OpenProject is the leading open source project management software for product, project and portfolio management. A powerful Jira alternative with agile planning, issue tracking, roadmaps, Gantt charts, time tracking, collaboration features, and more. Available on premises or in the cloud. ⭐ Star us on GitHub
Ruby agile-developmentangularbcfboardsbug-trackerganttgantt-chartifcissue-trackerjira-alternativekanbanopenprojectproduct-managementproject-managementproject-planningroadmaprubyscrumtimelineworkflows
# frozen_string_literal: true
#-- copyright
# OpenProject is an open source project management software.
# Copyright (C) the OpenProject GmbH
#
# This program is free software; you can redistribute it and/or
# modify it under the terms of the GNU General Public License version 3.
#
# OpenProject is a fork of ChiliProject, which is a fork of Redmine. The copyright follows:
# Copyright (C) 2006-2013 Jean-Philippe Lang
# Copyright (C) 2010-2013 the ChiliProject Team
#
# This program is free software; you can redistribute it and/or
# modify it under the terms of the GNU General Public License
# as published by the Free Software Foundation; either version 2
# of the License, or (at your option) any later version.
#
# This program is distributed in the hope that it will be useful,
# but WITHOUT ANY WARRANTY; without even the implied warranty of
# MERCHANTABILITY or FITNESS FOR A PARTICULAR PURPOSE. See the
# GNU General Public License for more details.
#
# You should have received a copy of the GNU General Public License
# along with this program; if not, write to the Free Software
# Foundation, Inc., 51 Franklin Street, Fifth Floor, Boston, MA 02110-1301, USA.
#
# See COPYRIGHT and LICENSE files for more details.
#++
require "spec_helper"
require Rails.root.join("db/migrate/20241120095318_update_scheduling_mode_and_lags.rb")
RSpec.describe UpdateSchedulingModeAndLags, type: :model do
# Silencing migration logs, since we are not interested in that during testing
subject(:run_migration) do
perform_enqueued_jobs do
ActiveRecord::Migration.suppress_messages { described_class.new.up }
end
table_work_packages.map(&:reload) if defined?(table_work_packages)
end
shared_let(:author) { create(:user) }
shared_let(:priority) { create(:priority, name: "Normal") }
shared_let(:project) { create(:project, name: "Main project") }
shared_let(:status_new) { create(:status, name: "New") }
before_all do
set_factory_default(:user, author)
set_factory_default(:priority, priority)
set_factory_default(:project, project)
set_factory_default(:project_with_types, project)
set_factory_default(:status, status_new)
end
describe "journal creation" do
context "when scheduling mode is changed by the migration" do
let_work_packages(<<~TABLE)
subject | scheduling mode
wp already manual | manual
wp automatic | automatic
TABLE
it "creates a journal entry only for the changed work packages" do
expect(wp_already_manual.journals.count).to eq(1)
expect(wp_automatic.journals.count).to eq(1)
expect(wp_automatic.lock_version).to eq(0)
run_migration
expect(wp_already_manual.journals.count).to eq(1)
expect(wp_automatic.journals.count).to eq(2)
expect(wp_automatic.last_journal.get_changes)
.to include("schedule_manually" => [false, true],
"cause" => [nil, { "feature" => "scheduling_mode_adjusted", "type" => "system_update" }])
aggregate_failures "the journal author is the system user" do
journal = wp_automatic.last_journal
expect(journal.user).to eq(User.system)
end
aggregate_failures "the lock_version of the work package is incremented" do
expect(wp_automatic.lock_version).to be > 0
end
aggregate_failures "changes the updated_at of the work package" do
expect(wp_automatic.updated_at).not_to eq(wp_automatic.created_at)
expect(wp_automatic.updated_at).to be > wp_automatic.created_at
first_journal, last_journal = wp_automatic.journals
expect(wp_automatic.updated_at).not_to eq(first_journal.updated_at)
expect(wp_automatic.updated_at).to eq(last_journal.updated_at)
end
end
end
end
# spec from #59539, "Migration from an earlier version" section:
#
# > - For work packages with no predecessors (or with no relations at all), they will be
# > switched to manual scheduling.
context "for work packages with no predecessors nor children" do
let_work_packages(<<~TABLE)
subject | start date | due date | scheduling mode
wp automatic 1 | 2024-11-20 | 2024-11-21 | automatic
wp automatic 2 | | 2024-11-21 | automatic
wp automatic 3 | 2024-11-20 | | automatic
wp automatic 4 | | | automatic
wp manual 1 | 2024-11-20 | 2024-11-21 | manual
wp manual 2 | | 2024-11-21 | manual
wp manual 3 | 2024-11-20 | | manual
wp manual 4 | | | manual
TABLE
it "switches to manual scheduling" do
run_migration
expect(table_work_packages).to all(be_schedule_manually)
