OpenProject is the leading open source project management software for product, project and portfolio management. A powerful Jira alternative with agile planning, issue tracking, roadmaps, Gantt charts, time tracking, collaboration features, and more. Available on premises or in the cloud. ⭐ Star us on GitHub

Allow editing the finish date in automatic scheduling mode

Henriette Dargef0c723ae43f3
diff --git a/app/components/work_packages/date_picker/date_form_component.rb b/app/components/work_packages/date_picker/date_form_component.rb
index 905d8ebd338..ae67d4894f5 100644
--- a/app/components/work_packages/date_picker/date_form_component.rb
+++ b/app/components/work_packages/date_picker/date_form_component.rb
@@ -157,12 +157,8 @@ module WorkPackages
end
def disabled?(name)
- if name == :duration
- if !@schedule_manually && @work_package.children.any?
- return true
- end
-
- return false
+ if name == :start_date && !@schedule_manually
+ return true
end
@disabled
@@ -196,7 +192,7 @@ module WorkPackages
"focus->work-packages--date-picker--preview#onHighlightField",
test_selector: "op-datepicker-modal--#{name.to_s.dasherize}-field" }
- if @focused_field == name
+ if @focused_field == name && !disabled?(name)
data[:qa_highlighted] = "true"
data[:focus] = "true"
end
diff --git a/app/components/work_packages/date_picker/dialog_content_component.html.erb b/app/components/work_packages/date_picker/dialog_content_component.html.erb
index 53fdc133812..91fd655f11d 100644
--- a/app/components/work_packages/date_picker/dialog_content_component.html.erb
+++ b/app/components/work_packages/date_picker/dialog_content_component.html.erb
@@ -5,6 +5,7 @@
controller: "work-packages--date-picker--preview",
"work-packages--date-picker--preview-date-mode-value": date_mode,
"work-packages--date-picker--preview-triggering-field-value": triggering_field,
+ "work-packages--date-picker--preview-schedule-manually-value": schedule_manually,
test_selector: "op-datepicker-modal" },
class: "wp-datepicker-dialog--content"
) do
diff --git a/app/components/work_packages/date_picker/form_component.html.erb b/app/components/work_packages/date_picker/form_component.html.erb
index e3cd37f7df1..1dc490678e9 100644
--- a/app/components/work_packages/date_picker/form_component.html.erb
+++ b/app/components/work_packages/date_picker/form_component.html.erb
@@ -105,6 +105,7 @@
ignore_non_working_days: work_package.ignore_non_working_days,
schedule_manually:,
is_schedulable: !disabled?,
+ minimal_scheduling_date:,
is_milestone: milestone?,
date_mode:,
start_date_field_id: "work_package_start_date",
diff --git a/app/components/work_packages/date_picker/form_component.rb b/app/components/work_packages/date_picker/form_component.rb
index 42c982b4577..63fc7f0299c 100644
--- a/app/components/work_packages/date_picker/form_component.rb
+++ b/app/components/work_packages/date_picker/form_component.rb
@@ -79,7 +79,7 @@ module WorkPackages
end
def disabled?
- !schedule_manually
+ !schedule_manually && (milestone? || work_package.children.any?)
end
def milestone?
@@ -95,6 +95,10 @@ module WorkPackages
def disabled_checkbox?
!schedule_manually && work_package.children.any?
end
+
+ def minimal_scheduling_date
+ schedule_manually ? nil : work_package.start_date
+ end
end
end
end
diff --git a/app/controllers/work_packages/date_picker_controller.rb b/app/controllers/work_packages/date_picker_controller.rb
index 7d37d70b53a..d1d45163c31 100644
--- a/app/controllers/work_packages/date_picker_controller.rb
+++ b/app/controllers/work_packages/date_picker_controller.rb
@@ -48,7 +48,7 @@ class WorkPackages::DatePickerController < ApplicationController
respond_to do |format|
format.html do
render :show,
- locals: { work_package:, schedule_manually:, params: params.merge(date_mode: date_mode).permit! },
+ locals: { work_package:, schedule_manually:, focused_field:, params: params.merge(date_mode: date_mode).permit! },
layout: false
end
@@ -120,10 +120,13 @@ class WorkPackages::DatePickerController < ApplicationController
# rubocop:enable Metrics/AbcSize
def update
+ wp_params = work_package_datepicker_params
+ wp_params = manage_params_for_automatic_mode(wp_params)
+
service_call = WorkPackages::UpdateService
.new(user: current_user,
model: @work_package)
- .call(work_package_datepicker_params)
+ .call(wp_params)
if service_call.success?
