paths:

  • "packages/database/src/supersession-pick.ts"
  • "apps/erp/app/modules/production/production.service.ts"
  • "packages/planning/src/mrp/**"
  • "apps/erp/app/modules/inventory/supersession-pick.ts"
  • "apps/erp/app/modules/items/ui/Item/ItemSupersessionForm.tsx"

Item Supersession

"This part is being phased out, use its successor instead." One row per item in itemSupersession (PK is ("itemId") alone — not the usual composite), holding supersessionMode, successorItemId, successorEffectivityDate, discontinuationDate and conversionFactor (1 old = N new).

Authored at Part → Planning → Supersession (ItemSupersessionForm, rendered by x+/part+/$itemId.planning.tsx). The same card lists the parts that name this item as their successor ("Supersedes", from getItemSupersededBy) and has an Add Predecessor modal (predecessorSupersessionValidator, intent supersession-predecessor) that writes the row on the OLD item with this item as successor — a planner starts from the new BOM, so the rule must be authorable from the successor side. The row still lives on the predecessor; the engines need no reverse lookup.

upsertItemSupersession refuses a loop (A→B plus B→A, any length) with SUPERSESSION_CYCLE_CODE; the route surfaces it as a field error. Before this guard the redirect map silently dropped both entries and neither part ever swapped, which reads as "working" in a trial.

discontinuationDate only suppresses NEW purchase suggestions for the old part (purchasing-planning views); it never stops picking or production. It is optional for Consume First — that mode switches when stock runs out, not on a date.

Three consumers, three different questions

Do not assume one rule. Each answers something different, deliberately.

Consumer Source Question
MRP (runMrp, @carbon/planning — packages/planning/src/mrp/mrp.ts) live, every run what should we replenish (buy or make), and how should existing supply change?
Job creation (get-method) live at creation, then frozen what does this job consume? (a Consume First predecessor with stock at the job's location keeps its Pull from Inventory lines, bought or made — the item-level withoutStockedConsumeFirst filter in loadSupersessionRedirect is provisional and settleConsumeFirstLines applies the per-line whole-assembly rule after insert. A made predecessor's Make to Order line follows the same rule by becoming a Pull from Inventory line on the predecessor when its stock covers at least one whole assembly — a Make to Order line is built in the job and never consumes stock, so pulling it is the only way the old sub-assemblies get used; with no whole assembly in stock it swaps to the successor's method and is built)
Picking (inventory/supersession-pick.ts) live, at pick time what do we pull off the shelf?

A jobMaterial row is a snapshot. Editing a supersession afterwards never rewrites existing rows — but picking re-evaluates live, so the same job can be picked differently tomorrow. That split is intentional; don't "fix" it.

Mode gating — three modes redirect

REDIRECTING_MODES = { "Consume First", "Prefer New", "Stock Only" } (packages/database/src/supersession-pick.ts). Stock Only is "service reserve, no production use", so production demand moves to the successor like a phase-out mode; only the predecessor's OWN replenishment is reserve-governed (the planning views top it up to minimumReserveQuantity). Leaving it out made a job's BOM name the spares-only part and dropped the successor demand from purchasing. No Stock has no successor and never redirects.

The single most common way to set up a test that proves nothing — seed No Stock, or a two-row loop, watch nothing swap, conclude the feature works.

Picking is stock-aware on purpose (apps/erp/app/modules/inventory/supersession-pick.ts, mirrored by get_picking_schedule, migration 20260908211552). The supersession row is looked up by resolvePickRule: the row's OWN item's rule when its successor is the substitutedFromItemId (a line pulled back onto the predecessor — the column holds the successor), else the substitutedFromItemId's rule (a line swapped at creation — the column holds the predecessor), else the row's own. Keying on the material's own item alone found no row for a swapped line, so Consume First never consumed the predecessor for any job created after the effectivity date; trusting the column FIRST inverted the roles on a pulled-back line whenever the successor had a rule of its own (NEW → NEWER) and sent the pick back to NEW. The SQL's lateral ORDER BY encodes the same precedence.