end
end
# spec from #59539, "Migration from an earlier version" section:
#
# > - Manually scheduled work packages remain so.
context "for manually scheduled work packages following another one" do
let_work_packages(<<~TABLE)
subject | start date | due date | scheduling mode | predecessors
main | | | manual |
wp 1 | 2024-11-20 | 2024-11-21 | manual | follows main
wp 2 | | 2024-11-21 | manual | follows main
wp 3 | 2024-11-20 | | manual | follows main
wp 4 | | | manual | follows main
TABLE
it "remains manually scheduled" do
run_migration
expect(table_work_packages).to all(be_schedule_manually)
end
end
# spec from #59539, "Migration from an earlier version" section
#
# > - If the successor is in automatic scheduling mode, has dates and some predecessors
# > have dates too:
# > - The successor remains in automatic mode
context "for automatically scheduled work packages following another one having dates" do
let_work_packages(<<~TABLE)
subject | start date | due date | scheduling mode | predecessors
pred with dates | 2024-11-19 | 2024-11-19 | manual |
pred without dates | | | manual |
wp 1 | 2024-11-20 | 2024-11-21 | automatic | follows pred with dates, follows pred without dates
wp 2 | | 2024-11-21 | automatic | follows pred with dates, follows pred without dates
wp 3 | 2024-11-20 | | automatic | follows pred with dates, follows pred without dates
wp 4 | | | automatic | follows pred with dates, follows pred without dates
TABLE
it "remains automatically scheduled" do
run_migration
expect([wp1, wp2, wp3, wp4]).to all(be_schedule_automatically)
end
end
# spec from #59539, "Migration from an earlier version" section
# > - If the successor is in automatic scheduling mode and has no dates
# > - The successor remains in automatic mode and continues to have no dates,
# > regardless of having predecessor with dates or not.
# > - If the successor is in automatic scheduling mode, has dates and none of the
# > predecessors have any dates
# > - The successor is switched to manual mode to preserve its dates and duration
context "for automatically scheduled work packages without dates following another one" do
let_work_packages(<<~TABLE)
subject | start date | due date | scheduling mode | predecessors
pred without dates | | | manual |
succ | | | automatic | follows pred without dates
TABLE
it "remains automatically scheduled and continues to have no dates" do
run_migration
expect(succ).to be_schedule_automatically
end
end
# spec from #59539, "Migration from an earlier version" section
#
# > - If the successor is in automatic scheduling mode, has dates and none of the
# > predecessors have any dates
# > - The successor is switched to manual mode to preserve its dates and duration
context "for automatically scheduled work packages following another one having no dates" do
let_work_packages(<<~TABLE)
subject | start date | due date | scheduling mode | predecessors
pred without dates | | | manual |
succ 1 | 2024-11-20 | 2024-11-21 | automatic | follows pred without dates
succ 2 | | 2024-11-21 | automatic | follows pred without dates
succ 3 | 2024-11-20 | | automatic | follows pred without dates
TABLE
it "switches to manual scheduling to preserve its dates and duration" do
run_migration
expect([succ1, succ2, succ3]).to all(be_schedule_manually)
end
end
# spec from #42388, "Migration from an earlier version" section
#
# > - Manually scheduled work packages remain so.
# > - If the relationship is parent-child, there are no changes to dates; the parent
# > remains in automatic mode.
context "for parent work packages" do
let_work_packages(<<~TABLE)
hierarchy | scheduling mode |
parent_automatic | automatic |
child1 | manual |
parent_manual | manual |
child2 | manual |
TABLE
it "keep their scheduling mode" do
run_migration
expect(parent_automatic).to be_schedule_automatically
expect(parent_manual).to be_schedule_manually
end
end
context "for 2 work packages following each other with distant dates" do
shared_let_work_packages(<<~TABLE)
subject | MTWTFSS | scheduling mode | predecessors
predecessor 1 | XX | manual |
follower 1 | XX | automatic | follows predecessor 1
# only start dates
predecessor 2 | [ | manual |
follower 2 | [ | automatic | follows predecessor 2
# only due dates
# if lag is already set, it's overwritten
predecessor 3 | ] | manual |
follower 3 | ] | automatic | follows predecessor 3 with lag 2
TABLE
it "sets a lag to the relation to ensure the distance is kept" do
run_migration
expect(follower1).to be_schedule_automatically
relations = _table.relations.map(&:reload)
expect(relations.map(&:lag)).to all(eq(3))
end
context "when there are non-working days between the dates" do
before do
# Wednesday is a recurring non-working day
set_non_working_week_days("wednesday")
# Thursday is a fixed non-working day
thursday = Date.current.next_occurring(:monday) + 3.days
create(:non_working_day, date: thursday)
end
it "computes the lag correctly by excluding non-working days" do
run_migration
expect(follower1).to be_schedule_automatically
relations = _table.relations.map(&:reload)
expect(relations.map(&:lag)).to all(eq(1))
end
end
end
context "for 2 work packages following each other with missing dates" do
let_work_packages(<<~TABLE)
subject | MTWTFSS | scheduling mode | predecessors
# only predecessor has dates
predecessor 1 | XX | manual |
follower 1 | | automatic | follows predecessor 1
# only successor has dates
predecessor 2 | | manual |
follower 2 | XX | automatic | follows predecessor 2
# none have dates
predecessor 3 | | manual |
follower 3 | | automatic | follows predecessor 3 with lag 2
TABLE
it "does not change the existing lag" do
run_migration
expect(follower1).to be_schedule_automatically
relations = _table.relations.map(&:reload)
expect(relations.map(&:lag)).to eq([0, 0, 2])
end
end
context "for a work package following multiple work packages" do
shared_let_work_packages(<<~TABLE)
subject | MTWTFSS | scheduling mode | predecessors
predecessor 1 | XX | manual |
predecessor 2 | XX | manual |
predecessor 3 | X | manual |
follower | XX | automatic | follows predecessor 1, follows predecessor 2, follows predecessor 3
TABLE
it "sets a lag only to the closest relation" do
run_migration
relations = _table.relations.map(&:reload)
expect(relations.map(&:lag)).to eq([0, 2, 0])
end
end
end