paths: - "packages/planning/src/scheduling/" - "apps/erp/app/routes/x+/priority+/" - "apps/mes/app/routes/x+/operations.tsx" - "packages/database/supabase/migrations/schedul.sql"

Production Scheduling: data structures + flow

How job operations get sequenced onto work centers, scheduled with dates, and displayed. The scheduling engine lives in packages/planning/src/scheduling/ (relocated from the Supabase edge runtime) and runs IN-PROCESS in Node — the ERP app (route actions, production.service.ts) and @carbon/jobs (the replan wave, the recalculate task) import runLocationSchedule / runExpediteWhatIf from @carbon/planning and execute it in-process, eliminating the edge cold-start + HTTP round-trip that made a regen take >2s on trivial data. The schedule Deno edge function was DELETED — there is no remaining edge wrapper; every caller goes through the in-process engine. Not MES, not a DB function. The boards only read results and feed inputs. Migrations are timestamp-ordered; newest wins and these functions/columns have been revised many times — read the newest, not the first match.

Spec/plan: .ai/specs/2026-08-19-schedule-in-process-node.md + .ai/plans/2026-08-19-schedule-in-process-node.md.

Capable-to-promise on a quote (quote-lead-time.ts, runQuoteLeadTimeWhatIf): the pure WorkCenterSelector is driven with SYNTHETIC ops built from a quote line's routing/BOM (buildQuoteSimulation), placed per quantity against TWO buildFiniteContext snapshots — queued (excludeJobIds: []) and front-of-queue (whole batch excluded, like the expedite what-if). A purchased/short-stock material sets the optional materialReadyAt floor on its consuming op (never set on jobs, so live scheduling is unchanged). Persists nothing; buildFiniteContext + loadAvailabilityWindows were lifted out of the engine into finite-context.ts so the engine and this what-if cannot drift. Spec/plan: .ai/specs/2026-09-22-quote-lead-time-prediction.md.