respond_to do |format|
@@ -162,12 +165,21 @@ class WorkPackages::DatePickerController < ApplicationController
trigger = params[:field]
+ # For automatic scheduling, we focus the due date initially and do not switch to start date after touching it
+ if !ActiveModel::Type::Boolean.new.cast(schedule_manually) && trigger != "duration"
+ return :due_date
+ end
+
# Decide which field to focus next
case trigger
+ when "startDate"
+ :start_date
when "work_package[start_date]"
handle_focus_order_for_fields(:start_date, :due_date)
- when "work_package[duration]"
+ when "work_package[duration]", "duration"
:duration
+ when "dueDate"
+ :due_date
when "work_package[due_date]"
handle_focus_order_for_fields(:due_date, :start_date)
else
@@ -249,9 +261,7 @@ class WorkPackages::DatePickerController < ApplicationController
def set_date_attributes_to_work_package
wp_params = work_package_datepicker_params
- if wp_params["schedule_manually"] == "false"
- wp_params = wp_params.without("start_date", "due_date")
- end
+ wp_params = manage_params_for_automatic_mode(wp_params)
if wp_params.present?
WorkPackages::SetAttributesService
@@ -308,4 +318,16 @@ class WorkPackages::DatePickerController < ApplicationController
alternative_field
end
end
+
+ def manage_params_for_automatic_mode(wp_params)
+ return wp_params if wp_params["schedule_manually"] != "false"
+
+ # For WP with children the dates are always fixed
+ return wp_params.without("start_date", "due_date") if work_package.children.any?
+
+ # the start should be preserved and will thus be send as a parameter
+ wp_params["start_date"] = work_package.start_date.to_s
+
+ wp_params
+ end
end
diff --git a/app/views/work_packages/date_picker/show.html.erb b/app/views/work_packages/date_picker/show.html.erb
index e15aebd024e..18df5d7e857 100644
--- a/app/views/work_packages/date_picker/show.html.erb
+++ b/app/views/work_packages/date_picker/show.html.erb
@@ -3,7 +3,7 @@
WorkPackages::DatePicker::DialogContentComponent.new(
work_package:,
schedule_manually:,
- focused_field: (params[:focused_field] || params[:field]).underscore.to_sym,
+ focused_field:,
triggering_field: params[:field].underscore.to_sym,
date_mode: params[:date_mode]
)
diff --git a/frontend/src/app/shared/components/datepicker/wp-date-picker-modal/wp-date-picker-instance.component.ts b/frontend/src/app/shared/components/datepicker/wp-date-picker-modal/wp-date-picker-instance.component.ts
index 0011800f5c6..0943a3acd81 100644
--- a/frontend/src/app/shared/components/datepicker/wp-date-picker-modal/wp-date-picker-instance.component.ts
+++ b/frontend/src/app/shared/components/datepicker/wp-date-picker-modal/wp-date-picker-instance.component.ts
@@ -258,7 +258,10 @@ export class OpWpDatePickerInstanceComponent extends UntilDestroyedMixin impleme
private isDayDisabled(dayElement:DayElement):boolean {
const minimalDate = this.minimalSchedulingDate || null;
- return !this.isSchedulable || (!this.scheduleManually && !!minimalDate && dayElement.dateObj <= minimalDate);
+ return !this.isSchedulable
+ || (!this.scheduleManually
+ && !!minimalDate
+ && dayElement.dateObj.setHours(0, 0, 0, 0) < new Date(minimalDate).setHours(0, 0, 0, 0));
