Skip to content

OpenProject is the leading open source project management software for product, project and portfolio management. A powerful Jira alternative with agile planning, issue tracking, roadmaps, Gantt charts, time tracking, collaboration features, and more. Available on premises or in the cloud. ⭐ Star us on GitHub

[#58113] 14.6 Documentation: Progress reporting changes https://comm… (#16869)

Maya Berdygylyjovad63f5681005f
diff --git a/docs/system-admin-guide/manage-work-packages/README.md b/docs/system-admin-guide/manage-work-packages/README.md
index 168c7271043..1fd3a40e22d 100644
--- a/docs/system-admin-guide/manage-work-packages/README.md
+++ b/docs/system-admin-guide/manage-work-packages/README.md
@@ -11,11 +11,12 @@ Manage work packages in OpenProject.
## Overview
-| Popular Topics | Description |
-| ----------------------------------- | :----------------------------------------------------------- |
-| [Settings](work-package-settings) | Configure general work package settings and defaults, such as display options and more. |
-| [Types](work-package-types) | Create and manage work package types. |
-| [Status](work-package-status) | Create and manage work package status. |
-| [Workflows](work-package-workflows) | Create and manage workflows for work packages in OpenProject. |
-| [Custom actions](custom-actions) | Create custom actions for work packages (Enterprise add-on). |
-| [FAQs](work-packages-faq) | Frequently asked questions about work packages in OpenProject. |
+| Popular Topics | Description |
+| --------------------------------------------------- | :----------------------------------------------------------- |
+| [Settings](work-package-settings) | Configure general work package settings and defaults, such as display options and more. |
+| [Types](work-package-types) | Create and manage work package types. |
+| [Status](work-package-status) | Create and manage work package status. |
+| [Progress tracking](work-package-progress-tracking) | Manage work package progress reporting settings. |
+| [Workflows](work-package-workflows) | Create and manage workflows for work packages in OpenProject. |
+| [Custom actions](custom-actions) | Create custom actions for work packages (Enterprise add-on). |
+| [FAQs](work-packages-faq) | Frequently asked questions about work packages in OpenProject. |
diff --git a/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/README.md b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/README.md
new file mode 100644
index 00000000000..737abda115b
--- /dev/null
+++ b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/README.md
@@ -0,0 +1,44 @@
+---
+
+sidebar_navigation:
+ title: Progress tracking
+ priority: 965
+description: Manage Work package progress tracking.
+keywords: work package progress tracking, percentage complete, % complete
+---
+
+# Manage work package progress tracking
+
+To manage the settings for progress tracking in work packages, navigate to *Administration* → *Work packages* → *Progress tracking*.
+
+![Progress tracking settings under OpenProject administration](openproject_system_guide_progress_tracking_settings.png)
+
+## Progress calculation mode
+*Progress calculation mode* lets you select between *work-based* and *status-based* modes.
+
+- **Work-based mode**: *% Complete* is either set manually or is automatically calculated based on *Work* and *Remaining work*, if they exist. Please refer to [progress tracking user guide](../../../user-guide/time-and-costs/progress-tracking/#work-based-progress-reporting) for more details and calculation examples.
+- **Status-based mode**: you will have to define fixed % Complete values for each [work package status](../work-package-status), which will update automatically when team members update the status of their work packages.
+
+ > [!NOTE]
+ > When switching progress calculation mode from one to another, you will see a warning message.
+ >
+ > - Changing progress calculation mode from work-based to status-based will result in all existing *% Complete* values to be lost and replaced with values associated with each status. Existing values for *Remaining work* may also be recalculated to reflect this change. This action is not reversible.
+ >
+ > - Changing progress calculation mode from status-based to work-based will make the *% Complete* field freely editable. If you optionally enter values for *Work* or *Remaining work*, they will also be linked to *% Complete*. Changing *Remaining work* can then update *% Complete*.