Where it lives

  • Orchestration: packages/planning/src/scheduling/run-schedule.ts (runLocationSchedule / runExpediteWhatIf) loads a whole LOCATION's open jobs and runs new SchedulingEngine(...).run() once per job in one deterministic forward pass (§ Engine pipeline). Every Node caller goes through it — one orchestration, zero drift. It is exported via @carbon/planning; its shared edge-lib deps are reached through the @carbon/database subpath barrels (types → @carbon/database, postgres → @carbon/database/client). Modules in packages/planning/src/scheduling/ (scheduling-engine.ts, dependency-manager.ts, date-calculator.ts, need-by-calculator.ts, work-center-selector.ts, apply-work-center-selections.ts, priority-calculator.ts, material-manager.ts, duration-calculator.ts, assembly-handler.ts, master-data-provider.ts, machine-availability.ts, calendar-utils.ts, slot-allocator.ts, conflict-messages.ts, types.ts). All engine READS go through the MasterDataProvider interface (KyselyMasterDataProvider is the live impl); writes stay on Kysely. The people reads (getPeopleAssignments/getPeopleAbsences) take the plant timeZone so peopleAssignment.date range bounds resolve on the plant's calendar, not UTC's. resource-manager.ts was dead code and has been deleted. machine-availability.ts / calendar-utils.ts / slot-allocator.ts / apply-work-center-selections.ts / duration-calculator.ts / date-utils.ts / operator-eligibility.ts / people-utils.ts / need-by-calculator.ts are pure and have unit tests (pnpm --filter @carbon/planning test, vitest — colocated *.test.ts), alongside the determinism + envelope suites. date-utils.toIsoDate normalizes pg DATE columns (JS Date at local midnight) to "YYYY-MM-DD" — required before any lexicographic date comparison (operator expiry).
  • ERP authoring boards (apps/erp/app/routes/x+/priority+/): operations.tsx (ops Kanban; drag → operations.update.tsx → api.production.reorderScheduleOperations, which writes jobOperation.workCenterId + priority and, only when a card moved to another work center, calls notifyScheduleInputsChanged(…, "work-center", …); a reorder within one column re-sequences the dispatch order and reschedules nothing — the board header carries a tooltip: "Reorders dispatch sequence and work center only — does not reschedule. Change dates on the Dates board.") and dates.tsx (jobs-by-due-date Kanban; drag → dates.update.tsx → api.production.moveScheduleJob, which writes job.dueDate + priority and, in the same UPDATE, the deadline type the date implies (deadlineTypeForDueDate: a dated No Deadline or ASAP job becomes Soft Deadline — the scheduler ignores an ASAP date that MRP would plan supply to — and an undated Hard / Soft Deadline job becomes No Deadline), then calls notifyScheduleInputsChanged(…, "reorder", …) — which only stamps the jobs schedule-outdated; the debounced wave regenerates the whole location. There is no immediate single-job path). people.tsx is the People page with a segmented view switcher (?view=): the People board (manning board: drag employees onto work-center columns per date; Unassigned column is position: sticky — needs min-w-max on the shared BoardContainer row and MeasuringStrategy.Always on the DndContext; mutations via people.update.tsx, which calls one people service function per intent (assignPerson, movePerson, markPersonAbsentRange, … in production.server.ts); each fires notifyScheduleInputsChanged(…, "people", …, workCenterId) — a MOVE notifies BOTH the destination and the source work center (via movePeopleAssignment's previousWorkCenterId), so the station the person left re-plans too instead of keeping a stale booking), a week matrix (PeopleMatrix.tsx: employee×day grid + assigned-vs-needed coverage as sub-tabs, department filter), and a week capacity board (PeopleCapacity.tsx). Both read each station's working windows: getWorkCenterWorkingWindows (the engine's ladder and holidays; a station's linked shifts at another location are loaded too, getShiftsWithTimesByIds) less the open offline maintenance outages (getWorkCenterOutages → downtimeOutages, @carbon/planning, the rule the engine uses). Capacity math: Demand = the hours each open jobOperation still needs as the engine counts them (remainingWorkHours: setup + max(labor, machine), netted by quantity complete, setup dropped once a production event exists) by due date (Draft/Planned jobs excluded — released work only; overdue lands in a Past-due column); Scheduled = capacityReservation.workHours split across the days of the booking by the station's working time in each day, so a booking from Monday noon to Tuesday 11:30 puts its hours in shift time and none on the night or a weekend (no working time falls back to the clock-time share); Available = the working hours in each plant day (workingHoursByDay: 0 on a holiday, less maintenance downtime, and the real day length on a lights-out station, 23 or 25 hours across DST). Coverage (Matrix) needs ceil(attended hours / person-day hours) people per station-day, where attended hours are the setup + labor share of each booking laid on the station's working time from the booking's start (attendedHoursByDay, getOperationAttendedShares); machine time and lights-out stations need nobody. On a shift tab only the hours inside that shift count (within, getShiftWorkingWindows), each on the day the shift STARTS: the roster puts Friday's night shift on Friday, so its hours past midnight are Friday's (a run longer than a day, back-to-back shifts merged into one window, is split by the clock). A shift id from the URL that is not one of the location's shifts reads as All shifts. Load renders as hours over/free (+Xh / Xh free), not %. Shift + location filters live in header popovers; the shift filter's "All shifts" option (shiftId null on drag) creates shift-less assignments that resolve hours via the ladder. The Board has Day | Week period tabs — Week renders PeopleWeekBoard (drag once = assigned all week via assign-week/unassign-week/move-week → assignPeopleWeek etc., one row per working day from the shift's weekday flags; matrix/capacity are week-only, no month range — removed on request). Header also has a Calendar date-jump popover (Calendar is exported from @carbon/react for this), copy previous day/week (copy/copy-week — day copy preserves split hours, overtime never copies), and a "Time off" range dialog (absent-range → setPeopleAbsenceRange). The route delegates its pieces to ui/Schedule/People/: PeopleHeader (filters/tabs/date nav/copy/menu), OvertimeDialog + TimeOffDialog (conditionally mounted), PeopleCard + PeopleColumn (extracted from PeopleBoard), with the shift-hours/time ladders shared via peopleShared.ts; the Capacity view's demand/scheduled buckets are computed server-side by buildPeopleCapacityBuckets (modules/production/production.service.ts).
  • MES display (apps/mes/app/routes/x+/operations.tsx): the "Schedule" page is a Kanban (columns = work centers, cards = operations sorted by priority), not a Gantt. Read-only re display; operators execute via operation.$operationId.tsx. apps/erp/app/routes/x+/scheduling+/gantt.tsx is a placeholder Gantt with hard-coded sample trace data in its loader — not wired to the engine. MES dispatch.*.tsx routes are maintenance dispatch (machine breakdowns), unrelated.

Batch pre-pass (Released operation batches schedule as ONE unit)

batch-scheduler.ts (placeReleasedBatches + pure planBatchPlacements, unit tested). Runs inside runLocationSchedule AFTER loadOrderedBatch and BEFORE the per-job loop; runExpediteWhatIf calls it with persist: false, which REUSES the existing batch rows instead of recomputing (the sim must agree with its own snapshot). A pre-pass throw degrades to per-member placement (logged), never abandons the location run.

