Skip to content

OpenProject is the leading open source project management software for product, project and portfolio management. A powerful Jira alternative with agile planning, issue tracking, roadmaps, Gantt charts, time tracking, collaboration features, and more. Available on premises or in the cloud. ⭐ Star us on GitHub

[#64503] Allow users to enter negative lag https://community.openpro… (#19176)

Maya Berdygylyjova6542c385bee9
diff --git a/docs/user-guide/work-packages/work-package-relations-hierarchies/README.md b/docs/user-guide/work-packages/work-package-relations-hierarchies/README.md
index 8960adc1659..9fb82490633 100644
--- a/docs/user-guide/work-packages/work-package-relations-hierarchies/README.md
+++ b/docs/user-guide/work-packages/work-package-relations-hierarchies/README.md
@@ -58,7 +58,16 @@ You can select one of the following relations:
> [!TIP]
> Prior to 15.1, *Predecessor (before)* was called *Precedes*, and *Successor (after)* was called *Follows*.
-For the relations of type Predecessor/Successor, you can also define **Lag**, which is the minimum number of working days to keep in between the two work packages. The default setting for lag is 0 working days. You can always edit the *Description* and *Lag* fields at a later time.
+For the relations of type Predecessor/Successor, you can also define **lag**, which is the minimum number of working days to keep in between the two work packages. The default setting for lag is 0 working days. Lag can also be negative. Here are a few examples:
+
+- A lag of 0 means the successor starts one working day after the predecessor finishes.
+- A lag of 2 means the successor starts three working day after the predecessor finishes.
+- A lag of -1 means the successor starts on the same day the predecessor finishes.
+- A lag of -2 schedules the successor to start one working day before the predecessor finishes, and so on.
+
+Only working days are considered when calculating lag. For example, if the predecessor finishes on a Wednesday and Saturday/Sunday are non-working days, then a lag of -3 schedules the successor to start on the previous Thursday.
+
+You can always edit the *Description* and *Lag* fields at a later time.