+
+![Warning message when changing progress calculation mode in OpenProject administration](openproject_system_guide_progress_tracking_settings_warning_message.png)
+
+## Calculation of % Complete hierarchy totals
+
+*Calculation of % Complete hierarchy totals* lets you determine how the values of the *% Complete* will be calculated in work package hierarchies.
+
+- **Weighted by work**: The total *% Complete* will be weighted against the *Work* of each work package in the hierarchy. Work packages with no *Work* values are not included into the calculation.
+
+- **Simple average**: The total *% Complete* is calculated by averaging the *% Complete* values of all work packages, regardless of their *Work* values. *Work* is not factored into the calculation.
+
+## % Complete when status is closed
+
+*% Complete when status is closed* lets you chose what happens to % Complete when you close a work package (even in the work-based mode).
+
+- **No change** - if you select this option, the value of *% Complete* will not change even when a work package is closed.
+- **Automatically set to 100%** - if you select this option, work package will be considered complete when closed.
diff --git a/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings.png b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings.png
new file mode 100644
index 00000000000..2738d1497f5
Binary files /dev/null and b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings.png differ
diff --git a/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings_warning_message.png b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings_warning_message.png
new file mode 100644
index 00000000000..9b3896850bb
Binary files /dev/null and b/docs/system-admin-guide/manage-work-packages/work-package-progress-tracking/openproject_system_guide_progress_tracking_settings_warning_message.png differ
diff --git a/docs/system-admin-guide/manage-work-packages/work-package-settings/README.md b/docs/system-admin-guide/manage-work-packages/work-package-settings/README.md
index 356262c10f8..b45120bdbfa 100644
--- a/docs/system-admin-guide/manage-work-packages/work-package-settings/README.md
+++ b/docs/system-admin-guide/manage-work-packages/work-package-settings/README.md
@@ -14,31 +14,12 @@ To change basic settings for work package tracking in OpenProject, navigate to *
You can adjust the following:
1. **Allow cross-project work package relations**, i.e. that work packages created in one project can have relations to work packages in another project, for example parent-children work packages.
-
2. **Display subprojects work packages in main projects** by default. This way the work packages of subprojects will always be visible in the main project if a user has the corresponding role in the subproject to see work packages.
-
3. **Use current date as start date for new work packages**. This way the current date will always be set as a start date if your create new work packages. Also, if you copy projects, the new work packages will get the current date as start date.
-
-4. **Progress calculation** lets you pick between two modes for how the **% Complete** field is calculated for work packages.
- - **Work-based**: % Complete is automatically calculated based on Work and Remaining work values for that work package, both of which are then necessary to have a value for % Complete.
-
- - **Status-based**: you will have to define fixed % Complete values for each [work package status](../work-package-status), which will update automatically when team members update the status of their work packages.
-
- > [!NOTE]
- > When switching progress calculation mode from one to another, you will see a warning message.
- >
- > - Changing progress calculation mode from work-based to status-based will result in all existing *% Complete* values to be lost and replaced with values associated with each status. Existing values for *Remaining work* may also be recalculated to reflect this change. This action is not reversible.
- >
- > - Changing progress calculation mode from status-based to work-based will make % Complete a non-editable field whose value is derived from Work and Remaining work. Existing values for % Complete are preserved. If values for Work and Remaining work were not present, they will be required in order to change % Complete.
-
- ![Warning message when changing progress calculation mode in OpenProject administration](openproject_system_guide_work_package_settings_warning.png)
-
-
-
-5. **Default highlighting mode** (Enterprise add-on) defines which should be the default [attribute highlighting](../../../user-guide/work-packages/work-package-table-configuration/#attribute-highlighting-enterprise-add-on) mode, e.g. to highlight the following criteria in the work package table. This setting is only available for Enterprise on-premises and Enterprise cloud users.
+4. **Default highlighting mode** (Enterprise add-on) defines which should be the default [attribute highlighting](../../../user-guide/work-packages/work-package-table-configuration/#attribute-highlighting-enterprise-add-on) mode, e.g. to highlight the following criteria in the work package table. This setting is only available for Enterprise on-premises and Enterprise cloud users.