  • Auto work-center selection: a Released batch with NO workCenterId gets one from the pre-pass — earliest finish across the process's ACTIVE work centers at the location (ties: fewer existing reservations, then id) — persisted to the batch AND its members in the placement txn (IS NULL guard defers to a human pick landing mid-wave). Release therefore never requires a work center; no candidates at all degrades to per-member placement.
  • What blocks a batch: batchBlockingReservations decides which live reservations a batch is placed around. It keeps other jobs' bookings and other batches' rows. It drops this location's own batch rows, and every non-batch row of a job the run re-plans (orderedJobIds): the run replaces those bookings, so they must not push the batch later. Before this, the batch drifted later on every regen. A job that throws during the run is left out of the write, so persistLocationWrites clears its stored bookings too (failedJobIds): otherwise the batch could sit on top of one.
  • One reservation per Released (Active/Completing) batch, tagged capacityReservation.jobOperationBatchId; operationId/jobId stay NOT NULL by anchoring on the min member op id. Placeholder semantics mirror unplaceable ops (isPlaceholder = true when no slot; never blocks). A batch whose open members all carry ZERO time standards is a placeholder too, not a skip: NO_ESTIMATE_PLACEHOLDER_HOURS (1h) gives the forecast a drawable window (snapped forward to the WC's next working window via nextWorkingInstant, so it never draws on a weekend), workHours stays 0, and members carry composeBatchNoEstimatesConflict naming the data gap — a Released batch must never silently vanish (its reservation is its ONLY forecast surface, and zero-estimate ops are how the batch dropped off the forecast unnoticed).
  • Duration = @carbon/utils batchDuration: setup(max, zero once any batch event exists) + Σ run (Sequential) or + max run (Simultaneous) per process.batchType, run_i = max(labor, machine) net of remaining fraction.
  • Anchor = max(now, member predecessors' PERSISTED projectedCompletionAt) (same-method lower-"order" ops; same-batch members never self-anchor). Stale-by-one-wave by design: a predecessor freshly placed past the batch start gets composeBatchPredecessorConflict on the member and the next wave re-anchors.
  • Members pin to the window in work-center-selector.ts (a batchPlacements map threaded engine→selector; the branch generalizes the pinned Outside-Processing path): no per-member placement, NO per-member reservation, successors chain after the batch end, priority: 0 like OSP.
  • Three predicate rules keep the coalesced row alive: the per-job regen delete adds AND "jobOperationBatchId" IS NULL; the snapshot's excludeJobIds filter never excludes batch-tagged rows; and the snapshot's job-STATUS filter (capacityHoldingJobStatuses) also spares batch-tagged rows — a Released batch may legitimately anchor a Draft job (membership handoff pulls members ahead of their jobs). loadOrderedBatch widens job loading with Released-batch member jobs so they regen in the same wave. Those sparing rules make the batch's OWN lifecycle the only retirement path, so a status trigger on jobOperationBatch (20260907155426_cleanup-reservations-on-batch-exit.sql, mirroring the terminal-job trigger) deletes the tagged rows on → Completed and on unrelease (→ Planned) — without it a finished batch kept blocking the work center and an unreleased one double-booked it against the members' per-op placements. Dissolve needs no trigger: the FK's column-list SET NULL untags the row and the anchor job's next regen sweeps it.
  • Planned batches are NOT coalesced — members place per-op exactly as before release (bounded residual over-book, gone at release). Employee finiteness for batches is deliberately absent in v1 (WC reservation only).

Trigger chain (verified)

Rescheduling is no longer a single-job event — the old per-job reschedule trigger, its Inngest task, and the direct-trigger service helpers were all removed. Every scheduling input change now funnels through one thin emitter, notifyScheduleInputsChanged(companyId, kind, reason, entityId?) (production.service.ts) → trigger("schedule-inputs-changed", …) → Inngest event carbon/schedule.inputs.changed. kind ∈ ability | shift | employee-shift | work-center | location | reorder | people.

Two Inngest functions listen on that event (packages/jobs/src/inngest/functions/scheduled/schedule-inputs-changed.ts):

  • MARK (markScheduleStaleFunction, immediate, concurrency 1 per company): stamps the affected jobs' scheduleOutdatedReason / scheduleOutdatedAt (scoped per kind — a qualification change in a shop with no gated ops stamps nothing; location / reorder stamp company-wide). A shift event with a shift id also stamps every job with an open op on a work center whose hours come from that shift (workCentersOnShift, shift-work-centers.ts: the stations linked to it, plus the stations at its location with no link to an active shift; lights-out stations never count), or on a process those stations run (processesOfWorkCenters: an unstarted op can move onto them). An unknown shift id stamps company-wide. createShift, updateShift and deleteShift send the id; an update that moves the shift to another location sends kind location instead, so the stations it left re-plan too. Changing a location's staffing requirement (updateProductionSettings) or its timezone (updateLocation, shifts are local times) also sends kind location, only when the value actually changed. Recomputes nothing.
  • WAVE (scheduleReplanWaveFunction, debounce 30s / timeout 10m, concurrency 1 per company): loads the company's stale jobs, groups them by LOCATION, and calls runLocationSchedule({ db: getJobDatabaseClient(), client: serviceRole, locationId, companyId, userId: "system" }) IN-PROCESS once per location — a whole-location regen (was serviceRole.functions.invoke("schedule", …)). Each engine run clears its own job's stale stamp (no wave-side flag-clearing). There is no pre-clear-reservations step, no batch slicing/chunking, and no chain-next-wave continuation. After the regens the wave sends one digest carbon/notify (NotificationEvent.JobsProjectedLate, documentIds = the newly-late job ids) per assignee; unassigned newly-late jobs are skipped in v1.

nightly-replan.ts (cron 0 1 * * *) is the time-passing backstop, and it now handles TWO staleness classes: (1) jobs still stamped schedule-outdated (the event path dropped them), AND (2) aged schedules — a stamp-aged-schedules step stamps any active job whose earliest open op startDate is before today (UTC-day threshold), because a forward plan anchored to an earlier day's now keeps DISPLAYING a past start until it re-anchors (placement itself always floors at now — it never schedules in the past). Both are then drained the same way: one carbon/schedule.inputs.changed (kind: "reorder", continuation: true) per company; the wave fans that out to the affected locations. NOTE: in local dev the Inngest worker (pnpm --filter @carbon/jobs dev:jobs) must be running or none of the reactive/nightly replan fires — a common cause of "my schedule went stale" / "my requiresAbility change didn't reschedule" locally (the change IS wired: processes.$processId.tsx fires notifyScheduleInputsChanged("ability", …, abilityId) on any requiresAbility flip, and the MARK function scopes to that ability's process ops).