Material still on the predecessor:

  • No Stock → skip
  • Stock Only → pick the successor (never the spares-only predecessor)
  • Prefer New → successor when effective, falling back to the predecessor while the successor has no warehouse stock and the predecessor does
  • Consume First → predecessor until it has no warehouse stock, then successor

Material swapped at creation (substitutedFromItemId set, quantity in successor units; effectivity is not re-checked — for Consume First this only happens when the predecessor had no stock at creation):

  • Consume First → predecessor while it has warehouse stock, then successor
  • Prefer New → successor, unless it has no stock and the predecessor does
  • anything else → successor

Pulling the predecessor converts the quantity by 1 / substitutionFactor. A row the BOM's successor pulled onto the predecessor carries the successor in substitutedFromItemId; resolvePickRule reads it as an unswapped line on the predecessor (see above), whether or not the successor has a rule of its own.

Whole assemblies. A unit that needs N of the part gets N of the SAME part — two of the old or two of the new, never one of each. Every Consume First consumer rounds the predecessor's usable on-hand DOWN to a multiple of the line's per-assembly quantity with consumableInWholeAssemblies(onHand, perAssembly) (packages/database/src/supersession-pick.ts; RoundingMode.Down exists for it). 2 per assembly and 3 on the shelf fits ONE assembly: 2 old, the rest new, and the odd part stays in stock. Units of one batch may differ from each other; a single unit never mixes. This came from a customer who would rather leave one old part on the shelf than fit a mismatched pair — the unit-level split before it did exactly that. A row's quantity is the per-assembly quantity in the row's own units; a row swapped at creation holds successor units, so the predecessor's per-assembly quantity is quantity / substitutionFactor (perAssemblyOld in generatePickingList and the SQL).

Partial stock. A job line is never split at creation: a Consume First line stays whole on the predecessor whenever it covers at least one assembly, and the job materials page shows "N in stock, for K assemblies; the remaining M will be picked as NEW" (consumeFirstByItemId in $jobId.materials.tsx, computed live from the row's on-hand, rounded as above). generatePickingList is where the split happens: it picks the predecessor for the whole assemblies the warehouse covers and the successor for the rest, as two pick lines on one material, and the page then shows the pick-based note instead. settleConsumeFirstLines (get-method, after every row of a job is inserted, all four flows) settles every Pull from Inventory line, bought or made. The decision per line is the pure settleConsumeFirstLine (packages/database/src/supersession-pick.ts, with buildConsumeFirstRules and the shared threshold keepsLineOnPredecessor), pinned by packages/database/src/supersession-pick.test.ts; get-method only loads stock and writes the row. Three cases — a row SWAPPED at creation from a Consume First predecessor that covers one assembly is reverted onto it with no provenance (the BOM named it; the provisional map swaps a made predecessor regardless of stock, for its Make to Order lines); a row on the successor with a predecessor that covers one assembly becomes the predecessor (substitutedFromItemId = the successor, substitutionFactor = 1 / factor); a row kept on a predecessor whose on-hand covers no whole assembly of it is pushed to the successor. The item-level withoutStockedConsumeFirst filter only asks "any stock" and is provisional; the settle pass is what applies the per-line rule. The job materials Order Status column (getJobMaterialShortfallByItem) nets a Consume First shortfall against the successor's on-hand and incoming supply in a second pass; ItemOrderStatus.substituteItemId tells the badge to say "In stock, the remainder as NEW" or "Order N × NEW for this job". The successor's own supply also drives the badge: getJobMaterialsOrderStatus loads PO lines and supply jobs for every substitute item that is not itself a material of the job, and getJobOrderStatusByMaterial reads a line's own item AND its substitute — so a job raised for the NEW remainder shows "Planned job" on the OLD line instead of no badge at all. The item planning tab's supply/demand list (api+/items.$id.$locationId.forecast.ts, getRedirectedOpenJobMaterials) applies the same split to open job material lines so the rows match the bars: the predecessor keeps what its on-hand covers, the successor lists the remainder "via ". hasWarehouseStock / the SQL EXISTS … GROUP BY storageUnitId HAVING SUM > 0 both count any single non-lineside bin (including the unassigned bin) with positive on-hand.