![default highlighting mode](openproject_system_guide_default_highlighting_mode.png)
-6. Customize the appearance of the work package lists to **define which work package attributes are displayed in the work package lists by default and in what order**.
+5. Customize the appearance of the work package lists to **define which work package attributes are displayed in the work package lists by default and in what order**.
Do not forget to save your changes with the green **Save** button at the bottom.
diff --git a/docs/system-admin-guide/manage-work-packages/work-package-settings/openproject_system_guide_work_package_settings.png b/docs/system-admin-guide/manage-work-packages/work-package-settings/openproject_system_guide_work_package_settings.png
index d2b4804e914..d5ca2938aec 100644
Binary files a/docs/system-admin-guide/manage-work-packages/work-package-settings/openproject_system_guide_work_package_settings.png and b/docs/system-admin-guide/manage-work-packages/work-package-settings/openproject_system_guide_work_package_settings.png differ
diff --git a/docs/user-guide/time-and-costs/progress-tracking/README.md b/docs/user-guide/time-and-costs/progress-tracking/README.md
index 74b992bdb42..9bc81e1b050 100644
--- a/docs/user-guide/time-and-costs/progress-tracking/README.md
+++ b/docs/user-guide/time-and-costs/progress-tracking/README.md
@@ -10,7 +10,9 @@ keywords: Progress tracking, estimated time, remaining time, work, % complete, p
OpenProject lets you track and monitor the progress of your work packages.
-> **Note:** Since OpenProject 14.0, the way progress is reported and calculated has changed significantly. Please read the documentation below to understand how OpenProject handles work and progress estimates.
+> [!IMPORTANT]
+> In OpenProject 14.0, the way progress is reported and calculated has changed significantly. Refer to [this blog article](https://www.openproject.org/blog/changes-progress-work-estimates/) to follow the changes.
+> **In OpenProject 14.6 some of the changes made in 14.0 were removed and updated**. Please read the documentation below and [this blog post](https://www.openproject.org/blog/updates-to-progress-tracking-in-14-6-based-on-user-feedback/) to understand how OpenProject handles work and progress estimates.
## Terms
@@ -22,7 +24,8 @@ OpenProject lets you track and monitor the progress of your work packages.
| Estimated time | Work |
| Remaining time | Remaining work |
->**Note**: You will still find the new attributes if you search using their older names (in the list of filters, for example).
+>[!NOTE]
+> You will still find the new attributes if you search using their older names (in the list of filters, for example).
## Units of measurement
@@ -50,27 +53,80 @@ The default setting is set to be 8 hours per day. Your administrator can change
OpenProject offers two modes for reporting progress:
-- **Work-based progress reporting** enables you to automatically derive progress based on the values you enter for Work and Remaining work
-- **Status-based progress reporting** allows you to assign fixed % Complete values to statuses, and automatically derive Remaining work based on the values for Work you can enter
+- **Work-based progress reporting** enables you to automatically derive progress based on the values you enter for Work and Remaining work. You can also manually enter a value for % Complete.
+- **Status-based progress reporting** allows you to assign fixed % Complete values to statuses, and automatically derive Remaining work based on the values for Work you can enter.
->**Note:** The administrator of your instance will have selected a mode for the entire instance. If you are an administrator, you can modify this by following our [admin guide on work package settings](../../../system-admin-guide/manage-work-packages/work-package-settings).
+> [!NOTE]
+> The administrator of your instance will have selected a mode for the entire instance. If you are an administrator, you can modify this by following our [admin guide on work package settings](../../../system-admin-guide/manage-work-packages/work-package-progress-tracking).
### Work-based progress reporting
-% Complete is an automatically calculated value that is a function of Work and Remaining work, unless % Complete is configured to be [set by status](#status-based-progress-reporting).
+In the work-based progress reporting mode % Complete can either be automatically calculated based on the values of Work and Remaining work, or entered manually.