Terminal-job reservation cleanup (20260819050906_cleanup-reservations-on-terminal-job.sql): an AFTER UPDATE OF status ON "job" trigger (delete_capacity_reservations_on_terminal_job, SECURITY DEFINER) deletes a job's live (scenarioId IS NULL) capacityReservation rows when it transitions to Cancelled/Completed/Closed. Reservations are a materialized output for active jobs only; before this, a cancelled/completed job's rows lingered as orphans (invisible to the forecast/capacity reads, which filter terminal jobs, but resurfacing as past-dated bars for any read that forgot the filter). The trigger is the one chokepoint every terminal path funnels through (the status route's updateJobStatus, and complete_job_to_inventory for Completed); SECURITY DEFINER because a cancel only holds production_update while the DELETE policy needs production_delete.

Other whole-location regen callers run runLocationSchedule(...) IN-PROCESS (no edge invoke): recalculateJobOperationDependencies (production.service.ts, resolves the job's locationId first, takes the caller's db handle and dynamic-imports @carbon/planning), releaseJobs (production.server.ts, once per location after every status flip), scanKanban (inventory.server.ts, a Make card's auto-release), api+/schedule.ts, and the jobs task tasks/recalculate.ts. The expedite what-if uses runExpediteWhatIf. rescheduleJob (production.service.ts, the reschedule posting) is a separate per-job backward re-plan, not a whole-location regen.

Engine pipeline (scheduling-engine.ts run())

initialize → assignMaterials → createDependencies → calculateDates → computeNeedBys → selectWorkCenters → calculatePriorities → buildWrites (the engine writes nothing; the location run stores the result, the expedite what-if drops it). There is no backward JIT pass in PLACEMENT and no initial/reschedule mode split — everything places FORWARD-ASAP, and the projected finish IS the overdue forecast (slack is real). The backward need-by pass (computeNeedBys, below) computes demand-anchored TARGETS only; its output is read by nothing in the placement path (spec .ai/specs/2026-08-15-dual-dates-due-vs-projected.md).

