonDate — the earlier of the target order's current date and the suggested date, so a Defer counts from where its order sits today and an Expedite from when it is needed — and the grids surface only rows with horizonDate <= today + days. That is what lets a planner move ONE row's fence in the Planning Horizon column (useTimeFenceOverrides, page state, gone on reload, never written to the item) without an MRP run. Named planningHorizonDays on purpose: planningTimeFenceDays is reserved by the MRP v2 spec for the auto-firm fence, a different concept.
    • The fence comparison exists twice and must stay one inclusive <= on ISO dates: in SQL (get_*_planning_grid, the saved horizon, for the Actions filter) and in ui/Planning/planning-fence.ts (on screen, override included; unit-tested). Sort and filter therefore use the SAVED horizon — an on-screen override changes what a row shows, not which rows match.
    • Inside the fence: the Actions chips, the expanded row, Apply Suggested Changes, the row's Order/Make quantity, and a bulk Order Parts / Create Jobs on rows never opened in the drawer. The drawer opens on the suggested orders REQUIRED on or before the fence. A "N More After " button EXTENDS the row's fence to the last suggested order rather than copying rows in — the fence is the one piece of state, so the order list and the grid row follow together. The drawer marks the fence on the chart and carries the same Planning Horizon control as the grid cell.
    • Moving a row's fence DROPS that item's entry in the grid's ordersMap (onFenceChange): the drawer's draft list is kept per item once opened, and a stale one would neither show the newly included orders nor offer them. That discards manual edits to the draft, by design.
  • The order drawer is two tables with two save models (ui/Planning/PlanningOrderGrids.tsx, both on the shared Grid), because a row that does not exist yet cannot autosave:
    • Suggested Orders / Suggested Jobs (SuggestedOrdersGrid) — a DRAFT. Quantity and due date are click-to-edit; the edits live in the planning grid's ordersMap and nothing is written until Order / Make. The drafts survive a loader reload (Apply, Dismiss, Assign inside the drawer revalidate it) and are dropped only when the page scope changes (the search params), MRP recalculates, or an order is placed — clearing on every data change wiped the planner's edits mid-task. The Order By / Start By column is derived (due date less lead time).
    • Open Orders / Open Jobs (OpenOrdersGrid) — existing PO lines / jobs at the page's location (both drawer reads filter on locationId, and updateLine / updateJob refuse another location's record with 409). A cell edit SAVES that one field (optimistic, reverted with a toast on failure) through planning.update's updateLine / updateJob action, which re-reads the record under the company and refuses a committed record with 409. Jobs: updateJob and Apply share isJobEditableFromPlanning (production.models.ts), an allowlist of Draft / Planned — anything else (on the floor, finished, closed, cancelled) is "Review on Job". POs: updateLine, Apply and the drawer's editable rows share isPurchaseOrderEditableFromPlanning (purchasing.models.ts), the same Draft / Planned allowlist — a PO in approval (Needs Approval, To Review, Rejected) or sent is "Review on PO", matching MRP's own isCommittedPurchaseOrderStatus. A quantity edit restates the line's tax pair (taxPairForQuantity): the extended price is generated, the tax amount is stored. A failed follow-up on a saved job edit (recalculating requirements, telling the scheduler) is reported as a warning, never a revert — the edit stands. A Draft job (listed, editable, charted as new supply, but NOT MRP supply) shows a Plan button when no action targets it (renderRowCommand): planJobFromPlanning (production.server.ts) checks the location, that no sales order owns it and that it is Draft, then planDraftJob (production.server.ts) recalculates its requirements (a failure leaves it Draft, as releaseJobs does), flips it to Planned (updateJobStatus fromStatuses: ["Draft"]) and runs MRP — after the flip, so the run counts it and the Make suggestion shrinks by it. No scheduler notice: only released jobs are scheduled. The drawer then drops the item's draft list to re-seed. Before this a Draft job and a Make for the same need sat side by side and could both be built (the pre-#1601 drawer promoted Drafts through order, which now refuses existing jobs). Locked rows render as plain cells (Grid isRowEditable). Each row carries the planning action that targets it — type, suggested value, reason, Apply / Review — so there is no separate action table. Released jobs (Ready / In Progress / Paused) are listed read-only for that reason: an action needs its job's row to sit on. An action whose order is not in the list still gets a read-only row.
    • The order's status is an icon, not a column. Status iconOnly (@carbon/react, passed through PurchasingStatus / JobStatus) renders the status colour and icon in front of the PO / job number, with the name in its tooltip — it says why a row is Review rather than Apply without adding row height or a column the drawer has no width for. The drawer takes it from the open line / job (OpenOrdersGrid renderStatusIcon); the grid's expanded row (PlanningActionLines) and the drawer's read-only fallback rows take it from the action, which getPlanningActions enriches with purchaseOrderStatus / jobStatus.