+
+#### Manual values for % Complete
+
+If you you prefer to enter the values for % Complete manually, you can. You can do that in the table view and work package details view. Values for *Work* and *Remaining work* are not required to enter % Complete.
+
+> [!IMPORTANT]
+>
+> If you do not enter \*Work\* or \*Remaining work\*, the \*% Complete\* field will remain an independent, manually editable field and behave like it did prior to OpenProject 14.0.
+
+![Manually entering values for % Complete in OpenProject](openproject_user_guide_percentage_complete_manual.png)
+
+
+
+#### Automatic values for % Complete
+
+If you enter a value for *% Complete* and one other field (*Work* or *Remaining work*), the third one will automatically be derived based on the other two. This means that there can be one value (if % Complete is entered manually) or three values but never just two values.
>**% Complete** is work done (**Work** - **Remaining work**) divided by **Work**, expressed as a percentage. For example, if Work is set at 50h and Remaining work is 30h, this means that % Complete is _(50h-30h)/50h))_ = **40%**. Please note that these calculations are independent and unrelated to the value of **Spent time** (which is based on actual time logged).
-This means that for a work package to have a value for % Complete, both Work and Remaining work are required to be set. To make this link clear and transparent, clicking on *Work* or *Remaining work* to modify them will display the following pop-over:
+To make this link clear and transparent, clicking on *Work* or *Remaining work* to modify them will display the following pop-over:
![Work estimates and progress pop-over with work-based progress reporting](progress-popover-work-based-days.png)
This allows you to edit Work or Remaining work and get a preview of the updated % Complete value before saving changes. Changing any one field will automatically update the other two.
->**Note:** If you enter a value for Remaining work that is higher than Work, you will see an error message telling you that this is not possible. You will have to enter a value lower than Work to be able to save the new value.
->
+When you add, edit, or remove a value for *Work*, *Remaining Work*, or *% Complete*, and it affects another field, a helpful message will appear explaining what has changed and why.
+
+![Helpful hint on progress tracking calculation in OpenProject](openproject_user_guide_percentage_complete_calculation_hint.png)
+
+#### Calculation logic
+
+**When no field is set**
+
+When none of the three fields (% Complete, Work, or Remaining Work) have values set, the field you fill in first will determine how the others are calculated:
+
+- If you enter % Complete only, no other fields will be automatically updated. Work and Remaining Work will remain empty.
+- If you enter Work only, Remaining Work will automatically match the Work value, and % Complete will be set to 100%. You can manually clear these values if needed.
+- If you enter Remaining Work only, Work will automatically match the Remaining Work value, and % Complete will be set to 100%. You can manually clear these values if needed.
+
+**When one field is set**
+
+When one field is already set and you enter a value in a second field, the third field will be automatically calculated:
+
+- If Work is already set and you enter % Complete, Remaining Work will be automatically calculated.
+- If Remaining Work is already set and you enter % Complete, Work will be automatically calculated.
+- If you enter Remaining Work when Work is already set (or vice versa), % Complete will be automatically calculated.
+
+> [!NOTE]
+> If you enter a value for Remaining work that is higher than Work, you will see an error message telling you that this is not possible. You will have to enter a value lower than Work to be able to save the new value.
>Additionally, the value for Remaining work cannot be removed if a value for Work exists. If you wish to unset Remaining work, you need to also unset Work.
+> [!NOTE]
+> **If you enter a % Complete value of 100% when Remaining work has a value**, this will also result in an error, since Remaining work must be 0h when % Complete is 100%.
+
+**When all values are set**
+
+- **Increasing Work**: When you increase the value of Work, the same amount is added to Remaining Work (since the total Work has increased). This change also updates the % Complete accordingly.
+- **Decreasing Work**:
+ - If you decrease *Work*, *Remaining work* is lowered by the same amount.