}
/**
diff --git a/frontend/src/stimulus/controllers/dynamic/work-packages/date-picker/preview.controller.ts b/frontend/src/stimulus/controllers/dynamic/work-packages/date-picker/preview.controller.ts
index 60acf46cd7a..55b52f9ecb7 100644
--- a/frontend/src/stimulus/controllers/dynamic/work-packages/date-picker/preview.controller.ts
+++ b/frontend/src/stimulus/controllers/dynamic/work-packages/date-picker/preview.controller.ts
@@ -39,10 +39,12 @@ export default class PreviewController extends DialogPreviewController {
static values = {
dateMode: String,
triggeringField: String,
+ scheduleManually: Boolean,
};
declare dateModeValue:string;
declare triggeringFieldValue:string;
+ declare scheduleManuallyValue:boolean;
private timezoneService:TimezoneService;
private highlightedField:HTMLInputElement|null = null;
@@ -217,12 +219,11 @@ export default class PreviewController extends DialogPreviewController {
this.setDurationFieldValue(this.currentDuration);
this.doMarkFieldAsTouched('due_date');
}
+
this.currentStartDate = selectedDate;
this.setStartDateFieldValue(this.currentStartDate);
this.doMarkFieldAsTouched('start_date');
- if (this.currentDueDate) {
- this.highlightField(this.dueDateField);
- }
+
this.keepFieldValue();
}
@@ -235,12 +236,11 @@ export default class PreviewController extends DialogPreviewController {
this.setDurationFieldValue(this.currentDuration);
this.doMarkFieldAsTouched('start_date');
}
+
this.currentDueDate = selectedDate;
this.setDueDateFieldValue(this.currentDueDate);
this.doMarkFieldAsTouched('due_date');
- if (this.currentStartDate) {
- this.highlightField(this.startDateField);
- }
+
this.keepFieldValue();
}
@@ -448,12 +448,19 @@ export default class PreviewController extends DialogPreviewController {
return;
}
+ if (!this.scheduleManuallyValue) {
+ // Fix the start date to avoid that it gets changed accidentally
+ this.markTouched('start_date');
+ }
+
if (this.isBeingEdited('start_date')) {
this.untouchFieldsWhenStartDateIsEdited();
} else if (this.isBeingEdited('due_date')) {
this.untouchFieldsWhenDueDateIsEdited();
} else if (this.isBeingEdited('duration')) {
this.untouchFieldsWhenDurationIsEdited();
+ } else if (this.isBeingEdited('ignore_non_working_days')) {
+ this.untouchFieldsWhenIgnoreNonWorkingDaysIsEdited();
}
}
@@ -479,29 +486,47 @@ export default class PreviewController extends DialogPreviewController {
}
private untouchFieldsWhenDueDateIsEdited():void {
- if (this.isTouchedAndEmpty('start_date') && this.isValueSet('duration')) {
- // force start date derivation
- this.markUntouched('start_date');
- this.markTouched('duration');
- } else if (this.isValueSet('start_date')) {
+ if (this.scheduleManuallyValue) {
+ if (this.isTouchedAndEmpty('start_date') && this.isValueSet('duration')) {
+ // force start date derivation
+ this.markUntouched('start_date');
+ this.markTouched('duration');
+ } else if (this.isValueSet('start_date')) {
+ this.markUntouched('duration');
+ }
+ } else {
this.markUntouched('duration');
}
}
private untouchFieldsWhenDurationIsEdited():void {
- if (this.isTouched('start_date')) {
- if (this.isValueSet('start_date')) {
- this.markUntouched('due_date');