  • Whole-location, deterministic run (run-schedule.ts, called by every Node caller): one now is captured once and shared across every job in the batch. The location's open jobs (Ready | In Progress | Paused) are ordered deadline class first (DEADLINE_PRIORITY: ASAP → Hard Deadline → Soft Deadline → No Deadline), then dueDate ASC NULLS LAST → job.priority ASC → createdAt ASC — so a no-due-date ASAP order claims capacity first. Each job's engine run excludes the jobs not yet run (itself + later) from the reservation snapshot, so it sees non-batch reservations plus the placements of already-run jobs → sequential capacity claiming, no pre-clear step. Nothing is written while the jobs run. The engine only computes: engine.getWrites() returns a JobWrites (run-overlay.ts), provider.recordJob(writes) makes that job's reservations and operation placements visible to the jobs after it (beginRun reads the live reservations once; the rules are the pure visibleReservations / mergeCrossJobOperations), and persistLocationWrites (persist-location.ts) stores the whole location in ONE transaction at the end. A job that throws while computing is left out of the write and keeps its stored reservations visible to later jobs; a database error in the write rolls the location back and runLocationSchedule throws. This replaced a write per job (about 17 statements each, 500 for a 28-job location).
  • Sequencing (dependency-manager.ts): the jobOperation."operationOrder" enum (methodOperationOrder = 'After Previous' | 'With Previous') decides serial vs parallel, plus assembly edges (a sub-make-method's last op feeds the parent's consuming op); dependency-free ops are stamped operation-status Ready. That is operation-level status only — the engine is status-neutral for JOB status and never flips a job to Ready (release is the app's job-status flow).
  • Dates (date-calculator.ts → buildScheduledOperations): now just durations + pins — startDate/projectedCompletionAt start null and forward-ASAP placement fills them for EVERY op, pinned included. dueDate (the backward need-by target) also starts null and is seeded from storage only for a pinned/manuallyScheduled op, whose value the need-by pass takes as-is. Duration = setup + max(labor, machine).
  • Backward need-by pass (computeNeedBys() → computeNeedByDates in need-by-calculator.ts, pure): demand-anchored per-op TARGETS diff-written to jobOperation.dueDate every regen. Walk = reverse topological order from job.dueDate (null due date ⇒ all-null targets); leaves are due on the job due date; an op with dependents is due at the earliest dependent constraint — the dependent's need-by START minus that dependent's operationLeadTime working days. An assembly edge (a sub-make-method feeding its parent) subtracts NO item lead time: the subassembly's own ops are in the walk, so adding itemReplenishment.leadTime (default 7) counted the build twice per BOM level and put targets weeks before the job's start. "With Previous" ops copy their partner's target dates; a pinned op's stored dueDate is taken as-is AND propagates upstream. Day math runs on real calendars via calendarAdapters over the SAME availability-ladder windows placement uses (one shared loadAvailabilityWindows() fetch): calendarHoursPerDay(wc) sizes duration-in-days, workingDayTest skips that calendar's zero-hour days. HARD RULE: targets are outputs, never placement constraints — placement never floors/delays on op.dueDate (comments at the floor sites in work-center-selector.ts; determinism.test.ts pins placement invariance with/without the need-by pass; the one remaining read is the pinned OUTSIDE-PROCESSING passthrough, which keeps its stored window and chains successors after the pinned end). The pass also produces no conflict flags.
  • Finite placement (work-center-selector.ts): ops are placed in a deterministic topological order (topologicalPlacementOrder, Kahn's algorithm over the dependency edges; the ready set is ordered by jobOperation."order" then id). Each op is placed forward from max(now, placed-dependency-ends) — no backward-pass floor — into the first feasible span. Two finite resources gate it: the work center (capacity 1 — one op at a time, decided by actual capacityReservation intervals) AND, for ability-gated processes, ≥1 qualified employee on shift and unreserved. Only a started op is sticky (isOperationStarted, apply-work-center-selections.ts: status In Progress or Paused, or quantityComplete > 0): it stays on its workCenterId. An op that has not started gets earliest-finish selection across its process's work centers, even when it carries a work center (the stored one is the fallback when the process has no mapped centers). applyWorkCenterSelections then puts the chosen work center on a placed op that has not started, and placementWrites (run-overlay.ts) writes it, so jobOperation.workCenterId and the op's capacityReservation always name the same station. A started op and a placeholder keep the stored one; an op with no work center gets one either way. Consequence: a card dragged to another column on the operations board can move back at the next regen when another station finishes it earlier. A placement past the job's dueDate sets hasConflict/conflictReason but keeps the placement.
  • Machine availability windows come from the ladder resolved per work center in machine-availability.ts (resolveWorkCenterWindows) — the provider's getWorkCenterAvailability does the reads and buildFiniteContext sets each WC's windows: (1) workCenter.alwaysOn = one continuous 24×7 window (lights-out); (2) explicit workCenterShift rows; (3) the union of the work center's LOCATION's shift rows; (4) the stock Mon–Fri 08:00–16:00 (8h) week in the location tz (STOCK_WEEK_SHIFTS in calendar-utils.ts). Machine downtime is subtracted (calendar-utils.subtractIntervals) from those windows, derived from open maintenance dispatches flagged maintenanceDispatch.takesWorkCenterOffline (status not Completed/Cancelled; outage [actualStartTime ?? plannedStartTime ?? createdAt, actualEndTime ?? plannedEndTime ?? horizon) on the dispatch's workCenterId + its maintenanceDispatchWorkCenter rows) — no separate downtime table; completing the dispatch restores the hours at the next regen. People with no employeeShift rows now default to the job LOCATION's calendar (rung 3/4 via getLocationCalendarWindows), not 24×7.
  • Company holidays close the plant. The provider reads the company's holiday dates once per run (getHolidayDates). closeHolidays (machine-availability.ts) removes each holiday's whole day, in the plant timezone, from every work center that is not alwaysOn; a lights-out station keeps running. loadLocationCalendarWindows removes them from the location calendar, and buildFiniteContext adds each holiday as an absence for every person (withHolidays, people-utils.ts). The ERP reads the same dates (getHolidayDates, production.service.ts): the Forecast shades a holiday as closed, and the Capacity view shows 0 Available on it. Each Forecast lane is shaded and its bars split on its OWN station's hours (getWorkCenterNonWorkingIntervals → the Gantt's nonWorkingIntervalsByRow; rows under a lane inherit it, the location rollup is not split, operator-pool lanes keep the plant calendar, getForecastNonWorkingIntervals), so a lights-out station is never shaded. createHoliday, updateHoliday and deleteHoliday (people.server.ts) notify kind location.