Lineside credit. Before anything is picked, material already at the operation's lineside bin is credited, and both the generator and the schedule use ONE definition (linesideCredit in @carbon/database/picked-consumption; get_lineside_credit in SQL): the material's OWN live pick lines to that bin (picked − returned, less the job's consumption of the item) plus whatever on-hand at the bin no LIVE job's live pick line claims — a claim is Σ(picked − returned) of a job's non-cancelled lines to the bin minus that job's consumption, and only jobs in Planned / Ready / In Progress / Paused hold claims (a finished job never consumes its leftover pick; a cancelled list's picked material is simply unclaimed). For a Consume First line the credit is taken in whole assemblies across predecessor AND successor (splitConsumeFirstPick, ERP supersession-pick.ts, tested) — one assembly of each already at the bin means nothing to pick — and the generator keeps a running unclaimedRemaining per (item, bin) so two materials in one list cannot credit the same stock. Consumption sees the same stock: getPickedBudgets takes the operation's lineside bin (getOperationLinesideBin) and adds the unclaimed on-hand of the line's item, its predecessor and its successor as budgets, and allocateAcrossBudgets takes a PREDECESSOR budget only in whole assemblies (perAssembly, the material's per-parent quantity), so a unit is never completed with one old and one new part out of the bin. The schedule hides an operation only while it is on an OPEN list (Draft / In Progress / Partial), not forever after a completed one, so a job whose quantity grows after picking gets a card for the remainder.

Inside generatePickingList the predecessor's stock test is the running balance (warehouseRemaining, seeded from getWarehouseOnHand and drawn down by every earlier line of the list) and nothing else — an || hasWarehouseStock fallback let a later line pick the predecessor in full after earlier lines had used it up, and never split. The "already staged at the op's lineside bin" check runs BEFORE the split, so material sitting at the machine neither charges the balance nor raises a successor line for nothing.

Make to Order lines. The row builders of itemToJob and itemToJobMakeMethod resolve a Make to Order child against consumeFirstOnHand (the second value loadSupersessionRedirect returns: the job-location on-hand of every MADE Consume First predecessor whose rule is effective) BEFORE the row is built: when consumableInWholeAssemblies(onHand, quantity) > 0 the row's methodType becomes Pull from Inventory on the predecessor, so it is inserted as a picked row — no jobMakeMethod is created (the insert interceptor keys on methodType), nothing is exploded, and picking splits it per unit like any other Consume First line. Otherwise swapMadeSubAssembly swaps it to the successor and explodes the successor's method. madeChildren is therefore derived from the BUILT rows' methodType, not the BOM lines' — the two are paired by index in the made-children loop, and a converted row must drop out of both. This is per unit, never per batch: a batch of five may use old sub-assemblies on three units and new on two, but one unit never mixes. Converting to Pull from Inventory (rather than splitting the line into a picked half and a built half) is what keeps it stable under recalculate, which rebuilds every line as per-assembly quantity × parent quantity and would inflate a split back to two full lines.