- } else if (this.isValueSet('due_date')) {
- this.markUntouched('start_date');
- this.markTouched('due_date');
+ if (this.scheduleManuallyValue) {
+ if (this.isTouched('start_date')) {
+ if (this.isValueSet('start_date')) {
+ this.markUntouched('due_date');
+ } else if (this.isValueSet('due_date')) {
+ this.markUntouched('start_date');
+ this.markTouched('due_date');
+ }
+ } else if (this.isTouched('due_date')) {
+ if (this.isValueSet('due_date')) {
+ this.markUntouched('start_date');
+ } else if (this.isValueSet('start_date')) {
+ this.markUntouched('due_date');
+ this.markTouched('start_date');
+ }
}
- } else if (this.isTouched('due_date')) {
- if (this.isValueSet('due_date')) {
- this.markUntouched('start_date');
- } else if (this.isValueSet('start_date')) {
+ } else {
+ this.markUntouched('due_date');
+ }
+ }
+
+ private untouchFieldsWhenIgnoreNonWorkingDaysIsEdited():void {
+ if (!this.scheduleManuallyValue) {
+ if (this.isTouched('duration')) {
this.markUntouched('due_date');
- this.markTouched('start_date');
+ } else if (this.isTouched('due_date')) {
+ this.markUntouched('duration');
}
}
}
diff --git a/spec/components/work_packages/date_picker/dialog_content_component_spec.rb b/spec/components/work_packages/date_picker/dialog_content_component_spec.rb
index 3dbbe2915ea..633b4fcea37 100644
--- a/spec/components/work_packages/date_picker/dialog_content_component_spec.rb
+++ b/spec/components/work_packages/date_picker/dialog_content_component_spec.rb
@@ -147,7 +147,7 @@ RSpec.describe WorkPackages::DatePicker::DialogContentComponent, type: :componen
it "shows the date form with disabled fields" do
expect(dialog_content).to have_field(I18n.t("attributes.start_date"), disabled: true)
- expect(dialog_content).to have_field(I18n.t("attributes.due_date"), disabled: true)
+ expect(dialog_content).to have_field(I18n.t("attributes.due_date"), disabled: false)
end
it "shows the banner 'The start date is set by a predecessor'" do
@@ -169,7 +169,7 @@ RSpec.describe WorkPackages::DatePicker::DialogContentComponent, type: :componen
it "shows the date form with disabled fields" do
expect(dialog_content).to have_field(I18n.t("attributes.start_date"), disabled: true)
- expect(dialog_content).to have_field(I18n.t("attributes.due_date"), disabled: true)
+ expect(dialog_content).to have_field(I18n.t("attributes.due_date"), disabled: false)
end
it "shows the banner 'The start date is set by a predecessor'" do
diff --git a/spec/features/work_packages/datepicker/datepicker_follows_relation_spec.rb b/spec/features/work_packages/datepicker/datepicker_follows_relation_spec.rb
index 48a337e89df..9b4f6733936 100644
--- a/spec/features/work_packages/datepicker/datepicker_follows_relation_spec.rb
+++ b/spec/features/work_packages/datepicker/datepicker_follows_relation_spec.rb
@@ -37,9 +37,10 @@ RSpec.describe "Datepicker logic on follow relationships", :js, with_settings: {
shared_let(:project) { create(:project, types: [milestone_type]) }
shared_let(:predecessor) do
create(:work_package,
- type:, project:,
- start_date: Date.parse("2024-02-01"),
- due_date: Date.parse("2024-02-05"))
+ type:,
+ project:,