  • getPlanningActions reads the item, the PO behind a line and the job as PostgREST embeds, and chunks the page's item ids (100 per request). It used to look them up afterwards with .in("id", <one id per action>); a page of busy parts (2,000+ actions) put 50 kB of ids in the URL, the gateway answered 431, and the loader's ?? [] turned that into a grid with no actions. The loaders now log and throw on a failed read instead — an empty Actions column must never be what a failure looks like. The id lists a bulk selection sends (Apply, Dismiss, Reopen, Assign, and Apply's job / PO line reads) have no page bound at all, so those go through Kysely as ONE statement each (getPlanningActionsByIds, markPlanningActionsActioned, dismissPlanningActions, reopenDismissedPlanningActions, assignPlanningActions take the db handle): the ids are bound parameters, never a URL. The set-based Apply claims and changes a batch in one transaction; the per-job path claims each action right BEFORE its own change, so a request that dies there strands at most the actions in flight. Every claim (claimPlanningActions, markPlanningActionsActioned) RETURNS the row's suggestedQuantity and suggestedDate, and Apply writes THOSE — an MRP run between the page's read and the claim can move an Open action in place, and the page's values would be the stale suggestion. A date apply (applyProductionPlanningDateActions, updatePlanningJob) also restates a "No Deadline" job as Soft Deadline (deadlineTypeForPlanningDate): the job form hides the due-date field for No Deadline, and nextJobPriority would rank the dated job with the undated weight.
    • Purchasing quantities are in PURCHASE units (the line's purchaseQuantity; the open-lines view reports inventory units), and an action's suggested quantity is converted and rounded up as Apply does. The chart still receives existing orders in inventory units.
    • A manual edit does NOT resolve the suggestion on that row: the action stays until the next MRP run re-evaluates the order. The earlier single list mixed both: an edit to an existing order sat unsaved until Order was pressed and was dropped by Close.
  • Grid RPCs are wrappers. get_purchasing_planning_grid / get_production_planning_grid (latest: 20261006205037_planning-grid-order-quantity.sql) select p.* from the base RPC and add itemPostingGroupId (Item Group column + filter), planningHorizonDays, timeFenceDate, firstNegativeDate (1st Negative On Hand: the start of the first week whose projection is below zero — weekly, because MRP buckets by week), latestOrderDate (the MIN of the item's open new-supply actions, which makes Latest Order Date sortable; the cell shows the same value) and orderQuantity (the SUM of the item's open Order / Make actions inside its saved fence, 0 when none — the grids' default sort, then the part number; there is no Qty to Order column, the row's Order / Make button shows the quantity). The base RPC's own quantityToOrder (calculate_quantity_to_order, a second sizing of the projection in SQL) is NOT shown or sorted on any more: it never sees what MRP does after sizing (Expedites, Increases, orders placed since the last run against a projection only a run refreshes), so it put items with nothing to order above real shortages. It stays in p.* for generatePlanningActions' Stock Only path. The base RPCs stay the one definition of the projection and are what generatePlanningActions reads. Adding a column to a base RPC means re-creating its wrapper with the same column — it fails loudly (return type mismatch) until then. Generated types mark every RPC column non-null; the new ones are not (PlanningGridColumns in production/types.ts).
  • Create planned orders — planning.update.tsx in each module:
    • production (orderPlannedJobs, create: "production"): inserts jobs + job methods, upserts supplyForecast ('Production Order'), then recalculateJobRequirements().
    • purchasing (create: "purchasing", role employee): one PO per supplier per WEEK (planningPurchaseOrderWeek: Sunday-start, as the grid's periods; a late or undated order is in the current week). It reuses the oldest open Draft/Planned Purchase PO for the supplier, at the planning location, in the supplier's currency, whose lines are ALL in that week (findPlanningPurchaseOrder), else inserts one. A PO with lines in several weeks (raised before this rule) takes no more orders; matching on ANY line in the week let such a PO keep collecting weeks. Before this, every week went on one PO, so finalizing it to send the first week locked the later weeks against MRP's Defer / Decrease / Cancel. A PO with no lines is never reused. All candidate POs and their lines are read once per submit. An order whose item and requiredDate match an existing line adds to it, restating the tax pair (taxPairForQuantity). Upserts supplyForecast ('Purchase Order') per order period.

Gotchas

  • The cron is Inngest, not Trigger.dev. There is no apps/erp/app/trigger/mrp.ts. The engine itself is in-process Node (runMrp from @carbon/planning), NOT a Supabase edge function — the mrp Deno function was deleted.
  • MRP itself writes demandForecast/demandActual/supplyActual/ demandForecastSource/planningAction; it never inserts supplyForecast — that comes from the user-driven planning.update routes (planned orders) — but Phase 7 deletes every supplyForecast row at the company's locations.
  • The engine runs full MRP regardless of type/id scope: type is only logged (run started), never used to narrow the reads, so every run is company-wide.
  • Don't rebuild the DB to test schema; ask the user (per AGENTS.md).