Picking never stages a Make to Order line (generatePickingList .neq("methodType", "Make to Order"), get_picking_schedule migration 20260908211552). The parent operation never consumes such a line from stock (issue's backflush skips it), so a pick only moved material to lineside that nothing would use. Since unassigned materials were attributed to the first operation of their method (20260720160557) every Make to Order sub-assembly was scheduled that way — visible as a second, phantom pick (old and new from the shelf) for a sub-assembly the job was already building as its successor.

settleConsumeFirstLines is scoped to the rows the calling flow just inserted (jobMaterialIds, collected at every jobMaterial insert of the four flows) and skips any row with issued quantity. Get Method on one sub-method rebuilds only that sub-method's rows; the job-wide read it started with rewrote lines on other sub-methods — some already issued in successor units. The moved row's quantities come from pullBackQuantities (packages/database/src/supersession-pick.ts), which is direction-agnostic despite its name: recover the source's target (estimatedQuantity − scrapQuantity on a Buy/Pick row), convert, and re-derive scrap at the TARGET item's rate — the rate the row now carries.

Cancelling a job (cancelJob, production.server.ts) sets it Cancelled, then returns the staged material, then cancelOpenPickingListsForJob cancels its lines on every open list and the lists that have no live line left; a list shared with other jobs stays open. get_picking_schedule ignores a cancelled LINE as well as a cancelled list, so a reopened job's operation returns to the schedule. Its Consume First predecessor stock test is the whole-assembly one (warehouse on-hand ≥ perAssemblyOld, migration 20260908211552); Prefer New keeps the any-bin test because it never splits.

The substituted pick line's note (ERP PickingListLines, MES picking route) says how many assemblies it covers — "8 × NEW in place of OLD, for 4 assemblies" — from the job material's quantity and factor; the select embeds jobMaterial(quantity, substitutionFactor, item(itemSupersession(conversionFactor))) for that. Only shown when it is a whole number.

Consumption follows what was picked

packages/database/src/picked-consumption.ts. A pick can bring a different part than the job material names (a Consume First split, a Prefer New fallback, a Stock Only redirect), and the material row is never rewritten after creation — so the consumers read the pick lines instead of the row:

  • getPickedBudgets — per picked item for one material: staged at lineside (Σ picked − returned over live lines) minus what the job has already consumed of that item (itemLedger "Job Consumption" rows for the job at the location), the lineside bin, and the line-units→item-units factor (pickFactor, from the supersession rule in either direction, else the row's substitutionFactor).
  • orderOldFirst — predecessors first, then the line's own item, then the rest. Partial completions therefore use up the old part before touching the new one.
  • allocateAcrossBudgets — spreads a line-unit quantity across the budgets; what no pick covered is returned as remaining and the caller falls back to the material's own item from its own bin (the pre-existing behaviour).

A budget is two pools, and only one is shared. own is the material's OWN live pick (scoped by jobMaterialId, so private to that material, at the bin its pick lines went to); unclaimed is what sits at the operation's lineside bin that no live job's pick claims, shared by every material of the operation. available is their sum. allocateAcrossBudgets attributes each take own-first (fromOwn / fromShared), recordSharedTakes accumulates ONLY the shared portion per (item, bin) into a SharedTakes map, and getPickedBudgets subtracts that map from unclaimed alone. The backflush loops over every material of the operation before inserting its ledger rows, so without the map two materials sharing a picked item were both offered the same unclaimed stock; but recording the WHOLE take, keyed by item, let material A's private pick zero out material B's private pick, and B fell back to the warehouse while its staged stock sat at the machine. splitTakeByBin turns a take back into ledger rows — the own portion against the pick bin, the shared portion against the lineside bin — so a take that draws on both pools is never charged to one bin.

Used by issue (issueJobOperationMaterials completion backflush and partToOperation manual/step issue, negative adjustments only) and by post-picking (returnUntrackedMaterialRemainder holds owed back predecessor-first and returns the rest per item; maybeRestoreJobMaterialSource keeps the lineside pointer while any budget is still available). Pinned by packages/database/src/picked-consumption.test.ts.

Consumed-so-far is attributed per (job, item), not per material — two materials on one job sharing an item share one counter.

buildSupersessionRedirectMap — the shared builder

packages/database/src/supersession-pick.ts, used by MRP and get-method so both resolve a supersession by the same rules. It does NOT make their answers identical: each caller passes its own asOfDate (below), so a date-effective supersession can apply to one and not the other. Collapses A→B→C to A→C with the product of the factors.