  • A qualification ends at its expiry. isEligibleOperator tests an operator at the op's earliest start only. clipToQualification (operator-eligibility.ts) then cuts the operator's windows at the start of the expiresAt day in the plant timezone, and buildEligibleMembers drops an operator with no window left. Without the clip, an op that waited for its machine could be booked on a day after the qualification expired. The People board treats the expiry day as expired too (expiresAt <= date).
  • Attended-window labor model is UNCHANGED (slot-allocator.ts): ability gating, manning-board / team mode, attended windows, wait attribution, absence subtraction (peopleAbsence), overtime extension (peopleAssignment.overtimeHours), split-day budgets (peopleAssignment.hours), and manual pins behave exactly as before — a team still runs one op at a time with labor parallelized across present members, setup and machine time never compressed. Machine calendars only refine the model: member windows are clipped to the machine windows via intersectWindows, and the unattended remainder accumulates on the machine windows via addWorkingTime. A blank people board is byte-identical to pre-people behavior. One deliberate change: the gated any-qualified fallback (pass 2 in work-center-selector.ts) now treats a manning assignment as a whole-horizon COMMITMENT — the fallback relay may only draw on true FLOATERS: qualified people with NO board assignment anywhere in the horizon (assignmentsByEmployee.has(id), built from peopleByWorkCenter; on the finite context). A person manned ANYWHERE is spoken for and is never pulled to a station they weren't assigned to. So moving your only qualified operator off a station makes that station's op an in-window unschedulable placeholder (surfaced on the Forecast), rather than double-booking the operator OR shoving the op onto the unmanned nights/weekends a per-date clip would leave open (the bug an earlier per-date version caused — the op landed on a future Saturday and fell out of the current-week view). Blank board => every qualified person is a floater => fallback unchanged. When people ARE qualified but every one is on the board elsewhere, the reason says so (composeNoFreeOperator: "No free operator for X: … assigned to other stations on the manning board"), the Forecast detail lists who is qualified and the stations the board has them at (getQualifiedPeopleByProcess), and the ability page warns how many operations of its process can't be scheduled (getAbilityScheduleImpact).
  • Require-staffing policy (location.requiresStaffing, 20260820151847_location-requires-staffing.sql; per-location, default false; edited on the Production settings page): when ON, the finite scheduler places work ONLY where an operator is manned. buildFiniteContext reads it (provider.getLocationRequiresStaffing) + the set of lights-out stations (provider.getAlwaysOnWorkCenterIds) and puts requiresStaffing on the context + alwaysOn on each capacity.workCenter. Two gates in work-center-selector.ts: a gated op's any-qualified floater fallback is skipped entirely (pass 1 assigned+qualified only); an ungated op's machine-only fallback is skipped too — EXCEPT on alwaysOn (lights-out) stations, which keep running unattended. An op with no manned coverage (and not lights-out) becomes an unschedulable placeholder on the Forecast. This is exactly how "route everything to the one staffed work center, nothing to the unstaffed ones during staffed periods" falls out — an unstaffed non-lights-out station has no way to place, so earliest-finish selection naturally routes to the staffed candidate. OFF => the fallbacks stay (pre-setting behavior, byte-identical). "Staffing defined for a period" is derived purely from manning-board presence — there is no separate resource-plan status entity.
  • Remaining-work netting (duration-calculator.remainingFractions): a started op reserves only the work left — labor + machine scaled by (1 − quantityComplete/operationQuantity) (clamped ≥ 0), setup counted done once any productionEvent exists on the op — anchored at now.
  • Priority = per-work-center dispatch sequence number (priority-calculator.ts): ops grouped by workCenterId, sorted by placed start date ascending (nulls last), tie-broken by job.priority then deadline type, then numbered 1, 2, 3…. The dispatch sequence IS the forward-ASAP placement order — one source of truth for what runs next. Boards sort by priority ascending. (Job-level job.priority is a separate fractional index set at job creation by calculateJobPriority.) There is no configurable dispatch-sequencing policy — the old per-work-center policy table, its rule enum, and the FIFO/EDD/SPT/… comparators were all removed; placement order is the only sequence.
  • persistLocationWrites (one transaction per location run; the expedite what-if never calls it) writes, for every op whose values changed (an is distinct from guard in the UPDATE, so a quiet regen writes no jobOperation or job row and queues no audit/search event), the forward placement's results — startDate (projected start, business day) + jobOperation.projectedCompletionAt (exact placed-end instant, timestamptz) + priority + workCenterId + conflict flags. dueDate is the backward need-by and is DIFF-written: only when the computed target differs from the stored value (a quiet regen touches zero dueDates), and never for a manuallyScheduled op — a human owns that target. It rebuilds the jobs' capacityReservation rows (one delete for all the run's jobs where scenarioId IS NULL, then bulk insert — a materialized OUTPUT, WorkCenter/Employee kinds); and writes job.projectedCompletionAt (= the max placed end, the forecast finish) while clearing scheduleOutdatedReason/scheduleOutdatedAt for each job. The engine's buildWrites also computes the newly-late flag (was on-time-or-unforecast before, now projected past dueDate on the location calendar) for the wave's digest. Every due-date judgement — need-by targets, lateness conflicts, newly-late, the behind-target sentence — reads committedDueDate (priority-calculator.ts): only a Hard or Soft Deadline job has one; the date left on an ASAP or No Deadline job (the job form hides it) is ignored.
  • Behind-target attribution (informational only): when the JOB's verdict is late, getCause() appends composeBehindTarget (conflict-messages.ts) — "First behind target: {op} (due X, projected Y)", the first op in topological order whose projected finish passes its need-by. It rides the job-level cause sentence (expedite dialog) and NEVER sets per-op hasConflict; the UI's amber behind-target states (BOP rows, ops-board ItemCard, MES operation detail) are computed from the two dates, not from conflicts.
  • Expedite what-if (expediteJobId): runs only the target job first with the WHOLE batch excluded from the snapshot (it claims capacity as if first), persist: false, and returns { projectedCompletionAt, cause } without touching the database.