+ - If you decrease *Work* by more than the current value for *Remaining work*, then *Remaining work* will be set to 0h and *% Complete* to 100%
+- **Changing Remaining work updates % Complete**
+- **Changing % Complete updates Remaining work**
+
+For more details and examples of progress tracking calculation please refer to this [blog article](https://www.openproject.org/blog/updates-to-progress-tracking-in-14-6-based-on-user-feedback/).
+
### Status-based progress reporting
Administrators can also switch to [status-based progress reporting mode](../../../system-admin-guide/manage-work-packages/work-package-settings/) for their instance.
@@ -89,7 +145,8 @@ In Status-based progress reporting mode, Work is not a required value. However,
This allows you to edit % Complete (by changing status) or Work and get a preview of the updated Remaining work before saving changes.
->**Note:** In the upcoming version, statuses cannot have an empty % Complete value in status-based progress reporting mode.When upgrading, all statuses that do not have a value will take the default value of 0%.
+> [!NOTE]
+> In the upcoming version, statuses cannot have an empty % Complete value in status-based progress reporting mode. When upgrading, all statuses that do not have a value will take the default value of 0%.
## Hierarchy totals
@@ -97,7 +154,20 @@ OpenProject will automatically show totals for Work, Remaining work and % Comple
![Hierarchy totals for Work, Remaining work and % Complete](hierarchy-totals-days.png)
-> **Note**: The total % Complete value of a hierarchy is a weighted average tied to Work. For example, a feature with Work set to 50h that is 30% done will influence the total of % Complete of the parent more than a feature with Work set to 5h that is 70% done.
+OpenProject offers two modes for calculating *% Complete* in hierarchy totals:
+
+- **Weighted by work**: The total % Complete value of a hierarchy is a weighted average tied to Work. For example, a feature with Work set to 50h that is 30% done will influence the total of % Complete of the parent more than a feature with Work set to 5h that is 70% done.
+
+ > [!TIP]
+ >
+ > Work packages without *Work* will be ignored.
+
+- **Simple average**: *Work* is ignored and the *total % Complete* is calculated as a simple average of the *% Complete* values from the direct work packages children in the hierarchy. The value used on each direct child for computing the average is its *total % Complete* value, or its *% Complete* value if it has no children, or 0% if its *% Complete* value is empty.
+
+> [!NOTE]
+> The administrator of your instance will have selected a mode for the entire instance. If you are an administrator, you can modify this by following our [admin guide on work package settings](../../../system-admin-guide/manage-work-packages/work-package-progress-tracking).
+
+
### Excluding certain work packages from totals
@@ -118,10 +188,12 @@ When switching from Work-based to Status-based mode, the previous value for %&nb
- If Work was previously set, it will be retained and Remaining work will be re-calculated based on the other two values
- If Work was previously empty, then Work and Remaining work will remain empty
+
+
## Status- to work-based
In Status-based mode, it is possible for work packages to have a % Complete value (defined by the status) without having values for Work or Remaining work. In other words, the Work and Remaining work can be empty.
-When switching to Work-based mode, OpenProject will retain the value for % Complete that was set with status. It can then be modified by putting in Work and Remaining work, thereby overwriting the previous value with a new computed value:
+When switching to Work-based mode, OpenProject will retain the value for % Complete that was set with status.
-![Work estimates and progress pop-over with only the previous % Complete value](progress-popover-percentage-complete-only.png)
+Changing progress calculation mode from status-based to work-based will make the *% Complete* field freely editable. If you optionally enter values for *Work* or *Remaining work*, they will also be linked to *% Complete*. Changing *Remaining work* can then update *% Complete*.
diff --git a/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_calculation_hint.png b/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_calculation_hint.png
new file mode 100644
index 00000000000..e537279c418
Binary files /dev/null and b/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_calculation_hint.png differ
diff --git a/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_manual.png b/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_manual.png
new file mode 100644
index 00000000000..9a050436251
Binary files /dev/null and b/docs/user-guide/time-and-costs/progress-tracking/openproject_user_guide_percentage_complete_manual.png differ