On a plant floor, capacity is one resource

Everything above describes a system's capacity in aggregate. A plant does not have one. It has a sequence of resources, and its output is set by the slowest one in the current product mix — which moves when the mix moves.

Three consequences that do not follow from the aggregate view:

  • The utilization threshold applies per resource, not per plant. A plant at 70% overall with the press at 95% behaves like a plant at 95%. Aggregate utilization is the number most likely to be quoted and least likely to explain the queue.
  • Capacity added anywhere else produces inventory. Speeding up a feeding operation puts more work in front of the constraint. The line looks busier and ships the same.
  • The constraint is worth protecting, not optimizing. Time lost at the constraint is lost for the whole plant and cannot be recovered elsewhere. Keeping a deliberate buffer of work in front of it, and scheduling maintenance and changeovers around it, is worth more than a percentage point of its own efficiency.

Changeover time is capacity that looks like demand. A resource whose nominal rate covers the order book can still be short, because a third of its hours go to setups the schedule implies. When capacity looks adequate on paper and is not in practice, count the changeovers the sequence requires before adding a shift. operations:production-management covers the sequencing decision that sets that number.

Labor availability is a separate constraint from machine availability, and on most sites the binding one. Certified operators, shift coverage, and absence run on different arithmetic from equipment, and a plan built on machine hours alone will be wrong every time a qualified operator is out.