Manual scheduling

jobOperation."manuallyScheduled" BOOLEAN NOT NULL DEFAULT false (20260525143721_manual-scheduling.sql — adds only this column). Under dual dates a pin means a human owns the need-by TARGET, not the placement: the backward pass takes the pinned op's stored dueDate as-is and derives upstream ops' targets from it (the pin propagates), and the location write never includes dueDate for a pinned op. Forward placement schedules pinned ops normally — the old frozen-window branch (reserve the pinned span, skip placement) was REMOVED with the dual-dates split, so a pinned op's startDate/projectedCompletionAt are re-projected every regen and may differ from its pin. The one exception is a pinned OUTSIDE-PROCESSING op, which skips placement and keeps its stored window (successors chain after the pinned end). Pins are set via setJobOperationDueDate (production.server.ts, sets manuallyScheduled) from OperationDueDatePicker on the BOP.

Conflict detection

jobOperation."hasConflict" BOOLEAN DEFAULT false + "conflictReason" TEXT (20251123000001_job-operation-conflicts.sql, plus index idx_job_operation_wc_priority on ("workCenterId","priority","status")). Conflicts come only from forward-ASAP finite placement: no feasible slot (machine capacity exhaustion, a work center with no resolved availability windows, missing/expired operator qualification, or calendar exhaustion — conflictReason names the cause), or a placement that finishes after the job's dueDate (the overdue verdict; jobDueDate is passed into the selector — the per-op need-by targets are NOT a lateness input and NEVER set hasConflict; an op behind its target only gets the informational amber state). Conflicts surface; scheduling never hard-fails. The read RPCs roll it up per job with BOOL_OR(...) so the board shows a red flag.

Unplaceable ops leave a placeholder (work-center-selector.ts best === null branch). An op that could not be placed at all (no qualified operator, no feasible slot, horizon-exhausted) has hasConflict/conflictReason stamped and a fallback work center — and now also emits a non-binding placeholder capacityReservation (isPlaceholder = true, 20260818044654_…): pinned at the op's earliest start (snapped forward to the fallback WC's next working window via nextWorkingInstant, so the marker never draws on a night/weekend the now anchor happened to fall in) for its work-content duration in calendar time, on the fallback WC. It exists so the Forecast (which is 100% reservation-driven) shows the op instead of the job silently ending after its last placeable op, and so job.projectedCompletionAt extends to it and successors chain after it (placedEndByOperation). It is deliberately NOT added to the in-run capacity.reservations blocking set, and getLiveReservations filters isPlaceholder IS NOT true, so it never holds the machine against other jobs or the next regen. The Forecast surfaces it with a red "can't be scheduled" alert (LuBan) in the TREE status column — via GanttEvent.data.isUnschedulable, set on BOTH the work-center lane (any unplaceable child) and the operation row, so it reports at the work-center level AND per operation (in a Compact lane the placeholders get their own bottom strip, overlapping ones merged into one "N can't be scheduled" chip, groupOverlaps); clicking either row opens the detail sidebar ("Unschedulable" chip + reason + "where it would run" explanation). Plus a separate "{n} can't be scheduled" header count. (Placed-but -LATE ops keep a real reservation, show the generic isError triangle, and are the "conflict" count.)

Read RPCs (display only; do not compute schedules)

get_active_job_operations_by_location(location_id, work_center_ids[])

Newest: 20261006021134_mes-hide-outside-processing.sql (excludes operationType = 'Outside Processing'; prior revisions: 20260905132037_job-operation-batching.sql added the batch columns and the membership-handoff floor rule, 20260818031629_dual-dates.sql added projectedCompletionAt TIMESTAMPTZ, 20260720121629_capacity-planning.sql added hasConflict/conflictReason, 20260531084723_rework-serial-flow.sql added quantityReworked/reworkId, 20260304000000 added operationDueDate). It feeds the MES Work Centers board, the ERP Priority board and the API tool production_getActiveJobOperationsByLocation. Outside Processing is filtered by TYPE, not by a null workCenterId: both boards' columns are work centers, so an outside operation holding a stale work center (left over from an in-house type) otherwise lands in that column for an operator to start. Pinned by supabase/tests/outside-processing-off-the-floor.test.sql. TS wrappers (identical): apps/mes/app/services/operations.service.ts getActiveJobOperationsByLocation and apps/erp/app/modules/production/production.service.ts. Returns 44 cols incl.: id, jobId, jobMakeMethodId, operationOrder (← jo."order"), priority, processId, workCenterId, description, setup/labor/machineTime+Unit, operationOrderType (← jo."operationOrder", serial/parallel enum), jobReadableId, jobStatus, jobDueDate, jobDeadlineType, jobCustomerId, customerName, parentMaterialId, itemReadableId, itemDescription, operationStatus ('Paused' if job paused), targetQuantity, operationQuantity, quantityComplete, quantityReworked, quantityScrapped, salesOrderId/LineId/ReadableId, assignee, tags, thumbnailPath, operationDueDate (← jo."dueDate", the need-by target), reworkId, hasConflict (COALESCEd, never null), conflictReason, projectedCompletionAt (← jo."projectedCompletionAt", the projected finish instant), processBatchable, jobOperationBatchId, batchReadableId. The ERP ops board (priority+/operations.tsx → ItemCard) and MES schedule loader map hasConflict/conflictReason onto Kanban items (red border + triangle tooltip on the ERP card); the dual dates drive the amber behind-target state (projected day > need-by). The same dual-dates migration also forks get_job_operation_by_id (newest was 20260721004140_operation-type-consolidation.sql) to add projectedCompletionAt for the MES operation detail.

