OpenProject is the leading open source project management software for product, project and portfolio management. A powerful Jira alternative with agile planning, issue tracking, roadmaps, Gantt charts, time tracking, collaboration features, and more. Available on premises or in the cloud. ⭐ Star us on GitHub

docs/user-guide/time-and-costs/progress-tracking/README.md: fix % Complete value

Levin Du603fdc4b97ef
diff --git a/docs/user-guide/time-and-costs/progress-tracking/README.md b/docs/user-guide/time-and-costs/progress-tracking/README.md
index 9bc81e1b050..91a13a69590 100644
--- a/docs/user-guide/time-and-costs/progress-tracking/README.md
+++ b/docs/user-guide/time-and-costs/progress-tracking/README.md
@@ -98,8 +98,8 @@ When you add, edit, or remove a value for *Work*, *Remaining Work*, or *% Comple
When none of the three fields (% Complete, Work, or Remaining Work) have values set, the field you fill in first will determine how the others are calculated:
- If you enter % Complete only, no other fields will be automatically updated. Work and Remaining Work will remain empty.
-- If you enter Work only, Remaining Work will automatically match the Work value, and % Complete will be set to 100%. You can manually clear these values if needed.
-- If you enter Remaining Work only, Work will automatically match the Remaining Work value, and % Complete will be set to 100%. You can manually clear these values if needed.
+- If you enter Work only, Remaining Work will automatically match the Work value, and % Complete will be set to 0%. You can manually clear these values if needed.
+- If you enter Remaining Work only, Work will automatically match the Remaining Work value, and % Complete will be set to 0%. You can manually clear these values if needed.
**When one field is set**