+ start_date: Date.parse("2024-02-02"),
+ due_date: Date.parse("2024-02-06"))
end
let(:work_packages_page) { Pages::FullWorkPackage.new(follower) }
@@ -60,26 +61,35 @@ RSpec.describe "Datepicker logic on follow relationships", :js, with_settings: {
datepicker.expect_working_days_only true
datepicker.expect_automatic_scheduling_mode
- datepicker.show_date "2024-02-05"
- datepicker.expect_disabled Date.parse("2024-02-05")
- datepicker.expect_disabled Date.parse("2024-02-04")
- datepicker.expect_disabled Date.parse("2024-02-03")
- datepicker.expect_disabled Date.parse("2024-02-02")
+ datepicker.show_date "2024-02-06"
+ datepicker.expect_not_disabled Date.parse("2024-02-06")
+ datepicker.expect_not_disabled Date.parse("2024-02-05")
+ datepicker.expect_not_disabled Date.parse("2024-02-04")
+ datepicker.expect_not_disabled Date.parse("2024-02-03")
+ datepicker.expect_not_disabled Date.parse("2024-02-02")
datepicker.expect_disabled Date.parse("2024-02-01")
datepicker.toggle_working_days_only
datepicker.expect_working_days_only false
- datepicker.expect_disabled Date.parse("2024-02-05")
- datepicker.expect_disabled Date.parse("2024-02-04")
- datepicker.expect_disabled Date.parse("2024-02-03")
- datepicker.expect_disabled Date.parse("2024-02-02")
+ datepicker.expect_not_disabled Date.parse("2024-02-06")
+ datepicker.expect_not_disabled Date.parse("2024-02-05")
+ datepicker.expect_not_disabled Date.parse("2024-02-04")
+ datepicker.expect_not_disabled Date.parse("2024-02-03")
+ datepicker.expect_not_disabled Date.parse("2024-02-02")
datepicker.expect_disabled Date.parse("2024-02-01")
end
end
context "if the follower is a task" do
- let!(:follower) { create(:work_package, type:, project:, schedule_manually: false) }
+ let!(:follower) do
+ create(:work_package,
+ type:,
+ project:,
+ schedule_manually: false,
+ start_date: Date.parse("2024-02-02"),
+ due_date: Date.parse("2024-02-06"))
+ end
let!(:relation) { create(:follows_relation, from: follower, to: predecessor) }
let(:date_field) { work_packages_page.edit_field(:combinedDate) }
@@ -87,7 +97,14 @@ RSpec.describe "Datepicker logic on follow relationships", :js, with_settings: {
end
context "if the follower is a milestone" do
- let!(:follower) { create(:work_package, type: milestone_type, project:, schedule_manually: false) }
+ let!(:follower) do
+ create(:work_package,
+ type: milestone_type,
+ project:,
+ schedule_manually: false,
+ start_date: Date.parse("2024-02-02"),
+ due_date: Date.parse("2024-02-06"))
+ end
let!(:relation) { create(:follows_relation, from: follower, to: predecessor) }
let(:date_field) { work_packages_page.edit_field(:date) }
diff --git a/spec/features/work_packages/datepicker/datepicker_logic_spec.rb b/spec/features/work_packages/datepicker/datepicker_logic_spec.rb
index e66fa8ad9c8..48d570f241b 100644
--- a/spec/features/work_packages/datepicker/datepicker_logic_spec.rb
+++ b/spec/features/work_packages/datepicker/datepicker_logic_spec.rb
@@ -1024,7 +1024,7 @@ RSpec.describe "Datepicker modal logic test cases (WP #43539)", :js, with_settin
end
end
- context "when setting 'Duration' and 'Working days only' of an automatically scheduled work package" do