get_jobs_by_date_range(location_id, start_date, end_date)

Newest: 20260720121629_capacity-planning.sql (PL/pgSQL RETURNS TABLE, not a view). TS wrapper getJobsByDateRange in apps/erp/app/modules/production/production.service.ts, consumed by apps/erp/app/routes/x+/priority+/dates.tsx loader. Filters jobs with non-null dueDate in range and status != 'Cancelled', ordered by dueDate. Returns 27 cols: id, jobId, status, dueDate, completedDate, deadlineType, customerId, customerName, salesOrderReadableId, salesOrderId, salesOrderLineId, itemId, itemReadableId, itemDescription, quantity, quantityComplete, quantityShipped, priority, assignee, tags, thumbnailPath, operationCount, completedOperationCount, hasConflict, jobMakeMethodId, scheduleOutdatedReason, projectedCompletionAt — the last two are new in the capacity-planning migration and drive the dates board's forecast/stale surfaces.

Key types / enums

  • methodOperationOrder: 'After Previous' | 'With Previous' (20240619095417_methods.sql).
  • jobOperationStatus: Canceled | Done | In Progress | Paused | Ready | Todo | Waiting.
  • deadlineType: No Deadline | ASAP | Soft Deadline | Hard Deadline.
  • Engine types (packages/planning/src/scheduling/types.ts): enum SchedulingStrategy { PriorityLeastTime, LeastTime, Random }. The SchedulingDirection / SchedulingMode types and the initial/reschedule/backward/forward plumbing are deleted — one uniform forward-ASAP rule.
  • ERP scheduling zod validators (apps/erp/app/modules/production/production.models.ts): scheduleOperationUpdateValidator, scheduleJobUpdateValidator.

Gotchas

  • The engine is forward-ASAP only — no backward pass, no Infinite mode. Every work center is finite (one op at a time) with real operating hours from the machine-availability ladder (workCenterShift → the location's shifts → stock Mon–Fri 8h, or alwaysOn = 24×7), minus maintenance-dispatch downtime. Qualified people's shifts only additionally gate ability-gated ops. The old "no work-center calendar / availability comes from people's shifts" claim is wrong now. So is the old "manually scheduled ops keep their window" claim: pinned ops are placed normally every regen (the pin owns only the need-by target; see § Manual scheduling).
  • jobOperation."order" (topo position) vs "operationOrder" (serial/parallel enum) are distinct columns — easy to confuse; the RPC surfaces them as operationOrder and operationOrderType respectively.
  • There is no scheduleStatus enum/column and no scheduledStart/estimatedEnd columns. Dual dates (20260818031629_dual-dates.sql): the forward projection goes into jobOperation.startDate (projected start day) + jobOperation.projectedCompletionAt (projected finish instant, timestamptz); jobOperation.dueDate is the backward demand-anchored need-by target (DATE, stable — changes only when the job due date, routing, or lead times change; a pinned op's is human-owned). The job-level forecast finish is job.projectedCompletionAt. Consumers that key urgency on op dueDate (MES queue sort, the People Capacity view's Demand buckets, get_picking_schedule ordering) are deliberately unchanged — they now honestly read "when work is needed", not the sim's last forecast. The MES operation view's "Due" header, Due Date card and overdue flag read the JOB's jobDueDate; the op target is shown under it as "Operation needed by …" and only drives the behind-target projection badge. Labelling the op target "Due" with the job's deadline icon read as the job being due weeks early. The MES Work Centers board cards follow the same rule: Item.dueDate is jobDueDate, so the "Due …" line, the overdue flag, the urgency border (getDueUrgency) and a collapsed batch's earliest member deadline all read the job's date, against the location's today from the loader rather than the device's day. The ERP Priority board still maps operationDueDate, since its card carries the behind-target badge. The urgency classifiers and both boards' batch reductions ignore an ASAP or No Deadline due date — only Hard and Soft Deadline carry one (deadlineRequiresDueDate), but an ASAP job can still hold a stale date. getJobPromiseDate returns job.projectedCompletionAt or null (its old max-op-dueDate fallback would now just echo the job due date and was removed).
  • Editing the ERP ops board (operations.update.tsx, reorderScheduleOperations) does NOT re-run the engine: it re-sequences workCenterId + priority, and notifies (notifyScheduleInputsChanged, kind work-center) only when a card changed work center. The dates board always notifies, and the debounced wave regenerates the whole location. A failed notify is logged and never fails the write. The MES board is display/drag-only.
  • The selector MUTATES each context's reservation arrays as it places, so the quote what-if runs every simulation on a cloneFiniteContext copy (quote-lead-time.ts) — reusing one context across quantities/scenarios would let earlier runs' placements bleed into later ones. One WorkCenterSelector instance is fine (it resets plannedReservations per call), but the CONTEXT must be cloned per run.