  • Effectivity: !date || date <= asOfDate, lexicographic on YYYY-MM-DD (all three columns are DATE, so string order is chronological).
  • asOfDate differs by caller: MRP uses today in the company timezone; get-method uses the job's build date (jobBuildDate).
  • MRP nets a Consume First component's on-hand, bought or made. Top-level demand (Phase 4.5) draws the old item's on-hand down first; the BOM rewrite leaves every Consume First child on the old part and passes the rule to the engine as consumeFirstRedirect (packages/database/src/mrp-engine.ts), with the engine's starting on-hand for the old part overlaid from remainingConsumeFirstOnHand. When the engine reaches the old part it nets its running balance per contributor in whole assemblies (redirectConsumeFirstShortfall: each contributor is one parent's demand and carries perAssemblyQuantity, the IMMEDIATE parent's per-unit need stamped by the cascade — parentItemId is the root source's item and cannot answer that for a sub-sub-assembly — so a parent needing two per unit draws only multiples of two, at any depth) and moves the shortfall (× factor, stamped redirectedFromItemId) to the successor — in the old part's period, or EARLIER by the difference when the successor's lead time is longer (the parent needs it by the same date); never later, since the old part's period may already be floored at period[0]. The old part never explodes its own BOM; the successor is planned as itself at a deeper level — its BOM explodes for exactly the shortfall when it is Make, and it surfaces as a buy when it is Buy. The supersession is a synthetic edge in computeLowLevelCodes for that: a successor that also sits shallower in another BOM would otherwise be planned before the redirect reaches it. Phase 4.5 (demand on the old part ITSELF — its own sales lines and existing job lines) nets the same way through the shared netConsumeFirstContributors (packages/database/src/mrp-engine.ts): a Job Material contributor carries perAssemblyQuantity from openJobMaterialLines.quantityPerParent, so an open job line needing two per unit draws only multiples of two, and only the MOVED contributors are stamped onto the successor (before this every contributor was copied over at full quantity). Sales lines and projections have no per-assembly quantity and net by the unit. Pinned by packages/database/src/mrp-engine.test.ts.
  • The redirect also moves the ACTUAL demand rows. Phase 4.5 rewrites jobMaterialDemandByKey / salesDemandByKey in the same proportion it moves grossDemand, so demandActual (which get_purchasing_planning, get_production_planning and the item planning chart read) shows the predecessor with only what its stock covers and the successor with the rest in successor units. Before this, planning suggested buying the predecessor while the successor sat in stock.
  • Consume First walks its chain one hop at a time. The collapsed map (A→B→C to A→C) is right for Prefer New / Stock Only, where B is being skipped, but B's own shelf stock must be used before Consume First demand moves on. buildConsumeFirstHops (same file) maps each effective Consume First item to the NEXT Consume First item in its chain, collapsing only through non-Consume-First hops and multiplying their factors; a chain that never terminates is dropped. MRP passes every hop as consumeFirstRedirect (a middle hop gets demand only through the redirect and must still net its stock) and Phase 4.5 moves a Consume First shortfall to the hop, not the collapsed terminal. Job creation walks the same hops for a Make to Order line (firstStockedInConsumeFirstChain): the first item in the chain with a whole assembly in stock becomes the Pull from Inventory line, recorded as a swap when it is not the BOM's own item. With no stock anywhere in the chain and a BOUGHT successor (boughtSuccessors, the fourth value the loader returns: every redirect target whose effective replenishment is not Make), the line becomes a Pull from Inventory line on the successor — it is purchased — instead of falling through swapMadeSubAssembly (no make method on a bought item) to building the phased-out part. A Pull from Inventory line needs no walk — settleConsumeFirstLine already pulls it back onto any direct stocked predecessor of the item it landed on. Phase 4.5 iterates redirected items predecessor-first along the hops (redirectOrder), so a hop's own pass sees the demand, actuals and contributors its predecessor just moved onto it and splits them again; a moved contributor keeps its ORIGINAL redirectedFromItemId and has its perAssemblyQuantity converted by the factor.
  • Cycles are dropped, not collapsed. A two-row cycle (A→B plus B→A) is writable from the UI — only self-reference is blocked, by both the DB CHECK and the zod refine. Collapsing one produced A → A with the cycle's factor product, so an item superseded itself and its quantities were multiplied by garbage. The walk builds into a SECOND map; mutating in place made the result depend on iteration order. Pinned by packages/database/src/supersession-pick.test.ts.