+ context "when setting values of an automatically scheduled work package" do
let(:work_package) do
bug_wp.tap do |wp|
# add a predecessor so that automatic scheduling mode can be selected and date picker is visible.
@@ -1047,27 +1047,112 @@ RSpec.describe "Datepicker modal logic test cases (WP #43539)", :js, with_settin
}
end
- it "updates the finish date, instead of disappearing (Regression #61894)" do
- datepicker.expect_automatic_scheduling_mode
- datepicker.expect_due_date "2022-06-21", disabled: true
- datepicker.expect_duration 2
- datepicker.expect_working_days_only true
+ context "when changing 'Duration' and 'Working days only'" do
+ it "updates the finish date, instead of disappearing (Regression #61894)" do
+ datepicker.expect_automatic_scheduling_mode
+ datepicker.expect_due_date "2022-06-21", disabled: false
+ datepicker.expect_duration 2
+ datepicker.expect_working_days_only true
- datepicker.set_duration 6
+ datepicker.set_duration 6
- # start date is 20 and Saturday and Sunday are non-working days, so finish date is 27
- datepicker.expect_due_date "2022-06-27", disabled: true
+ # start date is 20 and Saturday and Sunday are non-working days, so finish date is 27
+ datepicker.expect_due_date "2022-06-27", disabled: false
- datepicker.uncheck_working_days_only
+ datepicker.uncheck_working_days_only
- # start date is 20, non-working days are ignored so finish date is 25
- datepicker.expect_due_date "2022-06-25", disabled: true
+ # start date is 20, non-working days are ignored so finish date is 25
+ datepicker.expect_due_date "2022-06-25", disabled: false
- apply_and_expect_saved start_date: Date.parse("2022-06-20"),
- due_date: Date.parse("2022-06-25"),
- duration: 6,
- ignore_non_working_days: true,
- schedule_manually: false
+ apply_and_expect_saved start_date: Date.parse("2022-06-20"),
+ due_date: Date.parse("2022-06-25"),
+ duration: 6,
+ ignore_non_working_days: true,
+ schedule_manually: false
+ end
+ end
+
+ context "when changing 'Due date'" do
+ it "can change it via the input field" do
+ datepicker.expect_automatic_scheduling_mode
+ datepicker.expect_due_date "2022-06-21", disabled: false
+ datepicker.expect_duration 2
+ datepicker.expect_working_days_only true
+
+ datepicker.set_due_date "2022-06-27"
+
+ datepicker.expect_duration 6
+
+ datepicker.uncheck_working_days_only
+
+ # Since the due date was touched before, the value is kept and duration adjusted
+ datepicker.expect_due_date "2022-06-27", disabled: false
+ datepicker.expect_duration 8
+
+ apply_and_expect_saved start_date: Date.parse("2022-06-20"),
+ due_date: Date.parse("2022-06-27"),
+ duration: 8,
+ ignore_non_working_days: true,
+ schedule_manually: false
+ end
+
+ it "can change it via the datepicker field" do
+ datepicker.expect_automatic_scheduling_mode
+ datepicker.expect_due_date "2022-06-21", disabled: false
+ datepicker.expect_due_highlighted
+ datepicker.expect_duration 2
+ datepicker.expect_working_days_only true
+
+ # The non-working days are disabled
+ datepicker.expect_not_disabled Date.parse("2022-06-25")
+ # The rest is not disabled
+ datepicker.expect_not_disabled Date.parse("2022-06-27")
+
+ datepicker.set_date Date.parse("2022-06-27")
+
+ datepicker.expect_duration 6
+
+ datepicker.uncheck_working_days_only
+
+ # Since the due date was touched before, the value is kept and duration adjusted
+ datepicker.expect_due_date "2022-06-27", disabled: false
+ datepicker.expect_duration 8
+
+ apply_and_expect_saved start_date: Date.parse("2022-06-20"),
+ due_date: Date.parse("2022-06-27"),
+ duration: 8,
+ ignore_non_working_days: true,
+ schedule_manually: false
+ end
+
+ it "can change duration as well while preserving the start date" do
+ datepicker.expect_automatic_scheduling_mode
+ datepicker.expect_due_date "2022-06-21", disabled: false
+ datepicker.expect_duration 2
+ datepicker.expect_working_days_only true
+
+ # Changing the due date will change the duration
+ datepicker.set_due_date "2022-06-27"
+ datepicker.expect_start_date "2022-06-20", disabled: true
+ datepicker.expect_duration 6
+
+ # Changing the duration afterwards, will change the due date again
+ datepicker.set_duration 7
+ datepicker.expect_due_date "2022-06-28", disabled: false
+ datepicker.expect_start_date "2022-06-20", disabled: true
+
+ # Changing the due date again, will again change the duration
+ datepicker.set_due_date "2022-06-27"
+ datepicker.expect_start_date "2022-06-20", disabled: true
+ datepicker.expect_duration 6
+
+ # Even unchecking the non working days will preserve the start date
+ # Since the due date was touched before, the value is kept and duration adjusted
+ datepicker.uncheck_working_days_only
+ datepicker.expect_due_date "2022-06-27", disabled: false
+ datepicker.expect_start_date "2022-06-20", disabled: true
+ datepicker.expect_duration 8
+ end
end
end
diff --git a/spec/features/work_packages/scheduling/automatic_scheduling_logic_spec.rb b/spec/features/work_packages/scheduling/automatic_scheduling_logic_spec.rb
index eccb9589c0e..4831029f802 100644
--- a/spec/features/work_packages/scheduling/automatic_scheduling_logic_spec.rb
+++ b/spec/features/work_packages/scheduling/automatic_scheduling_logic_spec.rb
@@ -151,7 +151,7 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
open_date_picker
datepicker.expect_automatic_scheduling_mode
datepicker.expect_start_date "2025-01-03", disabled: true
- datepicker.expect_due_date "2025-01-07", disabled: true
+ datepicker.expect_due_date "2025-01-07", disabled: false
datepicker.expect_duration "3"
end
end
@@ -174,7 +174,7 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
datepicker.expect_automatic_scheduling_mode
datepicker.expect_start_date "2025-01-03", disabled: true
- datepicker.expect_due_date "2025-01-07", disabled: true
+ datepicker.expect_due_date "2025-01-07", disabled: false
datepicker.expect_duration "3", disabled: false
apply_and_expect_saved(
@@ -204,7 +204,7 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
datepicker.expect_automatic_scheduling_mode
datepicker.expect_start_date "2025-01-20", disabled: true
- datepicker.expect_due_date "2025-01-22", disabled: true
+ datepicker.expect_due_date "2025-01-22", disabled: false
datepicker.expect_duration "3", disabled: false
apply_and_expect_saved(
@@ -327,7 +327,7 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
# parent gets properties from last removed child: child 2
datepicker.expect_automatic_scheduling_mode
datepicker.expect_start_date "2025-01-15", disabled: true
- datepicker.expect_due_date "2025-01-22", disabled: true
+ datepicker.expect_due_date "2025-01-22", disabled: false
datepicker.expect_duration "6"
datepicker.expect_working_days_only_enabled
datepicker.expect_working_days_only true
@@ -348,7 +348,7 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
# parent gets properties from last removed child: child 1
datepicker.expect_automatic_scheduling_mode
datepicker.expect_start_date "2025-01-15", disabled: true
- datepicker.expect_due_date "2025-01-19", disabled: true
+ datepicker.expect_due_date "2025-01-19", disabled: false
datepicker.expect_duration "5"
datepicker.expect_working_days_only_enabled
datepicker.expect_working_days_only false
@@ -435,28 +435,28 @@ RSpec.describe "Automatic scheduling logic test cases (WP #61054)", :js, with_se
# change dates in manual mode
datepicker.set_start_date("2025-01-06")
- datepicker.set_due_date("2025-01-08")
+ datepicker.set_due_date("2025-01-20")
datepicker.expect_start_date "2025-01-06"
- datepicker.expect_due_date "2025-01-08"
- datepicker.expect_duration "3"
+ datepicker.expect_due_date "2025-01-20"
+ datepicker.expect_duration "11"
# switch back to automatic
datepicker.toggle_scheduling_mode
datepicker.expect_automatic_scheduling_mode
- # dates should be derived from predecessors, and the duration is the
- # initial one despite the manual change
+ # start date should be derived from predecessors,
+ # while the changed finish date is kept and a new duration calculated
datepicker.expect_start_date "2025-01-17", disabled: true
- datepicker.expect_due_date "2025-01-17", disabled: true
- datepicker.expect_duration "1"
+ datepicker.expect_due_date "2025-01-20", disabled: false
+ datepicker.expect_duration "2"
expect(datepicker.container).to have_no_text(/Can only be set to ....-..-.. or later/i)
apply_and_expect_saved(
start_date: Date.parse("2025-01-17"),
- due_date: Date.parse("2025-01-17"),
- duration: 1,
+ due_date: Date.parse("2025-01-20"),
+ duration: 2,
schedule_manually: false
)
end