get-method: four flows, one invariant

itemToJob, itemToJobMakeMethod, quoteLineToJob, jobToJob each build jobMaterial rows independently. Resolve the swap BEFORE any field derives from the item.

Building the row first and patching it afterwards is how itemScrapPercentage was left on the predecessor for years: the patch list was hand-written and the field was simply absent from it. All four now resolve itemId at the top of the row builder, so every derived field — scrap rate, bin, cost, tracking flags — follows automatically, including fields added later.

swapMadeSubAssembly is the exception: a made sub-assembly must be inserted before it can be re-exploded, so it genuinely patches. It restates item-derived fields by spreading itemDerivedJobMaterialFields() rather than listing them.

Made lines cascade target + scrap to their children, so a wrong scrap rate there under-explodes the entire sub-tree — every row below looks individually correct on a wrong base.

loadSupersessionRedirect is loaded once per request, before the transaction, in all four flows, and returns a SupersessionContext (packages/database/src/supersession-pick.ts: the collapsed redirect map, consumeFirstHops, consumeFirstOnHand, boughtSuccessors); resolveMadeLinePull(itemId, perAssembly, ctx) is the one decision for a Make to Order line — stocked chain hop first, then a bought successor, else null (build). supersessionMode is typed everywhere as the DB enum (Database["public"]["Enums"]["supersessionMode"], re-exported from the lib as SupersessionMode), never string. It pages with fetchAll + .order("itemId"); a bare select stops at PostgREST's 1000-row cap and would silently redirect a different subset than MRP.

Columns and what is visible

jobMaterial.substitutedFromItemId / substitutionFactor record provenance. methodMaterial has no equivalent — so jobToItem (Save Method) writes swapped items into the master BOM untraceably.

jobMaterial.itemScrapPercentage is NOT NULL, and recalculate only re-derives it when the stored value is NULL — which a NOT NULL column never is. A wrong scrap rate is permanent. It is surfaced by get_job_quantity_on_hand but rendered nowhere; the substitution indicator in JobMaterialsTable is the only supersession UI on a job.

Known gaps

  • quoteLineToJob and jobToJob never swap made sub-assemblies — documented as "a later layer". Fail-safe (you get the quoted/copied structure), but it disagrees with MRP, which has already redirected that demand.
  • A Make→Buy successor now becomes a Pull from Inventory line on the bought successor at job creation (see the chain paragraph above); the remaining fallthrough is a MADE successor whose make method isn't Active, or an item read failure — both leave the line on the predecessor, indistinguishably.
  • A Make to Order line pulled from a Consume First predecessor's stock is a Pull from Inventory line for the WHOLE quantity: the units the shelf does not cover are picked as the successor from stock, or planned by MRP (which nets the same predecessor stock and moves the shortfall to the successor). The job never builds the successor remainder itself. Splitting the line into a picked half and a built half would need recalculate's quantities engine to know about the split.
  • jobBuildDate falls back to UTC today when a job has neither start nor due date — which is the default creation path (No Deadline renders no due-date field). MRP uses the company timezone; this is where the shared-map guarantee breaks. Baselined in packages/checks/src/conformance/baseline.json.